ORIGINAL RESEARCH article

Front. Built Environ., 09 November 2026

Sec. Urban Science

Volume 12 - 2026 | https://doi.org/10.3389/fbuil.2026.1958158

Evidence-concordance audit before multicriteria ranking: reassessing Kabul’s historical water-supply options

  • 1. School of Information Engineering, Xi’an Fanyi University, Xi’an, China

  • 2. School of Civil Engineering, Kandahar University, Kandahar, Afghanistan

  • 3. Faculty of Economics and Management, Xi’an Fanyi University, Xi’an, China

  • 4. Geotill Engineering Inc., Fishers, IN, United States

  • 5. Department of Earth Sciences, University of Oxford, Oxford, United Kingdom

Abstract

Introduction:

Historical infrastructure decisions are often revisited using evidence developed under different definitions, assumptions, and system boundaries. This study reassesses seven water-supply alternatives from Kabul’s 2009 planning archive to determine whether the archived evidence remains sufficiently comparable for decision modeling.

Methods:

Each source-table cell or narrative quantity was transcribed with an exact locator, unit, construct label, and system boundary, then screened through five ordered binary gates: provenance, semantic typing, comparability, dependence, and uncertainty. The audit was qualitative and rule-based and did not assign a composite evidence-quality score. Costs were compared at 30 million m3/year, a common plotted service level rather than a demand target, with sensitivity analysis from 15 to 100 MCM/year. Reported supply quantities were excluded because the archive combines non-equivalent constructs, whereas availability statements were retained only as source-defined timing indicators.

Results:

Under the baseline cost-timing specification, CRITIC weights were driven mainly by criterion dispersion, and Shatoot ranked first. Across normalized cost weights, the Panjshir fan aquifer ranked first below 0.288, Shatoot from approximately 0.288 to 0.941, and Gat above 0.941. These three alternatives form the non-dominated set. Across tested service levels, the Pareto set and sequence of first-ranked alternatives remained unchanged; only the final positions of Gulbahar and Salang exchanged at 100 MCM/year. Alternative timing assumptions and bounded cost scenarios were descriptive stress tests, not probabilistic predictions.

Discussion:

The findings support conditional historical comparison, not a definitive project winner. A four-dam CRITIC formulation was not retained because estimating correlations across eight criteria from only four alternatives provides insufficient information for reliable weighting. Later JICA reports provide updated context but no comparable contemporary seven-option matrix. Any project recommendation requires renewed, comparable evidence.

1 Introduction

Urban water planning must balance reliability, affordability, energy requirements, implementation time, environmental constraints, and social legitimacy. Recent research on urban water resilience and integrated water management treats supply planning as the management of a staged portfolio of sources, networks, institutions, and adaptation options, rather than the selection of a single permanent project (Ferdowsi et al., 2024; Huang et al., 2023; Lim et al., 2023; Saikia et al., 2022; Tan and Yao, 2023; Thakur et al., 2024). Multicriteria decision analysis (MCDA) can make these trade-offs explicit. However, a numerical ranking is defensible only when criterion values represent comparable constructs, are defined within consistent system boundaries, and are combined through an interpretable preference model (Abrishamchi et al., 2005; Belton and Stewart, 2012; Hajkowicz and Collins, 2007; Marttunen et al., 2022; Shah et al., 2024).

Comparability becomes a distinct methodological challenge when a historical infrastructure decision is reconstructed from archival records. The same label may refer to fundamentally different concepts, such as reservoir yield, maximum development potential, staged urban allocation, or total multipurpose availability. Similarly, an availability date may represent the earliest possible commissioning rather than construction duration, while reported project costs may already incorporate conveyance infrastructure. Conventional sensitivity analysis cannot correct these conceptual mismatches: it can vary values or preference weights, but it cannot transform non-equivalent constructs into comparable decision criteria. The MCDA literature provides extensive guidance on value functions, rank reversal, uncertainty analysis, weighting methods, and stakeholder elicitation (Belton and Stewart, 2012; Hajkowicz and Collins, 2007; Marttunen et al., 2022; Shah et al., 2024; Zhao et al., 2022) yet offers comparatively limited operational guidance for determining whether an archival value is suitable for inclusion in a reconstructed consequence table.

The proposed evidence-concordance audit integrates established practices from several fields into a structured pre-ranking admissibility assessment. Construct validity evaluates whether a measure supports its intended interpretation (Chapelle, 1998). Data provenance principles require traceable sources and derivations (W et al., 2024; Moreau et al., 2011), while retrospective data harmonization distinguishes a shared construct from a merely similar label (Fortier et al., 2017). Value-focused and structured decision-making methods translate explicit objectives into measurable attributes (Gregory et al., 2012; Keeney, 1996), and MCDA practice cautions against criterion redundancy and double-counting (Dodgson et al., 2009). Together, these principles establish an explicit test to determine whether archival evidence is suitable for inclusion in a common decision model.

Kabul provides a demanding test case because its water planning record contains related studies developed under different scopes, assumptions, and analytical bases. The reviewed evidence indicates that the 2009 metropolitan master plan study by the Japan International Cooperation Agency (JICA) provides the most internally consistent cross-option engineering archive, and it is therefore used as the baseline. A subsequent 2013 JICA feasibility study narrowed the assessment to the Panjshir Fan aquifer, the Gulbahar Dam, and the Salang Dam (Japan International Cooperation Agency, 2013). Because its scope, demand and design assumptions, analytical framework, and cost basis differ materially from those of the 2009 study, the later report is treated as a feasibility update rather than independent validation. These differences preclude a direct, like-for-like numerical comparison with the seven-option cost curves reported in 2009. The 2013 report is therefore used to trace changed assumptions and identify evidence renewal needs rather than to validate or replace the earlier comparison. Subsequent JICA reports, government and donor documents, and hydrogeological and climate studies provide additional context (Hussaini et al., 2022; Japan International Cooperation Agency, 2018; Japan International Cooperation Agency, 2023; Khatiwada et al., 2024; Ministry of Energy and Water of Afghanistan, 2023; Taher et al., 2014; World Bank, 2020; Zaryab et al., 2022). However, the documented evidence review identified no contemporary seven-option matrix with consistent engineering boundaries.

