Introduction: Over the past few decades, there has been an increasing focus on Smart Building Projects (SBP) and the technologies associated with them. Numerous studies have been conducted globally to define smart building technologies (SBT), identify challenges, and explore areas for improvement. This study aims to examine the concept and terminology of SBT and the expertise and experience of participants in SBP in the Arab Gulf countries, specifically Saudi Arabia. The study also investigates the challenges faced by SBT throughout its life cycle.
Methods: To identify and assess the challenges affecting the adoption of smart building technologies. This approach included a literature review, pilot-testing, and a questionnaire survey. The survey targeted a sample of 90 architects/engineers, managers, and contractors.
Results: A total of 55 challenges were identified and categorized into four groups, corresponding to the key phases of the project life cycle. These phases include the programming and feasibility analysis phase, design phase, installation and commissioning phase, and operation and maintenance phase. The findings of this research expand the body of knowledge by providing architects/engineers, managers, and contractors in the architecture, engineering, construction, and facility management (AEC/FM) industry with insights into the influential challenges related to the adoption of SBT. In conclusion, this study sheds light on the concept and terminology of smart building technologies and explores the challenges faced by SBT during its life cycle. By identifying and categorizing these challenges, the study provides valuable information to AEC/FM practitioners, enabling them to overcome obstacles and improve the adoption of SBT.
1 Introduction
The purpose of buildings is to fulfill the requirements and preferences of their inhabitants, with an increasing focus on enhancing comfort within the living environment (). The planning of building systems holds a pivotal position in elevating user contentment and the overall standard of living (). Smart buildings, in particular, have surfaced as a method to enhance the efficiency, safety, and comfort of users’ lives (). The phrase “smart building” made its debut in 1981 when the United Technology Building Systems (UTBS) Corporation in the United States first introduced the concept. Their emphasis was on employing building automated systems (BMS) for the regulation of security and HVAC systems. A notable milestone occurred in 1983 with the construction of the City Place building in the United States, which was proudly marketed as the world’s inaugural intelligent building (; ). Essentially, a smart building integrates various systems such as HVAC, power management, lighting, security, safety, and shared networks to efficiently manage resources and enhance building performance (). It combines the best available technologies, designs, materials, and systems to improve occupants’ lives and provide cost-effective environments (). Smart buildings leverage technology to enhance building services and operations for the benefit of users (Ghansah et al., 2020). They aim to provide a dynamic infrastructure that optimizes energy efficiency, flexibility, cost, and comfort (). The concept of smartness in buildings encompasses characteristics such as green energy, zero emissions, space flexibility, population health, and working efficiency (). Smart buildings are described as equipped buildings with interconnected sensors, communication networks, and controllable devices (). They are also defined as flexible buildings that interact and connect with the ecosystem while generating and storing energy (). The aim of smart building technologies is to reduce energy consumption and improve comfort conditions and human welfare (; ).
Recent definitions of smart buildings focus on the adoption of structure connectivity solutions (SCS) to address various building systems, including security, data networking, and environmental control (). Designers of smart buildings should consider a range of smart building technologies and user characteristics, adopting a “respondents-oriented” approach (). However, the definition of intelligent buildings remains ambiguous, with diverse definitions across different countries (). Initially, early definitions primarily focused on automated functionalities, but subsequently, newer definitions have broadened their scope to encompass additional aspects. During the 1990s, the concept of smart buildings evolved to emphasize the integration of building occupants, intelligent systems, and environmental considerations to elevate the overall quality of life. Within the body of literature dedicated to smart buildings, there is a general consensus on three key defining characteristics: the incorporation of technology, the delivery of services, and the capacity to fulfill user requirements (; ; ). The core technologies of a smart building encompass hardware and software components, including sensors and home appliances. Sensors, whether physical devices or technological tools, detect changes in human behavior and environmental challenges (; ; ; ). By integrating sensors into household equipment and connecting them through wired or wireless systems, residents’ habits during activities such as watching television, cooking, sleeping, and cleaning can be observed and tracked (). The system, consisting of a variety of appliance and sensor configurations, facilitates a wide range of tailored tasks and services to meet the needs of the inhabitants (; ; ). A smart building can be defined as a dwelling equipped with sensors and connected domestic devices that form a communication network, providing lifestyle support (; ). In essence, a smart building integrates smart devices and sensors into an intelligent system that provides management, surveillance, assistance, and responsive services. This convergence yields a multitude of advantages spanning diverse areas, including the economy, society, health, emotional wellbeing, sustainability, and security, among others (; ).
In the last 30 years, numerous institutions around the world have undertaken comprehensive research to define and gain insight into smart building projects (SBPs) along with their fundamental principles and objectives (; ). Thus, this study aims to enhance the knowledge regarding the challenges and barriers that SBTs may face, providing valuable insights for stakeholders to promote effective SBT implementation in the big cities of the Arab Gulf ().
Sustainable and smart building is a growing trend that is catching on in public opinion and making its way into the agendas of researchers and city authorities worldwide. Indeed, 5G technology can significantly impact building construction, operation, and management by providing high-quality services and efficient functionalities. Singapore is one of the top smart cities in the world and among the first countries to adopt 5G technology in various sectors, including smart buildings. This article discusses the international trends in 5G applications for smart buildings, R&D, and test-bedding works conducted in 5G labs. It also reviews 5G technology development, use cases, applications, and future projects supported by the Singapore government. Lastly, the study discusses 5G use cases for smart buildings and building environment improvement applications. This research can serve as a benchmark for researchers and industries for future progress and development of smart cities in the context of big data ().
Large amounts of data are generated daily by sub-meters and smart sensors in residential buildings. Properly leveraging this data could help end users, energy producers, and utility companies in identifying unusual power consumption and understanding the causes of each anomaly ().
Currently, analyzing, detecting, and visualizing unusual power consumption patterns of households are some of the main challenges in finding ways to decrease power usage ().
Smart cities strive to achieve their net-zero emissions targets by minimizing wasted energy, enhancing grid stability, and fulfilling service demand. This is achievable by adopting advanced energy systems that utilize artificial intelligence, the Internet of Things (IoT), and communication technologies to gather and analyze large amounts of data in real time, thus efficiently managing city services. However, training machine learning algorithms to perform various energy-related tasks in sustainable smart cities presents a difficult data science challenge.
2 Research methodology
To examine the hindrances and possible remedies related to the adoption of smart building technologies, a research methodology was implemented, encompassing both qualitative and quantitative methodologies. This research approach encompassed the following steps: as shown in
1. Literature Review: To acquire an understanding of the challenges that smart building technologies encounter across their life cycle, a thorough examination of pertinent literature was conducted. In total, 55 challenges were pinpointed and sorted into four primary categories aligning with the various life cycle phases: programming and feasibility, design, installation and commissioning, and operation and maintenance.
2. Questionnaire Development: A Likert-scale questionnaire with five points was created to gauge the level of severity associated with the identified challenges. The term “severity” here denotes the influence of each challenge on the adoption of smart building technologies. A pilot test was executed, involving five participants from each relevant discipline, to assess the validity, comprehensiveness, and readability of the identified challenges. Subsequently, a questionnaire comprising 55 questions was formulated and distributed among professionals encompassing architects, engineers, constructors, facility managers, architects, and developers who are actively engaged in the domain of smart building projects in Saudi Arabia. The primary objective of this questionnaire was to delineate the principal challenges faced by smart building projects in Saudi Arabia.
3. Survey Administration: The pilot-tested questionnaire survey was administered to a targeted sample of 90 architecture/engineering/construction/facilities management (AE/C/FM) practitioners in Riyadh, Saudi Arabia. The sample comprised 30 architects/engineers (A/Es), 30 facilities managers, and 30 contractors. The selection of respondents was based on their years of experience and the nature of the projects they had been involved in. Table 1 provides an overview of the general information of the respondents.