This study contributes a reproducible link between evidence curation and numerical appraisal. The evidence-concordance audit applies an explicit, ordered, and auditable admissibility rule: before scoring, each value is assigned a source trace, construct type, system boundary, dependence classification, uncertainty class, and admissibility decision. A criterion enters the common matrix only when every alternative satisfies the same construct and boundary requirements. Specifically, the study addresses four questions (Ferdowsi et al., 2024): Which archival measures satisfy the comparability test? (Huang et al., 2023) Which alternatives form the cost-timing Pareto set? (Lim et al., 2023) How do conditional rankings change as the relative weight assigned to cost varies? (Saikia et al., 2022) What evidence must be renewed before any recommendation is made? After admissibility screening, the retained matrix is examined using Criteria Importance through Intercriteria Correlation (CRITIC) weighting, cost-timing Pareto analysis, and the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS). These tools support the numerical appraisal; the methodological contribution lies in the evidence-concordance audit. The audit is qualitative and deterministic: every gate is recorded as pass/fail, and ambiguous evidence is retained as contextual rather than being converted into an arbitrary score.

Section 2 describes the historical system, evidence base, and analytical methods. Section 3 presents the conditional results. Section 4 discusses the findings and limitations and sets out the evidence-renewal agenda. Section 5 summarizes the conclusions.

2 Materials and methods

2.1 Historical metropolitan system

The historical Kabul Metropolitan Area included the existing city and planned growth in Dehsabz and Barikab. The seven expansion options are the Shatoot Dam, the Gat Dam, the Upper Logar aquifer, the Panjshir fan aquifer, the direct Panjshir River abstraction, the Gulbahar Dam, and the Salang Dam. Local Kabul groundwater remains part of the historical portfolio but is not ranked because the archive does not provide a cost curve on the same decision boundary. Figure 1 provides the coordinate-based source schematic (Japan International Cooperation Agency: RECS International Inc, 2009). In geographical terms, Shatoot and Gat are dam options in the upper Kabul basin, located south or southeast of Kabul; the Upper Logar aquifer is in the Logar corridor, located south of Kabul; the Panjshir fan and direct Panjshir River abstraction are associated with the Panjshir-Gulbahar system, located north or northeast of Kabul; the Gulbahar Dam is near the Gulbahar locality in that corridor; and the Salang Dam is in the upper Salang basin, located farther north. Figure 1A provides approximate WGS84 reference coordinates for the named localities and hydrological units. These coordinates are contextual map references, not surveyed dam footprints or numerical inputs.

FIGURE 1

2.2 Archival search and inclusion protocol

The targeted archival update was completed on 26 July 2026 using sources from the JICA, the World Bank, the Asian Development Bank, the United States Geological Survey, the Afghanistan Ministry of Energy and Water, and Crossref. The date is the search cutoff and reference access date used throughout the manuscript. Of the 372 logged query-level records, 299 unique records were screened, and 12 were retained. Only records with a compatible engineering boundary entered the common matrix. Table 1 summarizes the retained sources and their analytical roles; Supplementary Material S1 documents the numerical calculation protocol and extended sensitivity results.

TABLE 1

RecordExact locator or dateAnalytical roleReasons for not merging into the common matrix
JICA metropolitan water-resources study (Japan International Cooperation Agency: RECS International Inc, 2009)Sector Report 3, Chapters 5–6, pp. 5–45–6-18Common seven-option archive and cost curvesIncluded as the historical analytical boundary
JICA feasibility update (Japan International Cooperation Agency, 2013)Summary, Chapters 1–4, 2013Later engineering comparison for three new city sourcesSubset, revised demand, design, and price basis
JICA Dehsabz South implementation review (Japan International Cooperation Agency, 2018)Executive summary and Chapter 2, pp. 2-1–2-2, 2018Implementation status and local well designDistribution project for one parcel; no seven-option comparison
JICA urban development survey (Japan International Cooperation Agency, 2023)Table of contents and Chapters 1–3, 2023Urban growth, institutions, and planning contextScope covers urban development, land, housing, and institutions, but excludes a technical water-source appraisal.
World Bank A-WASH record (World Bank, 2020)Project Appraisal Document, 13 November 2020Utility resilience and service delivery contextNo comparable source consequence table
ADB managed-recharge records (Asian Development Bank, 2015; Asian Development Bank, 2023)Projects 49187–002 and 48440–002Groundwater recharge alternative and institutional contextDifferent intervention and appraisal boundary
Afghanistan Ministry status records (Ministry of Energy and Water of Afghanistan, 2023)Gulbahar/Panjshir update, 5 December 2023Contemporary project status signalPublic status statement without reproducible common design basis
USGS monitoring and recent studies (Hussaini et al., 2022; Khatiwada et al., 2024; Taher et al., 2014; Zaryab et al., 2022)2004–2013 monitoring and later peer-reviewed analysesCurrent validation requirementsDifferent variables, periods, and spatial boundaries

Evidence-search results, analytical roles, and exclusions from the common matrix.

2.3 Semantic audit of supply quantities

The audit distinguishes six constructs: physical reservoir storage, aquifer or river abstraction potential, estimated urban supply, a planning ceiling, a staged contribution, and total multipurpose development. These constructs are not interchangeable benefits. Gulbahar’s 240 MCM/year denotes the total new multipurpose development in the 2009 alternative table, whereas 44.7 MCM/year is the dam contribution selected for the staged new-city portfolio. Shatoot, Gat, and Salang use other definitions, and the two Panjshir options share one 157.7 MCM/year ceiling. Table 2 retains every number for provenance but excludes supply magnitude from both the seven-option and dam aggregations.

TABLE 2

AlternativeReported quantityEvidence typeExact source locatorUse in revised analysis
Shatoot Dam54.0 MCM/yearEstimated domestic plus industrial urban supplyJICA 2009, Table 6.2, pp. 6-5–6-6Provenance only
Gat Dam122.0 MCM/yearEstimated urban supply from storageJICA 2009, Table 6.2, pp. 6-5–6-6Provenance only
Upper Logar aquifer31.5 MCM/yearPlanning maximum after local and mine considerationsJICA 2009, Table 6.2, pp. 6-5–6-6Provenance only
Panjshir fan aquifer157.7 MCM/yearShared planning ceiling after local reserveJICA 2009, Table 6.2, pp. 6-5–6-6Provenance only
Panjshir River abstraction157.7 MCM/yearSame ceiling; not an independent river yieldJICA 2009, Table 6.2, pp. 6-5–6-6Provenance only
Gulbahar Dam240.0 MCM/yearTotal multipurpose new developmentJICA 2009, Table 6.2, pp. 6-5–6-6Provenance only
Gulbahar Dam44.7 MCM/yearSelected staged new-city contributionJICA 2009, Table 6.9, p. 6–18; JICA 2013, pp. 1-5–1-7Historical sequence context only; not a numerical input
Salang Dam98–100 MCM/yearEstimated available urban supply; rounded across tablesJICA 2009, Tables 5.34 and 6.2, pp. 5–54 and 6–6Provenance only

Semantic typing of reported supply quantities.

MCM/year denotes million cubic meters per year. No reported supply row is treated as a like-for-like benefit in the revised model. The analysis instead compares the cost of delivering the same fixed service quantity, 30 MCM/year, for every alternative. This is a common cost-curve comparison point, not a demand forecast, a reported yield, or a recommended portfolio quantity. Service-level sensitivity and the non-target interpretation of 30 MCM/year are reported in Supplementary Table S5.

MCM/year denotes millions of cubic meters per year. No reported supply row is treated as a like-for-like benefit in the revised model. The analysis instead compares the cost of delivering the same fixed service quantity, 30 MCM/year, for every alternative. The value is not an identified demand target; it was selected because the JICA 2009 cost curves provide a common plotted range spanning approximately 15–100 MCM/year; 30 MCM/year lies within that range for all seven options, and it avoids extrapolating below the common curve domain. This is a common cost-curve comparison point, not a demand forecast, a reported yield, or a recommended portfolio quantity. Recalculation at 15, 20, 25, 30, 40, 50, 60, 80, and 100 MCM/year is reported in Supplementary Table S5; it tests whether the cost-curve geometry changes the ranking.

2.4 Timing evidence

JICA 2009 reports possible completion or availability years, not construction durations. An earlier version of this manuscript converted these statements to inclusive elapsed-year proxies from 2009. In the revised analysis, that convention is explicitly labeled as author-defined, and no probability distribution is fitted. Statements beginning with “after” are treated as lower bounds with no reported upper endpoint—a form of right censoring. The analysis therefore tests a calendar-difference lower-bound encoding and an ordinal source-sequence encoding rather than inventing uncertainty windows. The proxy is a source-derived temporal position only: it cannot distinguish between financing or permitting delays, construction duration, commissioning, or actual water availability. The lower-bound and ordinal encodings test whether the historical source sequence, rather than a claimed duration, drives the conditional ranking. If comparable construction or commissioning data become available, they should replace these proxies, and the screen should be recalculated. Table 3 reports the source statements and all three encodings.

TABLE 3

AlternativeSource statementInclusive-year proxyCalendar differenceOrdinal class
Shatoot DamAround 2018; 2015–2020992
Gat DamAfter 202517165
Upper Logar aquiferAfter 202517165
Panjshir fan aquiferAfter 2015761
Panjshir River abstractionAfter 2015761
Gulbahar DamAround 2023; 2020–202514144
Salang DamAfter 202012113

Source timing statements and alternative encodings.

Source: Japan International Cooperation Agency et al. (2009), Table 6.4, p. 6–8. Ordinal class 1 is the earliest, and class 5 is the latest. For Shatoot, the calendar difference uses the stated year 2018; the accompanying 2015–2020 range is retained as source context and is not interpreted as a construction-duration interval.

2.5 Post-2013 implementation and condition evidence

Later evidence does not support an extension of the historical schedule. The 2018 JICA review reported no new sources for Dehsabz South Parcel 2.2 and designed two Pol-e Charkhi wells with 5,000 m3/day maximum extraction, approximately 1.83 MCM/year, while reducing the design allowance from 150 to 92 L/day (Japan International Cooperation Agency, 2018). It documents a local bridging scheme, not a re-estimation of the regional options.

The 2023 JICA survey informs urban growth and institutions, but not technical water source comparison (Japan International Cooperation Agency, 2023). World Bank and ADB records provide service and managed-recharge context (World Bank, 2020; Asian Development Bank, 2015; Asian Development Bank, 2023), and a 2023 Ministry of Energy and Water, Afghanistan notice reports Gulbahar/Panjshir activity (Ministry of Energy and Water of Afghanistan, 2023). None supplies the common engineering boundary needed to replace values in the historical matrix. These later records were themselves passed through the same audit: they remain admissible as provenance and contextual renewal evidence, but not as entries in the 2009 seven-option consequence table.

2.6 Evidence-concordance audit

The evidence-concordance audit tests whether a reported value, the construct it represents, and the system boundary used in the decision table are mutually consistent. Five screens precede numerical aggregation: provenance, semantic typing, comparability, dependence, and uncertainty. Provenance passes only when the source, locator, wording, unit, and boundary are recorded; semantic typing passes only when one construct can be assigned without interpretive substitution; comparability passes only when the construct, time basis, spatial/service boundary, and denominator match across alternatives; dependence passes only when shared ceilings, duplicate flows, and embedded costs are not counted twice; uncertainty passes only when the evidence class (point, interval, right-censored, or ordinal) is recorded without inventing a distribution. Each gate is binary, there is no weighted audit score or numerical threshold, and a criterion enters the common matrix only if all alternatives pass all required gates. A criterion is admissible only when every alternative represents the same construct at a compatible boundary without material duplication. The results remain subordinate to environmental, social, geotechnical, financial, and institutional gates. Figure 2 summarizes the sequence.