4. Tabulation and Analysis: The relative challenging index (RCI) was calculated for each factor to determine its importance rating. The RCI is a percentage parameter based on a weighted mean, commonly used to quantify the significance of Likert-scaled questions (). It serves as an analytical method for prioritizing influential variables in professional practices, particularly in the construction industry (; ). In this research, the RCI was adopted to rank the challenges according to their relative importance as perceived by the respondents of the questionnaire survey. Both group and overall rankings were determined to identify the most important challenges within each group and across all groups of challenges.
FIGURE 1
TABLE 1
Parameter
A/Es Frequency (n = 30)
%
Contractors Frequency (n = 30)
%
Facilities managers Frequency (n = 30)
%
Years of experience
1–5 years
5
16.66
8
26.66
5
16.66
6–10 years
12
40.00
7
23.33
11
36.66
11–15 years
7
23.33
9
30.00
9
30.00
More than 15 years
6
20.00
5
16.66
5
16.66
Being involved in designing or constructing smart building systems
23
76.00
24
80.00
26
86.66
Profile of the AE/C/FM respondents.
Note(s): A/Es, Architects/Engineers.
Through the execution of this extensive research methodology, the study sought to collect valuable data concerning the obstacles related to the adoption of smart building technologies and to evaluate their level of severity as perceived by AE/C/FM practitioners in Riyadh, Saudi Arabia. Table 1 furnishes details about the demographic characteristics of the respondents, specifically architects/engineers (A/Es), contractors, and facilities managers. The data encompass the frequency and percentage of respondents in each category, stratified by their years of experience and their engagement in the design or construction of smart building systems (; ).
Figure 2 illustrates the dispersion of participants within each group categorized by their years of experience. It provides data on the count and proportion of respondents falling into various experience brackets, including 1–5 years, 6–10 years, 11–15 years, and over 15 years. Furthermore, the table also displays the percentage of respondents who indicated their involvement in the design or construction of smart building systems, which is notably high across all three groups ().
FIGURE 2
3 The literature review
The purpose of this article is to examine and evaluate the challenges that impact smart building technologies (SBTs) in the Arab Gulf States across their entire life cycle, spanning four crucial phases: the conceptual planning and feasibility study phase, the design and engineering phase, the construction phase, and the operation and maintenance phase (Pašek and Sojková, 2018). The following is a review of the existing literature and pilot testing; a total of 55 challenges that influence the adoption of smart buildings throughout their life cycle were identified. These challenges were categorized within the aforementioned four key phases, and their descriptions are presented in the following overview (Ahmed et al., 2021).
3.1 Challenges pertaining to the programming and feasibility analysis phase
The integration of smart building technologies can be affected by a range of challenges that arise during the programming and feasibility analysis phase. These 22 challenges have the potential to influence the decision-making procedures of stakeholders and organizations contemplating the adoption of smart building technologies. The following is an overview of the 22 challenges within the programming and feasibility analysis phase that have the potential to impact the adoption of smart building technologies:
A. The lack of a clear definition of smart buildings, a smart building is a structure that integrates advanced technologies and systems to enhance its performance, functionality, and sustainability (El-Motasem et al., 2021).
B. The lack of a clear taxonomy for smart buildings, a clear taxonomy for smart buildings, or the organization of their various components and subsystems, is currently lacking in the field (Alfalouji et al., 2023).
C. The lack of identified basic dimensions of smart buildings, the absence of identified basic dimensions of smart buildings contributes to the difficulty in defining and assessing their performance (Ejidike and Mewomo, 2023).
D. The lack of design standards of smart buildings, the lack of design standards for smart buildings can create challenges in the development and construction of these buildings (Aguilar et al., 2021).
E. The lack of sustainability measures for smart buildings, the lack of sustainability measures for smart buildings refers to the absence of clear and agreed-upon criteria for evaluating the environmental performance of smart buildings (El-Motasem et al., 2021, De Groote et al., 2017; Bibri, 2021; Ghansah et al., 2021).
F. The lack of automated evaluation schemes of smart building design, the lack of automated evaluation schemes for smart building design is an important challenge in the field (Ghaffarianhoseini et al., 2016).
G. The lack of knowledge and expertise of smart building systems, the lack of knowledge and expertise in smart building systems is a significant challenge that can hinder the successful implementation and operation of smart buildings (Zhao et al., 2021).
H. The lack of understanding of users’ needs for smartness, the lack of understanding of users’ needs for smartness in the context of smart buildings is a significant challenge that can impact the adoption and effectiveness of these technologies (Zhao et al., 2021).
I. The lack of historical databases of existing smart buildings’ performance, the lack of historical databases of existing smart buildings’ performance is indeed a challenge that can hinder the advancement and optimization of smart building technologies (Alanne and Sierla, 2022, Zhao et al., 2021).
J. The lack of regulations on a vision for achieving a specific level of smartness, the lack of regulations regarding a specific level of smartness for smart buildings is indeed a challenge that can impact the widespread adoption and integration of smart technologies (AlMuharraqi et al., 2022, Zhao et al., 2021).
K. Simplify technical jargon: Smart building technologies often come with complex technical terminology that can be overwhelming for consumers (Saad et al., 2022, Ghaffarianhoseini et al., 2016).
L. The lack of specialized and qualified suppliers and manufacturers for smart building systems, the lack of specialized and qualified suppliers and manufacturers for smart building systems is indeed a challenge that can hinder the widespread adoption and implementation of these technologies (Jacobsson, 2016, Li et al., 2020).
M. The cost of human technical expertise is relatively high over the benefits of smart buildings, smart buildings can come at a significant cost. Here are a few challenges that contribute to the relatively high cost: specialized skillset: designing, implementing, and maintaining smart building systems (Pašek and Sojková, 2018, Ghansah et al., 2020).
N. The total cost of ownership of smart buildings is unclear or relatively forecasted as a high investment, the total cost of ownership of smart buildings is unclear or relatively forecasted as a high investment due to several challenges.
O. The lack of motivational regulations on the choice and implementation of smart buildings, these buildings incorporate advanced technologies and design features that make them more energy efficient and environmentally sustainable (Sovacool and Furszyfer Del Rio, 2020).
P. The lack of provision of insights into smart building impacts (positive or negative) to policymakers, a lack of understanding may cause policy-makers to overlook the potential benefits and opportunities that smart buildings offer, resulting in missed opportunities to promote sustainability and energy efficiency.
Q. The insufficient basis of stating users’ needs and requirements, without information about users and requirements, it is hard for companies and designers to create products or buildings that meet their customers’ expectations.
R. The difficulty in forecasting the selected systems’ cycles of upgradeability and the changes of their technologies, it is important to choose systems that will last and be able to adapt to new technologies. However, it can be difficult to know exactly when and how these changes will happen, making it challenging to plan and budget for them.
S. Smart buildings are not self-sufficient; there are performance risks based on dependability on specific energy sources (no power, no smartness), if there is a disruption in the energy supply, the smart features in these buildings may not function properly. This can lead to decreased efficiency and potential issues.