FIGURE 2

The coding unit was one source-table cell or narrative quantity. A first pass transcribed wording, value, unit, locator, and boundary; a second assigned provenance, construct, dependence, uncertainty, and admissibility. Ambiguous cases defaulted to provenance-only status. The most judgment-dependent decisions were the classification of mixed supply labels, the assignment of the relevant cost boundaries, and the assessment of whether later evidence had a compatible engineering basis. This single-analyst audit cannot claim coding reliability. The audit criteria, calculation protocol, and decision rules are reproduced in Supplementary Material S1 so that the analytical decisions can be reviewed; independent blinded coding is needed before an agreement statistic is claimed. For a future validation exercise, at least two independent reviewers should blind-code the same source cells before adjudication. Agreement should be reported as raw percentage agreement, and Cohen’s κ for categorical construct, boundary, dependence, and final admissibility labels, with weighted κ for ordinal uncertainty classes; disagreements and post-adjudication decisions should remain separately traceable.

2.7 Cost reconstruction

The 2009 archive provides 50-year annualized cost curves that include construction, replacement, non-energy operation and maintenance, electricity, and treatment. It uses a 10% discount rate, a 10-year pump replacement period, stated electricity and treatment tariffs, and a 1% non-energy operation and maintenance factor. Gulbahar’s intake cost follows the separable-cost remaining-benefit allocation (Japan International Cooperation Agency: RECS International Inc., 2009). Each curve is evaluated at the fixed 30 MCM/year service quantity to impose a common comparison boundary; the value does not estimate future demand or any option’s achievable yield.

Supplementary Material S1 provides the formulas, the extracted common matrix, and a self-contained script that reproduces the primary 30 MCM/year cost-timing screen. The supplement now transcribes the JICA Table 5.32 component coefficients, and the script re-evaluates all seven curves at V = 30 MCM/year; the reconstructed values match the rounded values in Table 4 within 0.001 USD/m3. The same code also evaluates the service-level sensitivity in Supplementary Table S5.

TABLE 4

AlternativeSupply field, excludedUnit cost at 30 MCM/yearConveyance, excludedTiming proxy
Shatoot Dam54.00.44410 km9
Gat Dam122.00.38117 km17
Upper Logar aquifer31.50.54071 km17
Panjshir fan aquifer157.7 shared ceiling1.00465 km7
Panjshir River abstraction157.7 shared ceiling1.07965 km7
Gulbahar Dam240.0 multipurpose total1.31882 km14
Salang Dam98.01.471100 km12

Reconstructed seven-option matrix and admissibility status.

Supply fields are in MCM/year and are shown only to document their incompatible meanings. Unit cost is USD/m3. Timing is an author-defined proxy in years. The values reproduce Japan International Cooperation Agency (Japan International Cooperation Agency: RECS, international inc, 2009), Tables 5.32, 6.2, and 6.4, pp. 5–47 and 6-5–6-8. The transcribed JICA, Table 5.32 coefficients independently re-derive all seven displayed 30 MCM/year costs to within 0.001 USD/m3; the calculation is documented in Supplementary Tables S4–S6 and the accompanying script.

2.8 Consequence table and normalization

The admissible common screen contains the annual unit cost at V = 30 MCM/year and the historical timing proxy. Both are cost criteria. Reported supply magnitude fails the semantic gate, and distance fails the dependence gate because the annualized cost already includes conveyance construction, pumping, and operation. Table 4 retains the excluded fields as provenance so that the diagnostic model can be reproduced without presenting it as the preferred decision model. Table 5 provides representative evidence-to-decision examples so that the effect of each gate can be inspected rather than inferred from the final rank alone.

TABLE 5

Evidence exampleAudit decisionConsequence for numerical appraisal
Reported supply: Gulbahar 240 versus 44.7 MCM/yearSemantic/comparability fail: total multipurpose development is not the staged urban contribution; provenance retainedExcluded from primary. Restoring supply makes the Panjshir fan first, demonstrating a construct-driven reversal
Panjshir fan and river: shared 157.7 MCM/year ceilingDependence/semantic fail if treated as two independent delivered yieldsNo supply score; prevents double counting of a shared planning ceiling
Conveyance distance: 10–100 kmDependence fail: transfer construction, pumping, and operation are already in annualized costsExcluded from the primary. Adding it changes the weights and makes the Panjshir fan first
“After 2025” timing statementUncertainty fail for duration: right-censored lower bound with no reported upper endpointRetained only as a lower-bound/ordinal proxy; no fitted probability distribution
2013 Panjshir fan update: 52.8 MCM/year and 3-year estimateComparability fail: revised three-option boundary and design basisContextual renewal evidence; not merged into the 2009 seven-option matrix

Representative evidence-concordance decisions and numerical consequences.

Min–max normalization was used for the primary two-criterion screen. Vector and rank-based normalizations were examined only as diagnostic transformations, with the baseline CRITIC weights held fixed so that the transformation, rather than the preference case, changed. The full normalization formulas and tie rules are provided in Supplementary Material S1.

2.9 Weighting, TOPSIS, and Pareto analysis

CRITIC and TOPSIS are used only as conditional diagnostics; their formulas and implementation choices are provided in Supplementary Material S1. With two criteria, CRITIC’s conflict factor cancels after normalization, so the reported weights are normalized dispersions. Equal weights and the full cost-weight interval are therefore reported as explicit preference cases.

TOPSIS scores are conditional comparative values, not probabilities. The Pareto set contains alternatives that no other option matches or improves on both cost and timing. Preference transitions were located on a deterministic grid of 1,000,001 cost weights at a resolution of 10−6; these are grid locations, not random-weight experiments.

2.10 Timing and cost uncertainty

Timing sensitivity uses the three reported encodings without timing frequencies because lower-bound statements lack defensible upper endpoints. Cost sensitivity applies illustrative stress tests to the discount rate, capital, replacement, energy, and operating costs, treatment costs, and Gulbahar allocation. Typical cases include a 5% or 15% discount rate, with the 50-year life and 10-year pump replacement retained; an electricity cost of USD 0.05 or 0.20/kWh, based on USD 0.10/kWh; a ±25% capital/replacement cost; a ±50% operation, maintenance, and treatment cost; a ±25% Gulbahar intake allocation; and combined lower- and higher-cost envelopes. These are one-factor or bounded directional diagnostics, not probabilistic forecasts or cost ceilings. Full bounds and envelopes are reported in Supplementary Material S1; none are statistical intervals or forecasts.