3.2 Challenges pertaining to the design phase
In the process of implementing smart building technology, the design phase presents several challenges that demand careful attention. These challenges have the potential to affect the effective design and incorporation of smart building systems. The following is an overview of the 11 challenges typically associated with the design phase of smart building technology.
a. The lack of descriptive guidelines for the design of different systems in smart buildings, there may not be enough information or clear instructions on how to design the various systems in a smart building (Alsolami, 2022)
b. The technological lack of systems integration and interoperability capabilities, there may not be enough availability of resources or tools for making different systems work together and communicate with each other in smart buildings.
c. The lack of available visions of principal directions for the design thinking of smart buildings, this can make it difficult for architects and engineers to create a building that meets the needs and expectations of those who will use it.
d. The lack or absence of authoritative action plans to manage the design process of smart building projects, without these plans, it can be difficult to make sure that the building is designed in a way that meets the goals and requirements of the project.
e. The lack of measures to maintain the privacy and data security of users, there should be enough rules or systems in place to protect the personal information and privacy of those who use smart buildings.
f. The lack of regulations to maintain the privacy and data security of users, if there are not enough regulations to maintain privacy and data security, this could lead to unauthorized access to personal information, identity theft, and other serious issues.
g. The complexity of the design process, the complexity can also lead to increased costs and delays in the construction process. Having better resources and tools to simplify the design process would help make it easier to create smart buildings that meet all the necessary standards and requirements. (Ghaffarianhoseini et al., 2016, Kaklauskas et al., 2019)
h. The inability of specifying qualified and quality local manufacturers. Even if qualified and quality manufacturers are available, it can be challenging to find the right products for the building or the information and resources needed to identify and work with these local manufacturers. (El-Rashidy et al., 2021, Ejidike and Mewomo, 2023, Himeur et al., 2023)
i. The lack of distinguishing between the smartness requirements of owners, users, operators, and facility managers, the owners, users, operators, and facility managers may all have different ideas about what makes a building “smart” and how it should function.
j. The lack of understanding of the basis of design responsiveness of occupational health and safety precautionary measures from a technological point of view, many advanced technologies and systems in smart buildings can help keep the respondents safe and healthy, but designers and builders may not understand how to incorporate these technologies effectively (Alanne and Sierla, 2022).
k. The lack of specification of protection ratings and testing of systems, materials, and components, without standards for testing and rating the safety and protection of the systems, materials, and components used in smart buildings, it can be difficult to know whether the building and its various parts are safe and reliable. (Jacobsson, 2016, Kaklauskas et al., 2019)
3.3 Challenges pertaining to the installation and commissioning phase
The following is an overview of the 9 challenges commonly associated with the installation and commissioning phase in various industries:
a. Smart building projects are subject to scope variations that result in an excessive increase of budgets allocated, the accurate design of smart buildings is difficult, as is estimating the cost of the project and staying within budget. This can lead to delays and other complications.
b. Smart building projects are subject to variations that result in an excessive increase of time allocated, the construction and design of smart buildings often involve changes that can lead to an increase in the time allocated for the project. (Pramanik et al., 2019, Ahmed et al., 2021)
c. The lack of logistical support/logistical challenges for procuring smart systems, this indicates that logistical issues may make it difficult to procure the tools, supplies, and systems required for smart buildings. (Belani et al., 2014, Himeur et al., 2023)
d. The lack of experience in testing smart behaviors and systems, this indicates that the testing of intelligent systems and behaviors in intelligent buildings lacks knowledge and skill.
e. The lack of well-trained labor that can work on smart buildings, this indicates that there is a lack of trained and experienced professionals who can operate on smart buildings. (Hamida et al., 2022, Taktak, 2016)
f. The lack of systems’ compatibility with domestic utilities and national information and communication technologies and services, this implies that certain systems or equipment might not function properly with the country’s current technology and services. Users may find it challenging to use and link them appropriately as a result of this.
g. The lack of expertise, support services, and skills for installation and commissioning, it is important to make sure the technology is compatible with existing systems and that there are professionals with the right expertise to help with any installation and support.
h. The high costs of devices and installations, due to the high costs of devices and installations, purchasing and configuring the equipment required for smart buildings may be prohibitively expensive (Hamida et al., 2022, AlMuharraqi et al., 2022).
i. The requirement of high cash flow and financing for smart building projects, the start-up and completion of smart building projects may require significant funding. This might entail both having enough cash on hand and having the ability to borrow money if necessary (Hamida et al., 2022, Alanne and Sierla, 2022, AlMuharraqi et al., 2022).
3.4 Challenges pertaining to the operation and maintenance phase
There are several challenges that need to be considered. These challenges can impact the successful operation and maintenance of smart building systems.
a. The operations and maintenance costs (OPEX) are relatively high compared to regular buildings, it costs more to run and maintain smart buildings compared to regular buildings. This includes costs for aspects such as repairs and energy consumption.
b. The absence of operations and maintenance teams during early project phases means a lot of risks evolve during the operation and maintenance phase, during the initial phases of the project, a team should be in place to handle the maintenance and upkeep of smart buildings.
c. The need to reduce replacement cycles of systems, it is crucial to find solutions to extend the lifespan of the technology employed in these buildings if we want to limit the number of times that systems need to be replaced (Ghansah et al., 2020).
d. The lack of skilled and specialized maintenance and operation technicians, it is important to make sure there are enough skilled technicians available and to provide training and education to help them become specialized in this area. (Hamida et al., 2022, Alanne and Sierla, 2022, Alfalouji et al., 2023, AlMuharraqi et al., 2022, Balta-Ozkan et al., 2013, Holt, 2013)
e. Lack of ensured guaranties and warranties, this could make it difficult for the users to get help if something goes wrong or to be confident in the quality of the technology they are using.
f. There is a continuous change in operation and maintenance requirements, which affects systems’ effectiveness, for the systems to remain effective and efficient, they should be adapted and adjusted as needed to ensure they can still perform well even as changes occur.
g. Reliability (smart building systems must aim to be robust), to ensure the best possible reliability, there must be high-quality components, regular maintenance should be regularly performed, and systems should be closely monitored.
h. The changing demand for security that affects systems’ effectiveness, this has an impact on how well systems operate and perform. It is crucial to be flexible and modify systems as necessary to satisfy shifting security requirements.
i. The changing demand for privacy that affects systems’ effectiveness, this has an impact on the effectiveness of systems in various industries. There are increasing concerns about data protection and privacy regulations.
j. The changing functional requirements for controlling and monitoring capabilities, the changing functional requirements for controlling and monitoring capabilities refer to the evolving needs of organizations to manage and oversee their operations, products, and services (Himeur et al., 2023, Taktak, 2016, Attoue et al., 2018).
k. The social implications of the accessibility of smart technologies (e.g., elderly use of technologies, gender requirements), the social implications of the accessibility of smart technologies include improving the lives of elderly individuals and individuals with disabilities.
l. The lack of understanding of human–smart systems interactions and behaviors (involvement of virtual reality, augmented reality, and responsive intelligibility), the lack of understanding of human–smart systems interactions and behaviors, including the involvement of virtual reality, augmented reality, and responsive intelligibility, is indeed a complex challenge. (Jacobsson, 2016, El-Rashidy et al., 2021, De Groote et al., 2017)
4 Assessment of the challenges affecting the adoption of smart building technologies
4.1 Data collection
A questionnaire survey was created employing a five-point Likert scale to evaluate the significance of the 55 challenges, as detailed in Table 2. The participants, comprising AE/C/FM practitioners located in Riyadh City, Saudi Arabia, were tasked with assigning importance ratings to each of the factors. The rating options included “Extremely challenging” (4), “Very challenging” (3), “challenging” (2), “Somewhat challenging” (1), and “Not challenging” (0). The ratings were determined according to the perceived influence of each challenge on the capacity to adhere to project schedules, financial limitations, and investor anticipations related to work excellence. It was presumed that client requisites had already been addressed and integrated during the architectural programming phase, with an emphasis on the long-term robustness and excellence of the construction. The survey garnered responses from a total of 90 professionals, with equal representation from architects/engineers (A/Es), contractors, and facilities managers, with each group encompassing 30 respondents.