2.11 Dam evidence and no compensatory gates

The eight-criterion dam CRITIC model reported in an earlier version of this manuscript is withdrawn. The four-dam subset was initially retained because the 2009 archive reports a common preliminary set of dam-site fields costs, timings, inundations, affected irrigations, resettlements, and road burden for Shatoot, Gat, Gulbahar, and Salang. This was a documentary inclusion decision, not an assertion that four alternatives are a statistically adequate sample or that dams are the complete option universe. With four projects, the centered eight-criterion data matrix has a rank of at most three, so its eight-by-eight correlation structure is singular, and any correlation-based weight is highly sensitive to a single project. Because CRITIC depends on these correlation terms, a stable eight-criterion model cannot be defensibly estimated. The exclusion is therefore driven primarily by rank deficiency and dependence among burden indicators, not by missing data alone. It also creates a purposive-selection risk: aquifer and river alternatives do not have the same raw land-burden fields, whereas the four dams do. The dam results are consequently presented as a raw diagnostic subset and are not generalized to the full portfolio. Inundation, affected irrigation, and resettlement are also dependent manifestations of reservoir footprint. Supply magnitude and effective storage are excluded from compensatory aggregation because the service quantity is fixed at 30 MCM/year and storage is not equivalent to delivered urban benefit. The revised dam assessment reports raw cost, timing, land, resettlement, and road evidence, Pareto trade-offs, and five documentary gates: verified current urban service at the common quantity, current environmental flow and hydrological evidence, a completed environmental and social impact assessment (ESIA) with a resettlement plan, adequate geotechnical and seismic investigation, and credible financing, operation, and institutional responsibility. Failure or absence of any of these cannot be compensated by a high score elsewhere.

2.12 Reproducibility and AI-assisted technologies

Supplementary Material S1 contains a self-contained Python script that reproduces the primary cost-timing screen, the deterministic preference grid, and the extended sensitivity tables. The script includes the transcribed JICA component coefficients, re-estimates the seven cost curves, and reproduces the displayed 30 MCM/year values to within 0.001 USD/m3; it also reports the service-level sensitivity and the proposed audit coding fields. Other analytical inputs are contained in the manuscript tables or cited source reports.

3 Results

3.1 Conditional cost–timing screen

The reconstructed coefficients yield primary weights of 0.481 for cost and 0.519 for the timing proxy. Under that single weighting and the min–max TOPSIS method, the Shatoot option has the highest closeness score, followed by the Panjshir fan and the direct Panjshir River abstraction. This is not a preference-independent ordering. Gat, Shatoot, and the Panjshir fan are non-dominated in the cost-timing space; every other option is dominated by at least one of those three. Table 6 reports the complete results, and Figure 3 shows the frontier and preference intervals. Figure 3a makes the geometry explicit: Shatoot is earlier but costlier than Gat, while the Panjshir fan is earlier but costlier than Shatoot; these three points form the frontier. Figure 3b translates that geometry into preference intervals, and Figure 3c shows that the complete order, and not only the winner, remains unchanged in all 13 bounded cost cases.

TABLE 6

AlternativeUnit cost at 30 MCM/year (USD/m3)Timing proxy (years)TOPSIS closeness (CRITIC weights)Share of cost-weight range ranked firstPareto status
Shatoot Dam0.44490.85165.3%Non-dominated
Gat Dam0.381170.4815.9%Non-dominated
Upper Logar aquifer0.540170.4390.0%Dominated
Panjshir fan aquifer1.00470.67028.8%Non-dominated
Panjshir River abstraction1.07970.6400.0%Dominated
Gulbahar Dam1.318140.2360.0%Dominated
Salang Dam1.471120.3220.0%Dominated

Complete primary cost–timing results and deterministic weight sensitivity.

The first-rank share is the percentage of the deterministic cost-weight interval from 0 to 1 in which an alternative is ranked first. It is not a probability or confidence interval. Service-level sensitivity is reported separately from these preference interval shares because service volume and preference weight answer different questions.

FIGURE 3

The grid locates the first-rank transition at cost weights of approximately 0.288 from the Panjshir fan to Shatoot and at approximately 0.941 from Shatoot to Gat. Consequently, the fan occupies 28.8% of the weight interval, Shatoot 65.3%, and Gat 5.9%. The other four alternatives are never first among the 1,000,001 evaluated weights. The result quantifies a trade-off, not a sampling frequency.

3.2 Timing-encoding sensitivity

Changing the cardinal interpretation of the historical calendar statements changes score magnitudes but not the first-ranked alternative under either CRITIC dispersion weights or equal weights. This limited invariance does not validate the timing proxy; it shows only that the three tested encodings preserve the same source sequence. Supplementary Table S1 reports every ranking rather than first-rank frequencies.

3.3 Cost-scenario sensitivity

Shatoot remains first under the bounded cost cases when either the dispersion weights are recalculated, or equal weights are used. The complete rankings are more informative than the winner alone: the Panjshir fan and river remain second and third, Gat is fourth, Upper Logar is fifth, Salang is sixth, and Gulbahar is seventh in these common-direction component cases. This result does not cover unknown alternative-specific design changes, treatment requirements, security costs, or present prices. It therefore supports only conditional stability within the stated historical cost model. Supplementary Table S2 reports all 13 scenarios and their complete orders. Re-evaluating the curve at 15–100 MCM/year yields the same first-ranked sequence and the same three-option Pareto set at every tested level; at 100 MCM/year, only the last two positions exchange, with Gulbahar moving ahead of Salang. This sensitivity analysis does not establish the current demand level, but it does show how the selected common service point affects the historical cost geometry.

3.4 Historical four-criterion diagnostic

If the incompatible supply field and overlapping conveyance distance are restored, the four-criterion CRITIC weights are 0.264 for reported supply, 0.258 for cost, 0.192 for distance, and 0.286 for timing. The Panjshir fan is ranked first, followed by Shatoot and direct river abstraction. This reversal is evidence that criterion construction drives the result; it is not an alternative primary model. Because supply and distance fail the audit gates, the diagnostic order is not used in the conclusion.