TABLE 2
No.
Challenges
References
G1
Challenges pertaining to the programming and feasibility analysis phase
1
The lack of clear definition of smart buildings
El-Motasem et al., (2021); Alfalouji et al., (2023)
2
The lack of clear taxonomy of smart buildings
Alfalouji et al. (2023)
3
The lack of identified basic dimensions of smart buildings
Ejidike and Mewomo (2023)
4
The lack of design standards of smart buildings
AlMuharraqi et al. (2022)
5
The lack of sustainability measures for smart buildings
Alsolami (2022)
6
The lack of automated evaluation schemes of smart building designs
Alsolami (2022)
7
The lack of knowledge and expertise of smart building systems
Roman et al. (2016)
8
The lack of understanding of users’ needs for smartness
Ghaffarianhoseini et al. (2016)
9
The lack of historical databases of existing smart buildings’ performance
McLauchlan et al. (2020)
10
The lack of historical feasibility assessments of smart building systems
Ejidike and Mewomo (2023)
11
The lack of regulations on a vision for achieving a specific level of smartness
El-Motasem et al. (2021)
12
The limited demand from consumers for smart buildings
Ejidike and Mewomo (2023)
13
The lack of awareness by consumers (e.g., designers, owners, and users) of the benefits of smart buildings
ASRIC (2021)
14
The lack of consumers’ (e.g., designers, owners, and users) awareness of the technical specifications of smartness
Alfalouji et al. (2023)
15
The lack of specialized and qualified suppliers and manufacturers for smart building systems
Pramanik et al. (2019)
16
The cost of human technical expertise is relatively high compared to the benefits of smart buildings
Bashir et al. (2022)
17
The total cost of ownership of smart buildings is unclear or relatively forecasted as a high investment
Ghansah et al. (2020)
18
The lack of motivational regulations on choice and implementation of smart buildings
Bashir et al. (2022)
19
The lack of provision of insights into capabilities of smart building impacts (positive or negative) to policymakers
Ghansah et al. (2021)
20
The insufficient basis of stating users’ needs and requirements
Ghaffarianhoseini et al. (2016)
21
The difficulty of forecasting the selected systems’ cycles of upgradeability and the changes of their technologies
Bibri (2021)
22
Smart buildings are not self-sufficient; there are performance risks based on dependability on specific energy sources (no power, no smartness)
Pramanik et al. (2019)
G2
Challenges pertaining to the design phase
1
The lack of descriptive guidelines for the design of different systems in smart buildings
Alsolami, (2022); El-Motasem et al. (2021)
2
The technological lack of systems integration and interoperability capabilities
Da Xu et al. (2014)
3
The lack of available visions for principal directions for design thinking of smart buildings
Alanne and Sierla (2022)
4
The lack or absence of authoritative action plans to manage the design process of smart building projects
Sathesh and Hamdan, (2021); El-Motasem et al. (2021); Da Xu et al. (2014)
5
The lack of measures to maintain the privacy and data security of users
Sathesh and Hamdan, (2021); Da Xu et al. (2014)
6
The lack of regulations to maintain the privacy and data security of users
El-Motasem et al. (2021), Salkuti, (2021)
7
The complexity of the design process
Salkuti, (2021); Da Xu et al. (2014)
8
The inability of specifying qualified and quality local manufacturers
Li et al. (2020)
9
The lack of distinguishing between the smartness requirements of owners, users, operators, and facility managers
Pašek and Sojková, (2018); AlMuharraqi et al. (2022); Attoue et al. (2018)
10
The lack of understanding of the basis of design responsiveness of occupational health and safety precautionary measures from a technological point of view
Ejidike and Mewomo, (2023); Bashir et al. (2022); Ibrhem et al. (2020)
11
The lack of specification of protection ratings and testing of systems, materials, and components
Ghaffarianhoseini et al. (2016); Gadakari et al. (2014); Bibri, (2021)
G3
Challenges pertaining to the installation and commissioning phase
1
Smart building projects are subject to scope variations that result in an excessive increase of budgets allocated
Alsolami, (2022); El-Motasem et al. (2021)
2
Smart building projects are subject to variations that result in an excessive increase of time allocated
AlMuharraqi et al. (2022); Alsolami, (2022); Alanne and Sierla, (2022); Aguilar et al. (2021)
3
The lack of logistical support/logistical challenges for procuring smart systems
Belani et al. (2014); El-Motasem et al. (2021); Ibrhem et al. (2020)
4
The lack of experience in testing smart behaviors and systems
El-Motasem et al. (2021); AlMuharraqi et al. (2022)
5
The lack of well-trained labor that can work on smart buildings
El-Motasem et al. (2021)
6
The lack of systems’ compatibility with domestic utilities and national information and communication technologies and services
Balta-Ozkan et al. (2013)
7
The lack of expertise, support services, and skills for installation and commissioning
Alfalouji et al. (2023)
8
The high costs of devices and installations
Alfalouji et al. (2023); Taktak, (2016)
9
The requirement of high cash flow and financing for smart building projects
Saad et al. (2022); Gadakari et al. (2014); Ejidike and Mewomo, (2023)
G4
Challenges pertaining to the operation and maintenance phase
1
The operations and maintenance costs (OPEX) are relatively high compared to regular buildings
Pašek and Sojková, (2018); Belani et al. (2014); El-Motasem et al. (2021)
2
The absence of operations and maintenance teams during early project phases means a lot of risks evolve during the operation and maintenance phase
Pašek and Sojková, (2018); Belani et al. (2014); El-Motasem et al. (2021)
3
The need to reduce replacement cycles of systems
Salkuti (2021)
4
The need to reduce replacement cycles of systems
Aguilar et al., (2021); Bibri, (2021); Bashir et al. (2022)
5
The lack of skilled and specialized maintenance and operation technicians
Pramanik et al. (2019); Alfalouji et al. (2023); De Groote et al. (2017)
6
The lack of ensured guaranties and warranties
Saad et al., (2022); Alsolami, (2022); El-Motasem et al. (2021); AlMuharraqi et al. (2022)
7
There is a continuous change in operation and maintenance requirements, which affects systems’ effectiveness
Ghaffarianhoseini et al. (2016); Belani et al. (2014)
8
There is a continuous change in users’ lifestyles and behaviors
Belani et al. (2014); Zhenxing et al. (2009)
9
Reliability (smart building systems must aim to be robust)
Da Xu et al., (2014); Da Xu et al. (2014); Zhenxing et al. (2009); Sathesh and Hamdan, (2021)
10
The changing demand for security that affects systems’ effectiveness
Ghaffarianhoseini et al. (2016); Da Xu et al. (2014)
11
The changing functional requirements for controlling and monitoring capabilities
Fabi et al. (2017a), Balta-Ozkan et al. (2013)
12
The social implications of the accessibility of smart technologies (e.g., elderly use of technologies, gender requirements)
Balta-Ozkan et al. (2013), Hoy, (2016), Salkuti (2021)
13
The lack of understanding of human–smart systems interactions and behaviors (involvement of virtual reality, augmented reality, and responsive intelligibility)
Belani et al. (2014); Ghansah et al. (2021)
Challenges facing the adoption of smart building technologies (SBTs) in previous studies.
4.2 Data analysis
The obtained data from the four groups of respondents were tabulated and analyzed, separately and collectively. The relative challenge index (RCI) was calculated for each factor, using the following equation (1):
Where:
i: Response category index.
a_i: Weight given to i response.
x_i: Variable expressing the frequency of (i).
To calculate the RCI, the appropriate values for the weights (a_i) and frequencies (x_i) need to be substituted into the equation. The weights (a_i) represent the importance or significance assigned to each response category, and the frequencies (x_i) represent the number of occurrences or observations for each category, as listed in Table 3 (Figure 3) (Sathesh and Hamdan, 2021; Jayasinghe et al., 2023; Attoue et al., 2018; So and Wong, 2002; Adelgren et al., 2012).
TABLE 3
Challenging rating
Weight (ai)
Scale (%)
Extremely challenging (x0)
4
87.5–100
Very challenging (x1)
3
62.5–87.5
Challenging (x2)
2
37.5–62.5
Somewhat challenging (x3)
1
12.5–37.5
Not challenging (x4)
0
0–12.5
The adopted weighting and scale of interpretation for each challenging rating.
FIGURE 3
The adopted weighting and scale of interpretation for each importance rating (Alsolami, 2022).
Based on the ranking of the challenges, the correlation among the three groups of respondents was analyzed to determine their level of agreement on the importance of the challenges. Spearman’s coefficient of rank correlation was used to determine the level of agreement on the importance of the challenges. The analysis of the agreement was performed through three-paired comparisons, namely, A/Es and contractors, A/Es and facilities managers, and contractors and facilities managers (Hamida et al., 2022). The following equation was used to calculate the Spearman’s coefficient of rank correlation: as shown in Table 4
TABLE 4
Paired comparisons
Interpretation of the level of correlation
A/Es and contractors
0.43
Moderate positive correlation
A/Es and facility managers
0.77
Moderate positive correlation
Facility managers and contractors
0.41
Moderate positive correlation
Correlation among the groups of respondents.
Where:
Spearman’s coefficient of rank correlation.
Sum of the squared differences in ranks of the paired comparison.
Number of parameters for which the ranking is made (Zhao et al., 2021).
A summary of Figures 4–7 showcasing the relative challenge index (RCI) as a percentage pertaining to different phases of smart building projects is provided. These phases encompass the programming and feasibility analysis phase comprising 22 challenges, the design phase comprising 11 challenges, the installation and commissioning phase comprising 9 challenges, and the operation and maintenance phase comprising 13 challenges. Over recent decades, smart building projects have garnered substantial attention, leading to a multitude of studies aimed at establishing global definitions for smart building technologies (SBTs), recognizing the challenges encountered, and identifying areas for enhancement. The study highlighted here centered on the examination of the concept and terminology associated with SBTs, in addition to the proficiency and hands-on experience of individuals engaged in smart building projects within Saudi Arabia. Moreover, the study sought to determine the features, challenges, and hindrances encountered by SBTs throughout their entire life cycle. While the specific challenges within the Figures are not specified, it can be inferred that the RCI reflects the relative level of complexity or challenge associated with each phase.
FIGURE 4
RCI of programming and feasibility analysis phase (Alsolami, 2022).
FIGURE 5
RCI of the design phase (Alsolami, 2022).
FIGURE 6
RCI of the installation and commissioning phase (Saad et al., 2022; Alsolami, 2022).
FIGURE 7
RCI of the operation and maintenance phase (Saad et al., 2022; Alsolami, 2022).
5 Findings and discussion
Table 5 illustrates the findings of the assessment. It presents the RCI, challenge rating, challenge group ranking, and overall ranking of each challenge.
TABLE 5
No.
Challenges affecting the adoption of smart building technologies in Saudi Arabia
A/Es
Contractors
FMs
Overall
RCI
CR
CGR
OR
RCI
CR
CGR
OR
RCI
CR
CGR
OR
RCI
CR
CGR
OR
Challenges pertaining to the programming and feasibility analysis phase
C1
The lack of clear definition of smart buildings
56.67
C
19
38
83.33
VC
3
6
69.17
VC
9
20
69.72
VC
9
20
C2
The lack of clear taxonomy of smart buildings
60.83
C
18
36
79.17
VC
5
11
72.5
VC
7
16
70.83
VC
7
18
C3
The lack of identified basic dimensions of smart buildings
45.83
C
21
48
66.67
VC
11
22
50.83
C
20
48
54.44
C
21
43
C4
The lack of design standards of smart buildings
54.17
C
20
41
65.83
VC
13
25
60
C
13
32
60
C
17
34
C5
The lack of sustainability measures for smart buildings
66.67
VC
16
30
66.67
VC
12
23
56.67
C
17
37
63.34
VC
14
28
C6
The lack of automated evaluation schemes of smart building design
68.33
VC
14
23
72.5
VC
8
17
56.67
C
18
38
65.83
VC
11
23
C7
The lack of knowledge and expertise of smart building’ systems
71.67
VC
17
22
64.17
VC
15
28
57.5
C
14
35
64.45
VC
13
26
C8
The lack of understanding users’ needs for smartness
67.5
VC
15
29
64.17
VC
16
29
65
VC
11
24
65.56
VC
12
24
C9
The lack of historical databases of existing smart buildings’ performance
91.67
EC
2
2
71.67
VC
9
18
78.33
VC
5
8
80.56
VC
5
9
C10
The lack of historical feasibility assessments of smart building systems
79.17
VC
6
13
79.17
VC
7
10
85
VC
3
5
81.11
VC
4
8
C11
The lack of regulations on a vision for achieving a specific level of smartness
64.17
VC
17
32
70.83
VC
10
19
70
VC
8
18
68.33
VC
10
21
C12
The limited demand from consumers for smart buildings
70.83
VC
12
23
52.5
C
18
41
50
C
21
49
57.78
C
19
38
C13
The lack of awareness by consumers (e.g., designers, owners, and users) of the benefits of smart buildings
71.67
VC
10
21
46.67
C
20
44
53.33
C
19
44
57.22
C
20
39
C14
The lack of consumers’ (e.g., designers, owners, and users) awareness of the technical specifications of smartness
93.33
EC
1
1
83.33
VC
4
8
86.67
VC
2
4
87.78
VC
2
4
C15
The lack of specialized and qualified suppliers and manufacturers for smart building systems
42.5
C
22
50
45
C
21
46
45
C
22
53
44.17
C
22
50
C16
The cost of human technical expertise is relatively high compared to the benefits of smart buildings
88.33
EC
4
7
85
VC
2
5
82.5
VC
4
7
85.28
VC
3
6
C17
The total cost of ownership of smart buildings is unclear or relatively forecasted as a high investment
90
EC
3
4
88.33
EC
1
3
89.17
EC
1
1
89.17
VC
1
1
C18
The lack of motivational regulations on choice and implementation of smart buildings
77.5
VC
7
15
46.67
C
20
44
54.17
C
18
40
59.45
C
18
6
C19
The lack of provision of insights into smart building impacts (positive or negative) to policymakers
69.17
VC
13
27
60
C
17
32
56.67
C
16
38
61.95
C
15
31
C20
The insufficient basis of stating users’ needs and requirements
79.17
VC
6
12
65.83
VC
14
25
64.17
VC
12
28
69.72
VC
9
20
C21
The difficulty of forecasting the selected systems’ cycles of upgradeability and the changes of their technologies
71.67
VC
11
20
73.33
VC
7
16
73.33
VC
6
14
72.78
VC
6
15
C22
Smart buildings are not self-sufficient; there are performance risks based on dependability on specific energy sources (no power, no smartness)
75
VC
8
18
45
C
22
47
65.83
VC
10
22
61.94
C
16
32
Challenges pertaining to the design phase
C23
The lack of descriptive guidelines for the design of different systems in smart buildings
70.83
VC
3
24
60.83
C
5
31
66.67
VC
2
21
66.11
VC
3
22
C24
The technological lack of systems integration and interoperability capabilities
33.33
C
11
55
32.5
SC
11
54
39.17
C
11
55
35
SC
11
55
C25
The lack of available visions for principal directions for design thinking of smart buildings
54.17
C
7
42
55
C
6
38
54.17
VC
6
41
54.45
C
7
42
C26
The lack or absence of authoritative action plans to manage the design process of smart building projects