3.5 Dam evidence without unstable correlation weights

At the common 30 MCM/year service quantity, the four dams exhibit genuine trade-offs. Gat has the lowest reconstructed cost but the latest timing proxy and the largest preliminary land and resettlement burdens. Salang has the smallest footprint but the highest unit cost. Shatoot has an earlier timing proxy and intermediate land burdens. Gulbahar has a high cost, a pumped transfer, a large 2013 resettlement estimate, and unresolved geological and safeguard evidence in the later feasibility report. No dam dominates the others across the raw criteria. Supplementary Table S3 records the source values and gate evidence required before a project recommendation, and Figure 4 summarizes the non-aggregated resettlement and land burdens. Figure 4a shows the scale and date mismatch directly: the 2009 resettlement ranges are 1,000–2,000 people for Shatoot and Gulbahar, 15,000–25,000 for Gat, and 500–1,000 for Salang, while the separate 2013 Gulbahar estimate is 13,000. Figure 4b separates inundation from affected irrigation: Gat has 2,619 and 1,476 ha, Shatoot 602 and 140 ha, Gulbahar 429 and 114 ha, and Salang 118 and 37 ha, respectively. These raw contrasts explain why a composite dam score would be consequential, but the dates, constructs, and dependence prevent a defensible eight-criterion CRITIC aggregation.

FIGURE 4

3.6 Historical sequence and evidence gates

The 2009 staged portfolio remains a record of the intended service sequencing, not a current schedule. Its source quantities are retained in Table 2 because they are historical plan entries rather than comparable benefit estimates. The 2018 local well scheme shows that planned transitions were not automatic. A renewed sequence must depend on verified demand, safe yield, environmental flow, energy and tariff capacity, safeguard completion, and institutional readiness. The gates are decision rules, not additional weighted criteria: a missing gate prevents a recommendation rather than lowering a score. New evidence could change an option’s service quantity, cost, timing, or feasibility and would require the audit to be re-run rather than a mechanical adjustment of the historical ranking.

4 Discussion

4.1 Decision-theoretic interpretation

The central decision-relevant result is a Pareto set, not a winner. Gat represents a lower historical unit cost and later availability position, the Panjshir fan an earlier and more expensive position, and Shatoot an intermediate position. Choosing among them requires an explicit cost-timing preference and safeguards that cannot be traded away. The CRITIC point falls within Shatoot’s leading interval, but it does not confer public preference, technical objectivity, or probability. The normalized cost weight is a preference parameter rather than a share of monetary expenditure: below 0.288, timing is emphasized strongly enough that the earlier Panjshir fan leads; between 0.288 and 0.941, the intermediate Shatoot trade-off leads; above 0.941, the model expresses an extreme cost emphasis, and Gat leads despite its later timing proxy. These thresholds therefore identify policy preference regimes, not universal technical breakpoints.

The findings also clarify rank reversal. The Panjshir fan leads when supply magnitude and distance are included, whereas Shatoot leads when those fields are removed. This is not evidence that one normalization is correct. Instead, it demonstrates that a shared planning ceiling can reward two alternatives as if they had independent yields and that distance can duplicate costs already embedded in the annualized curve. The comparability and dependence gates should therefore precede any robustness exercise. The service-level check qualifies this interpretation: the frontier is stable over the JICA curve domain, but the conditional result should not be treated as current feasibility evidence.

4.2 Meaning of later evidence

The 2013 feasibility update makes the Panjshir fan concept more concrete by specifying an infiltration gallery, an average design supply of 52.8 MCM/year, a 3-year construction estimate, and a shorter transfer than the 2009 planning representation (Japan International Cooperation Agency, 2013). It also reports energy, finance, and subsidy constraints. Because it compares only three new-city alternatives under revised assumptions, it does not validate the seven-option ranking. Its strongest role is to show how planning ceilings can be replaced by project-specific design quantities when a ncept matures.

The 2018 implementation review narrows the interpretation further. Local wells and a reduced per capita design supply were used because a new source was not then expected for the target parcel (Japan International Cooperation Agency, 2018). The 2023 JICA urban survey and the post-2013 donor and government records show continuing urban growth, groundwater pressure, institutional change, and project activity (Japan International Cooperation Agency, 2023; Ministry of Energy and Water of Afghanistan, 2023; World Bank, 2020; Asian Development Bank, 2015; Asian Development Bank, 2023) but no complete, current engineering comparison. Later evidence therefore changes the questions that must be asked—it does not supply missing commensurability. The newer evidence is therefore relevant to the audit even when it cannot enter the matrix: it identifies which historical assumptions have become outdated.

4.3 Evidence gates and portfolio planning

The quantitative screen cannot establish environmental flow limits, acceptable displacement, aquifer drawdown thresholds, affordability standards, or service equity commitments. These require current assessment and stakeholder deliberation. Missing evidence cannot be treated as zero, and serious impacts cannot be offset by cost or timing gains.

A staged portfolio is more defensible than an isolated-source ranking. Reliability, resilience, and vulnerability metrics can test combinations of groundwater, managed recharge, storage, transfer, demand management, leakage control, and emergency capacity (Hashimoto et al., 1982). Adaptive pathways can link transitions to observed triggers (Haasnoot et al., 2013). Behzadian and Kapelan (2015) demonstrate the value of integrating sustainability dimensions into strategic urban-water assessment. Brown et al. (2009) explain how urban water-management regimes shift historically, which supports treating the 2009 portfolio as a time-specific regime rather than as a timeless optimum. Moorthy and Bibi (2023) identify cross-border water-security and institutional issues in the Kabul River Basin; Shams and Muhammad (2023) focus more specifically on the governance requirements for Afghanistan–Pakistan cooperation. Wong and Brown (2009) provide the water-sensitive-city principles that connect source decisions to land use, decentralization, and urban form, while the World Bank guidance note (World Bank, 2018) translates integrated urban-water management into an operational project-planning approach. Together, these references support the portfolio and governance implications, but none supplies the missing common engineering matrix for the present seven-option comparison. A recent Kabul aquifer model adds contemporary hydrogeological context but not a comparable historical matrix (Nazari et al., 2025); recent work on structured evidence integration and decision-relevant information selection further supports explicit statements of gaps and update triggers (Rode et al., 2025; Zaniolo et al., 2026).