45.83
C
10
49
53.33
C
8
39
54.17
VC
7
42
51.11
C
9
46
C27
The lack of measures to maintain the privacy and data security of users
78.33
VC
3
14
80.83
VC
1
9
76.67
VC
1
10
78.61
VC
1
11
C28
The lack of regulations to maintain the privacy and data security of users
76.67
VC
2
17
79.17
VC
2
12
62.5
VC
3
30
72.78
VC
2
16
C29
The complexity of the design process
70
VC
4
26
63.33
VC
4
30
53.33
C
9
45
62.22
C
5
30
C30
The inability of specifying qualified and quality local manufacturers
50.83
C
8
44
47.5
C
10
43
46.67
C
10
51
48.33
C
10
48
C31
The lack of distinguishing between the smartness requirements of owner, users, operators, and facility managers
59.17
C
6
37
53.33
C
8
40
55
C
5
39
55.83
C
6
41
C32
The lack of understanding of the basis of design responsiveness of occupational health and safety precautionary measures from a technological point of view
64.17
VC
5
33
70.83
VC
3
20
59.17
C
4
34
64.72
VC
4
25
C33
The lack of specification of protection ratings and testing of systems, materials, and components
50.83
C
9
45
55
C
7
38
54.17
C
8
42
53.33
C
8
45
Challenges pertaining to the installation and commissioning phase
C34
Smart building projects are subject to scope variations that result in an excessive increase of budgets allocated
89.17
EC
2
6
89.17
EC
1
1
78.33
VC
2
9
85.56
VC
2
5
C35
Smart building projects are subject to variations that result in an excessive increase of time allocated
70.83
VC
4
25
50
C
4
42
65
VC
4
25
61.94
C
4
32
C36
The lack of logistical support/logistical challenges for procuring smart systems
55
C
6
39
35.83
SC
6
51
60
C
7
33
50.28
C
6
47
C37
The lack of experience in testing smart behaviors and systems
65
VC
5
31
37.5
C
5
50
65
VC
5
26
55.83
C
5
40
C38
The lack of well-trained labor that can work on smart buildings
50.83
C
7
48
33.33
SC
8
53
53.33
C
8
46
45.83
C
7
49
C39
The lack of systems’ compatibility with domestic utilities and national information and communication technologies and services
37.5
C
8
53
34.17
SC
7
52
41.67
C
9
54
37.78
C
9
54
C40
The lack of expertise, support services, and skills for installation and commissioning
36.67
SC
9
54
30
SC
9
55
64.17
VC
6
29
43.61
C
8
51
C41
The high costs of devices and installations
90
EC
1
5
89.17
EC
2
2
88.33
VC
1
2
89.17
EC
1
1
C42
The requirement of high cash flow and financing for smart building projects
83.33
VC
3
10
68.33
VC
3
21
73.33
VC
3
15
75
VC
3
14
Challenges pertaining to the operation and maintenance phase
C43
The operations and maintenance costs (OPEX) are relatively high compared to regular buildings
90.83
VC
1
3
86.67
VC
1
4
87.5
VC
1
3
88.33
VC
1
3
C44
The absence of operations and maintenance teams during early project phases means a lot of risks evolve during the operation and maintenance phase
55
C
9
40
57.5
C
10
35
65
VC
9
27
59.17
C
9
36
C45
The need to reduce replacement cycles of systems
54.17
C
10
43
59.17
C
8
33
60.83
C
8
31
58.06
C
10
37
C46
The lack of skilled and specialized maintenance and operation technicians
41.67
C
12
51
42.5
C
12
48
45.83
C
13
52
43.33
C
12
52
C47
The lack of ensured guaranties and warranties
63.33
VC
7
34
56.67
C
11
36
70
VC
7
19
63.33
VC
8
29
C48
There is a continuous change in operation and maintenance requirements, which affects systems’ effectiveness
62.5
VC
8
35
65
VC
7
27
65.83
VC
8
23
64.44
VC
7
27
C49
There is a continuous change in users’ lifestyles and behaviors
77.5
VC
5
16
79.17
VC
3
13
76.67
VC
3
11
77.78
VC
4
12
C50
Reliability (smart building systems must aim to be robust)
40
C
13
52
40
C
13
49
48.33
C
12
50
42.78
C
13
53
C51
The changing demand for security that affects systems’ effectiveness
88.33
EC
2
8
75.83
VC
5
15
72.5
VC
6
17
78.89
VC
3
10
C52
The changing demand for privacy that affects systems’ effectiveness
80
VC
4
11
79.17
VC
4
14
74.17
VC
5
13
77.78
VC
4
12
C53
The changing functional requirements for controlling and monitoring capabilities
50
C
11
47
58.33
C
9
34
53.33
C
11
47
53.89
C
11
44
C54
The social implications of the accessibility of smart technologies (e.g., elderly use of technologies, gender requirements)
84.17
VC
3
9
83.33
VC
2
8
83.33
VC
2
6
83.61
VC
2
7
C55
The lack of understanding of human–smart systems interactions and behaviors (involvement of virtual reality, augmented reality, and responsive intelligibility)
74.17
VC
6
19
66.67
VC
6
24
75.83
VC
4
12
72.22
VC
6
17
Assessment of challenges affecting the adoption of smart building technologies in Saudi Arabia (ref. author).
Notes: c, challenging; A/Es, architects/engineers; FMs, facilities managers; RCI, relative challenge index (%); CR, challenge rating; CGR, challenge group ranking; OR, overall ranking; EC, extremely challenging; EC, very challenging; and C challenging.
5.1 Programming and feasibility analysis phase
This category encompasses 22 challenges. Among these, the respondents identified “The total cost of ownership of smart buildings is unclear or relatively forecasted as a high investment” as the most critical factor and assigned it a rating of “Very Challenging.” The authors concur with this evaluation as many respondents tended to perceive a smart building as being at the forefront of technology. However, in reality, a smart building is characterized by its capacity to seamlessly and efficiently integrate various categories and types of diverse technologies. This discovery aligns with the findings of other studies as well (Ibrhem et al., 2020; Bibri, 2021). “The lack of consumers” (e.g., designers, owners, and users) awareness of the technical specifications of smartness” was rated “Very Challenging” and was ranked first by A/Es and second by facility managers. This finding is also in agreement with the outcomes of different studies (Belani et al., 2014; Ahmed et al., 2021; Zhao et al., 2021).
This is a reasonable assertion as awareness levels are also contingent on several challenges, including the accessibility of information. The findings reveal that A/Es ranked “The lack of historical databases of existing smart buildings’ performance” as the second most crucial challenge in this phase, attributing it an “Extremely Important” importance rating. The authors concur with this evaluation as comprehending the concept of smart buildings is a fundamental step in gaining a better grasp of smart buildings, and the historical databases related to this concept remain ambiguous, lacking a well-defined framework.
5.2 Design phase
This category encompasses 11 challenges, as outlined in Table 3. A/Es, contractors, and facilities managers all identified “The lack of measures to maintain the privacy and data security of users” as the most critical challenge during this phase, assigning it a rating of “Very Challenging” in terms of importance. The authors concur with these assessments as a substantial number of respondents were driven to transition to smart technologies due to their notable advantages in enhancing efficiency, curbing energy expenses, and furnishing analytics that underpin environmentally sustainable initiatives. Nevertheless, the more technology a business integrates, the more exposed it becomes to potential data breaches (Gadakari et al., 2014; Sathesh and Hamdan, 2021). “The lack of descriptive guidelines for the design of different systems in smart buildings” was rated second by facilities managers and third by A/Es, with an importance rating of “Very Challenging.” This is justified, since acquiring users with the needed information of smart features is a vital aspect of persuading them to adopt smart building technologies (Saad et al., 2022).
5.3 Installation and commissioning phase
This group consists of 9 challenges. As shown in Table 2, most of the challenges that face implementing smart building technologies in Saudi Arabia during installation and commissioning phase are due to the high costs of devices and installations. This finding is also in agreement with the outcomes of different studies (El-Motasem et al., 2021; AlMuharraqi et al., 2022). The secondary source of challenges encountered during the installation and commissioning phase relates to “scope variations in smart building projects that lead to significant budget overruns.” This can be rationalized by the absence of a facility management team at this stage and the absence of an all-encompassing framework capable of meeting the objectives related to the life cycle costs of smart building technologies.
5.4 Operation and maintenance phase
This category comprises 13 challenges. The respondents ranked “The operations and maintenance costs (OPEX) are relatively high compared to regular buildings” as the most significant factor in this group, assigning it a “Very Challenging” rating. The authors concur with this evaluation, given that many of the challenges tend to surface during the operation and maintenance phase, often resulting from unresolved and cumulative issues. Contractors and facilities managers identified “The social implications of the accessibility of smart technologies (e.g., elderly use of technologies, gender requirements)" as the second most crucial challenge during this phase, giving it a “Very Challenging” importance rating. This factor was rated third by A/Es, with identical importance ratings. These findings are consistent with previous research (El-Motasem et al., 2021; AlMuharraqi et al., 2022; Ejidike and Mewomo, 2023).
6 Conclusion and recommendations
This study explored the challenges that impact the adoption of smart building technologies throughout their life cycle in Saudi Arabia. Through a combination of a literature review and pilot testing, a total of 55 challenges were identified and subsequently categorized based on their alignment with the life cycle phases, which include the programming and feasibility analysis phase, design phase, installation and commissioning phase, and operation and maintenance phase. To assess the significance of these challenges, a five-point Likert-scale questionnaire survey was developed and pilot tested. This questionnaire served as a valuable tool for quantifying the qualitative research variables that were identified. As a result, it streamlined the process of prioritizing and rating the importance of these challenges with regard to their influence on the execution of smart building technologies in Saudi Arabia. This assessment was primarily focused on understanding the significance of these challenges in terms of their impact on the successful implementation of smart building projects while adhering to specified budget constraints, targeted project durations, and the mandated quality criteria that align with stakeholder expectations.
The evaluation process involved the engagement of three distinct practitioner groups, namely, A/Es, contractors, and facilities managers. Each group provided 30 responses to the questionnaire survey, and these responses were carefully tabulated and analyzed to compute the relative challenge index (RCI) value, rate index percentage, group ranking of challenges, and overall rankings for each factor. Furthermore, an extensive analysis encompassing all 90 responses from all three groups was conducted to ascertain the overall assessment of the challenges. This process also entailed an examination of the consensus among the three groups of respondents.
These challenges are evidently linked to different stages of the project’s life cycle. The results substantiate the interrelation and direct influence of these challenges on the successful execution of these projects, especially within the context of a life cycle. Furthermore, the outcomes from both the comprehensive evaluation and individual assessments align with the discussions and conclusions presented in the existing literature. Remarkably, a high level of consensus regarding the significance of these challenges was evident among all three respondent groups. This underscores the critical importance of all the identified challenges in realizing smart building projects while adhering to the specified time, quality, and budgetary constraints.
Based on the research findings, the following recommendations are proposed to improve the practice of smart buildings:
⁃ Encourage more research and development in smart building technologies for better adoption in Saudi Arabia.
⁃ Provide incentives to real estate developers and building owners to implement smart buildings practices in their projects.
⁃ Develop a comprehensive regulatory framework and standards for the adoption of smart building technologies.
⁃ Promote public awareness and education about the benefits of smart building technologies.
⁃ Foster collaboration between stakeholders, including the public sector, industry, and academia, to promote the adoption of smart buildings practices and technologies.
Statements
Data availability statement
The original contributions presented in the study are included in the article/Supplementary Material, further inquiries can be directed to the corresponding author.
The author(s) declare financial support was received for the research, authorship, and/or publication of this article. The authors would like to acknowledge that this research work was partially financed by Kingdom University, Bahrain, from the research grant number 2023-11-012.
Conflict of interest
The authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.
Publisher’s note
All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article, or claim that may be made by its manufacturer, is not guaranteed or endorsed by the publisher.
References
1
AdelgrenJ. R.BradleyD. T.Mueller-TrapetM.VorlaenderM. (2012). Effect of boundary diffusers in a reverberation chamber: a preliminary investigation. J. Acoust. Soc. Am.132 (3), 1986. 10.1121/1.4755328
AguilarJ.Garces-JimenezA.R-MorenoM. D.GarcíaR. (2021). A systematic literature review on the use of artificial intelligence in energy self-management in smart buildings. Renew. Sustain. Energy Rev.151, 111530. 10.1016/j.rser.2021.111530
AhmedH.EdwardsD. J.LaiJ. H. K.RobertsC.DebrahC.Owusu-ManuD. G.et al (2021). Post occupancy evaluation of school refurbishment projects: multiple case study in the UK. Buildings11 (4), 169–184. 10.3390/buildings11040169
AlfaloujiQ.SchranzT.FalayB.WilflingS.ExenbergerJ.MattauschT.et al (2023). Co-simulation for buildings and smart energy systems — a taxonomic review. Simul. Model. Pract. Theory126, 102770. 10.1016/j.simpat.2023.102770
AlMuharraqiM.SweisG.SweisR.SammourF. (2022). Factors affecting the adoption of smart building projects in the Kingdom of Bahrain. J. Build. Eng.62, 105325. 10.1016/j.jobe.2022.105325
AlsolamiB. M. (2022). Identifying and assessing critical success factors of value management implementation in Saudi Arabia building construction industry. Ain Shams Eng. J.13 (6), 101804. 10.1016/j.asej.2022.101804
AttoueN.ShahrourI.YounesR. (2018). Smart building: use of the artificial neural network approach for indoor temperature forecasting. Energies11 (2), 395–406. 10.3390/en11020395
Balta-OzkanN.DavidsonR.BicketM.WhitmarshL. (2013). Social barriers to the adoption of smart homes. Energy Policy63, 363–374. 10.1016/j.enpol.2013.08.043
BelaniD.MakwanaA. H.PitrodaJ.VyasC. M. (2014). Intelligent building new era of todays world. Trends Challenges Civ. Eng. Today‟s Transform. World2014, 1–16. 10.13140/RG.2.1.1723.4965
BibriS. E. (2021). Data-driven smart eco-cities and sustainable integrated districts: a best-evidence synthesis approach to an extensive literature review. Eur. J. Futur. Res.9 (1), 16. 10.1186/s40309-021-00181-4
De GrooteM.VoltJ.BeanF. (2017). Is Europe ready for the smart buildings revolution? Mapping smart-readiness and innovative case studies. Available at: www.bpie.eu.