4.4 Methodological contribution and transfer hypothesis

This audit does not claim to invent construct validity, provenance, harmonization, consequence tables, or safeguards against double counting. Its contribution is an ordered, falsifiable rule that connects those practices to an archival MCDA admissibility decision. The trace records source wording, construct, boundary, dependence, uncertainty, and inclusion before normalization while preserving excluded evidence. In Kabul, it removes supply and distance from the primary matrix, withdraws timing probabilities and the dam correlation model, and yields a Pareto set with preference intervals. Supplementary Material S1 enables each semantic decision to be checked or contested. The approach also aligns with recent evidence-integration methods that preserve gaps and convert them into testable data-collection questions rather than masking them in an aggregate score (Rode et al., 2025) and also aligns with decision-relevant information-selection research that links monitoring choices to future policy performance (Zaniolo et al., 2026).

Application beyond Kabul remains hypothetical. The dam layer is a second decision level within the same archive and not an independent case. The audit was conducted by one analyst and provides no inter-reviewer agreement estimate, particularly for construct and boundary judgments. A follow-up study should preregister the coding dictionary, have two reviewers independently code a shared random or purposive sample of source cells, calculate Cohen’s κ for nominal decisions and weighted κ for ordinal uncertainty classes, report raw agreement and category prevalence, adjudicate disagreements only after the blinded pass, and rerun the matrix under each reviewer’s unadjudicated decisions to test rank stability. Future research should use independent blinded coding, a second infrastructure archive, and comparison with established data-quality and value-focused processes to test agreement, reproducibility, and rank stability.

4.5 Practical use, limitations, and evidence-renewal priorities

The historical hydrological series covers 1962–1978, cost estimates use a 2009 price and design basis, and timing statements are not durations. The timing encodings test a historical source sequence rather than actual construction duration, commissioning, or water availability; other reasonable interpretations may therefore change the cost-timing screen. The cost scenarios are bounded diagnostics rather than empirically fitted distributions. Current security, procurement, construction escalation, electricity reliability, treatment requirements, replacement assets, and multipurpose allocation could alter the options differently. Public websites and catalogs may omit non-digitized government, utility, donor, or consultant records. The archive search is therefore documented and updatable rather than claimed to be complete. A 2025 Kabul aquifer model is an example of the kind of newer evidence that should inform the next audit cycle, but it does not share the seven-option cost boundary and is therefore not merged into the historical matrix (Nazari et al., 2025).

The results should guide evidence renewal rather than approval. First, a shared register should be maintained, with updates for demand, streamflow, aquifer, water-quality, treatment, energy, and affordability evidence at a common service boundary. Before feasibility comparison, hydrological and environmental-flow studies, aquifer testing, treatment designs, and a current cost and finance assessment should be completed. Geotechnical and seismic investigations, land and safeguard studies, participatory resettlement planning, service-equity targets, and credible operating responsibility are required before construction approval. Stakeholders should be shown the three Pareto alternatives as transparent cost-timing trade-offs with their outstanding evidence gates before documenting an acceptable preference trade-off.

5 Conclusion

This evidence-concordance audit reframed Kabul’s historical water supply appraisal from a single project ranking to a conditional cost-timing frontier. Only the annualized unit cost and a source-defined timing proxy met the admissibility requirements for the common matrix. The cost curves were evaluated at 30 million m3 per year because it is a common plotted point within the JICA curve domain at which all retained alternatives can be compared without extrapolation; it is not a current demand target. Supply quantities were excluded because the archive combines physical capacity, planning ceilings, staged urban allocations, and multipurpose totals. Conveyance distance was excluded to avoid double counting, because annualized costs already include the transfer system. Historical availability statements were retained only as timing proxies, not as probabilistic forecasts of project delivery. The 15–100 MCM/year check leaves the frontier and first-ranked sequence intact, with only the Gulbahar–Salang tail order changing at 100 MCM/year.

Under the baseline min–max specification, the CRITIC conflict factor was identical for both retained criteria and therefore was canceled during weight normalization, leaving normalized dispersion weights. The resulting TOPSIS model ranked Shatoot first, but the ranking was preference-dependent. The leading alternative changed from the Panjshir Fan aquifer to Shatoot at a normalized cost weight of approximately 0.288 and from Shatoot to Gat at approximately 0.941. These three alternatives form the non-dominated cost-timing set. No overall ranking of the four dams was retained because estimating correlations across eight criteria from only four alternatives produced a rank-deficient structure and weights that were highly sensitive to individual projects. Later JICA reports, donor and government records, and groundwater and climate studies provide updated context but not a contemporary seven-option matrix with consistent engineering boundaries. In practical terms, a cost weight below 0.288 represents a strong timing priority, the interval 0.288–0.941 represents a broad intermediate cost-timing preference regime, and a cost weight above 0.941 represents an extreme cost priority. These thresholds are decision language for the normalized model and not monetary thresholds or forecasts.

The main methodological contribution made here is an auditable process that traces each value to its source, classifies its meaning and system boundary, identifies dependence and uncertainty, and determines admissibility before numerical aggregation. For Kabul, the appropriate next step is to renew the evidence before any project recommendations are made. Because the audit was conducted by one analyst, future research should assess agreement between independent reviewers and test the framework’s transferability to other infrastructure archives. Because the present audit was conducted by one analyst, this submission does not report an observed inter-reviewer κ; it does specify the independent blinded coding, Cohen’s κ/weighted κ, disagreement adjudication, and the reviewer-specific rank-stability checks required for the next validation study.

Statements

Data availability statement

The data presented in this study are available upon request from the corresponding author.

Author contributions

MA: Conceptualization, Data curation, Formal Analysis, Investigation, Methodology, Project administration, Resources, Software, Validation, Visualization, Writing – original draft. MZA: Data curation, Formal Analysis, Investigation, Methodology, Project administration, Resources, Software, Writing – review and editing. SB: Conceptualization, Data curation, Formal Analysis, Methodology, Validation, Visualization, Writing – review and editing. WH: Conceptualization, Data curation, Formal Analysis, Investigation, Methodology, Software, Visualization, Writing – review and editing. ZS: Conceptualization, Data curation, Formal Analysis, Investigation, Methodology, Supervision, Visualization, Writing – review and editing.