EjidikeC. C.MewomoM. C. (2023). Benefits of adopting smart building technologies in building construction of developing countries: review of literature. SN Appl. Sci.5 (2), 52. 10.1007/s42452-022-05262-y
El-RashidyN.El-SappaghS.Riazul IslamS. M.El-BakryH. M.AbdelrazekS. (2021). Mobile health in remote patient monitoring for chronic diseases: principles, trends, and challenges. Diagnostics11 (4), 607–632. 10.3390/diagnostics11040607
FabiV.BarthelmesV. M.SchweikerM.CorgnatiS. P. (2017a). Insights into the effects of occupant behaviour lifestyles and building automation on building energy use. Energy Procedia140, 48–56. 10.1016/j.egypro.2017.11.122
FabiV.BarthelmesV. M.SchweikerM.CorgnatiS. P. (2017b). Insights into the effects of occupant behaviour lifestyles and building automation on building energy use. Energy Procedia140, 48–56. 10.1016/j.egypro.2017.11.122
GadakariT.MushatatS.NewmanR. (2014). Intelligent buildings: key to achieving total sustainability in the Built environment. J. Eng. Proj. Prod. Manag.4 (1), 2–16. 10.32738/jeppm.201401.0002
GhaffarianhoseiniA.BerardiU.AlWaerH.ChangS.HalawaE.GhaffarianhoseiniA.et al (2016). What is an intelligent building? Analysis of recent interpretations from an international perspective. Archit. Sci. Rev.59 (5), 338–357. 10.1080/00038628.2015.1079164
GhansahF. A.Owusu-ManuD. G.AyarkwaJ. (2020). Project management processes in the adoption of smart building technologies: a systematic review of constraints. Smart Sustain. Built Environ.10 (2), 208–226. 10.1108/SASBE-12-2019-0161
GhansahF. A.Owusu-ManuD. G.AyarkwaJ.EdwardsD. J.HosseiniM. R. (2021). Exploration of latent barriers inhibiting project management processes in adopting smart building technologies (SBTs) in the developing countries. Constr. Innov.21 (4), 685–707. 10.1108/CI-07-2020-0116
HamidaM. B.HassanainM. A.Al-HammadA. M. (2022). Review and assessment of factors affecting adaptive reuse of commercial projects in Saudi Arabia. Int. J. Build. Pathol. Adapt.40 (1), 1–19. 10.1108/IJBPA-04-2020-0033
HimeurY.AlsalemiA.BensaaliF.AmiraA. (2020). A novel approach for detecting anomalous energy consumption based on micro-moments and deep neural networks. Cogn. Comput.12 (6), 1381–1401. 10.1007/s12559-020-09764-y
HimeurY.ElnourM.FadliF.MeskinN.PetriI.RezguiY.et al (2023). AI-big data analytics for building automation and management systems: a survey, actual challenges and future perspectives. Springer Neth.56 (6), 4929–5021. 10.1007/s10462-022-10286-2
HimeurY.GhanemK.AlsalemiA.BensaaliF.AmiraA. (2021). Artificial intelligence based anomaly detection of energy consumption in buildings: a review, current trends and new perspectives. Appl. Energy287, 116601. 10.1016/j.apenergy.2021.116601
HuseienG. F.ShahK. W. (2022). A review on 5G technology for smart energy management and smart buildings in Singapore. Energy ai.7, 100116. 10.1016/j.egyai.2021.100116
IwuagwuB. U.ChiomaM.IwuagwuB. (2014). “Adopting intelligent buildings in Nigeria: the hopes and fears,” in 2nd International Conference on Emerging Trends in Engineering and Technology (ICETET'2014), London (UK), May 30-31, 2014.
JayasingheI.DomingoN.Thi HoaiA. L.SutrisnaM. (2023). A Systematic review of vertical construction project characteristics. Moratuwa: University of Moratuwa, 37–46. 10.31705/wcs.2023.4
KaklauskasA.LillI.AmaratungaD.UbarteI. (2019). Model for smart, self-learning and adaptive resilience building. Emerald Reach Proc. Ser.2, 315–324. 10.1108/S2516-285320190000002017
LiZ.ZhangJ.LiM.HuangJ.WangX. (2020). A review of smart design based on interactive experience in building systems. Sustain12, 6760–6774. 10.3390/SU12176760
MarigoM.MaccariniA.ZarrellaA.AfshariA. (2023). Fault impact analysis of ventilation systems in residential buildings: a simulation-based case study in Denmark. Energy Build.292, 113150. 10.1016/j.enbuild.2023.113150
McLauchlanK. K.HigueraP. E.MieselJ.RogersB. M.SchweitzerJ.ShumanJ. K.et al (2020). Fire as a fundamental ecological process: research advances and frontiers. J. Ecol.108 (5), 2047–2069. 10.1111/1365-2745.13403
PramanikP. K. D.MukherjeeB.PalS.PalT.SinghS. P. (2019). Green smart building: requisites, architecture, challenges, and use cases. Green Build. Manag. Smart Automation2019, 1–50. 10.4018/978-1-5225-9754-4.ch001
RomanK. K.O’BrienT.AlveyJ. B.WooO. J. (2016). Simulating the effects of cool roof and PCM (phase change materials) based roof to mitigate UHI (urban heat island) in prominent US cities. Energy96, 103–117. 10.1016/j.energy.2015.11.082
SaadS.AlaloulW. S.AmmadS.AltafM.QureshiA. H. (2022). Identification of critical success factors for the adoption of Industrialized Building System (IBS) in Malaysian construction industry. Ain Shams Eng. J.13 (2), 101547. 10.1016/j.asej.2021.06.031
SalkutiS. R. (2021). Smart cities: understanding policies, standards, applications and case studies. Int. J. Electr. Comput. Eng.11 (4), 3137–3144. 10.11591/ijece.v11i4.pp3137-3144
Sánchez-CorcueraR.Nuñez-MarcosA.Sesma-SolanceJ.Bilbao-JayoA.MuleroR.ZulaikaU.et al (2019). Smart cities survey: technologies, application domains and challenges for the cities of the future. Int. J. Distrib. Sens. Netw.15, 155014771985398. 10.1177/1550147719853984
SovacoolB. K.Furszyfer Del RioD. D. (2020). Smart home technologies in Europe: a critical review of concepts, benefits, risks and policies. Renew. Sustain. Energy Rev.120, 109663. 10.1016/j.rser.2019.109663
TaktakE. (2016). “An adaptation approach for Smart Buildings,” in 2016 IEEE 18th International Conference on High Performance Computing and Communications; IEEE 14th International Conference on Smart City; IEEE 2nd International Conference on Data Science and Systems (HPCC/SmartCity/DSS), Sydney, NSW, Australia, 12-14 December 2016. 10.1109/HPCC-SmartCity-DSS.2016.0156
ZhaoS.ZhangP.LiW. (2021). A study on evaluation of influencing factors for sustainable development of smart construction enterprises: case study from China. Buildings11 (6), 221. 10.3390/buildings11060221
ZhenxingW.ShutaoW.LinxiangS.ZhongyuanL. (2009). “The analysis and implementation of smart home control system,” in 2009 International Conference on Information Management and Engineering, Kuala Lumpur, Malaysia, 03-05 April 2009, 546–549. 10.1109/ICIME.2009.79
smart building technologies, challenges, buildings lifecycle phases, building automation, smart city
Citation
Baharetha S, Soliman AM, Hassanain MA, Alshibani A and Ezz MS (2024) Assessment of the challenges influencing the adoption of smart building technologies. Front. Built Environ. 9:1334005. doi: 10.3389/fbuil.2023.1334005
Received
06 November 2023
Accepted
19 December 2023
Published
23 January 2024
Volume
9 - 2023
Edited by
Yassine Himeur, University of Dubai, United Arab Emirates
Reviewed by
Adel Oulefki, University of Sharjah, United Arab Emirates
This is an open-access article distributed under the terms of the Creative Commons Attribution License (CC BY). The use, distribution or reproduction in other forums is permitted, provided the original author(s) and the copyright owner(s) are credited and that the original publication in this journal is cited, in accordance with accepted academic practice. No use, distribution or reproduction is permitted which does not comply with these terms.
All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.