Funding

The author(s) declared that financial support was not received for this work and/or its publication.

Conflict of interest

Author WH was employed by Geotill Engineering Inc.

The remaining author(s) declared that this work was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Generative AI statement

The author(s) declared that generative AI was used in the creation of this manuscript. The authors employed ChatGPT for language enhancement and proofreading. The final manuscript was thoroughly reviewed and edited by the authors, who assume complete responsibility for its content.

Any alternative text (alt text) provided alongside figures in this article has been generated by Frontiers with the support of artificial intelligence and reasonable efforts have been made to ensure accuracy, including review by the authors wherever possible. If you identify any issues, please contact us.

Publisher’s note

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article, or claim that may be made by its manufacturer, is not guaranteed or endorsed by the publisher.

Supplementary material

The Supplementary Material for this article can be found online at: https://www.frontiersin.org/articles/10.3389/fbuil.2026.1958158/full#supplementary-material

References

  • 1

    AbrishamchiA.EbrahimianA.TajrishiM.MariñoM. A. (2005). Case study: application of multicriteria decision making to urban water supply. J. Water Resour. Plan. Manag.131 (4), 326–335. 10.1061/(asce)0733-9496(2005)131:4(326)

  • 2

    Asian Development Bank (2015). Afghanistan: Kabul Managed Aquifer Recharge Project. Available online at: https://www.adb.org/projects/49187-002/main (Accessed July 26, 2026).

  • 3

    Asian Development Bank (2023). Afghanistan: Preparing the Kabul Managed Aquifer Recharge Project. Available online at: https://www.adb.org/projects/48440-002/main (Accessed July 26, 2026).

  • 4

    BehzadianK.KapelanZ. (2015). Advantages of integrated and sustainability based assessment for metabolism based strategic planning of urban water systems. Sci. Total Environ.527, 220–231. 10.1016/j.scitotenv.2015.04.097

  • 5

    BeltonV.StewartT. (2012). Multiple Criteria Decision Analysis: An Integrated Approach. Springer Science and Business Media.

  • 6

    BrownR. R.KeathN.WongT. H. F. (2009). Urban water management in cities: historical, current and future regimes. Water Sci. Technol.59 (5), 847–855. 10.2166/wst.2009.029

  • 7

    ChapelleC. A. (1998). “Construct definition and validity inquiry in SLA research”, in Interfaces between Second Language Acquisition and Language Testing Research. Editors BachmanL. F.CohenA. D. (Cambridge:Cambridge University Press) 32–70. 10.1017/CBO9781139524711.004

  • 8

    DodgsonJ. S.SpackmanM.PearmanA.PhillipsL. D. (2009). Multi-Criteria Analysis: A Manual.

  • 9

    FerdowsiA.PiadehF.BehzadianK.MousaviS.-F.EhteramM. (2024). Urban water infrastructure: a critical review on climate change impacts and adaptation strategies. Urban Clim.58, 102132. 10.1016/j.uclim.2024.102132

  • 10

    FortierI.RainaP.Van den HeuvelE. R.GriffithL. E.CraigC.SalibaM.et al (2017). Maelstrom research guidelines for rigorous retrospective data harmonization. Int. J. Epidemiol.46 (1), 103–105. 10.1093/ije/dyw075

  • 11

    GregoryR.FailingL.HarstoneM.LongG.McDanielsT.OhlsonD. (2012). Structured Decision Making: A Practical Guide to Environmental Management Choices. John Wiley and Sons.

  • 12

    HaasnootM.KwakkelJ. H.WalkerW. E.Ter MaatJ. (2013). Dynamic adaptive policy pathways: a method for crafting robust decisions for a deeply uncertain world. Glob. Environ. Chang.23 (2), 485–498. 10.1016/j.gloenvcha.2012.12.006

  • 13

    HajkowiczS.CollinsK. (2007). A review of multiple criteria analysis for water resource planning and management. Water Resour. Manag.21 (9), 1553–1566. 10.1007/s11269-006-9112-5

  • 14

    HashimotoT.StedingerJ. R.LoucksD. P. (1982). Reliability, resiliency, and vulnerability criteria for water resource system performance evaluation. Water Resour. Res.18 (1), 14–20. 10.1029/wr018i001p00014

  • 15

    HuangD.LiuJ.HanG.Huber-LeeA. (2023). Water-energy nexus analysis in an urban water supply system based on a water evaluation and planning model. J. Clean. Prod.403, 136750. 10.1016/j.jclepro.2023.136750

  • 16

    HussainiM. S.FarahmandA.ShresthaS.NeupaneS.AbrunhosaM. (2022). Site selection for managed aquifer recharge in the city of Kabul, Afghanistan, using a multi-criteria decision analysis and geographic information system. Hydrogeol. J.30 (1), 59–78. 10.1007/s10040-021-02408-x

  • 17

    Japan International Cooperation Agency: RECS International Inc (2009). Yachiyo Engineering Co., Ltd.: CTI Engineering International Co. L: SCI. The study for the development of the master plan for the Kabul metropolitan area in the Islamic Republic of Afghanistan final report : sector report ; 3. -Water resources. Available online at: https://openjicareport.jica.go.jp/618/618/618_301_11965167.html (Accessed July 26, 2026).

  • 18

    Japan International Cooperation Agency (2023). Japan International Cooperation Agency: T and Associates I. Data Collection Survey on Urban Development in Afghanistan: Final Report. Available online at: https://openjicareport.jica.go.jp/618/618/618_301_12373056.html (Accessed July 26, 2026).

  • 19

    Japan International Cooperation Agency (2013). Yachiyo Engineering Co. L: SCI. Feasibility Study on Urgent Water Resources Development and Supply for Kabul Metropolitan Area the I Slamic Republic of Afghanistan: Final Report, 1. Tokyo, Japan: CTI Engineering International Co., Ltd.Available online at: https://openjicareport.jica.go.jp/618/618/618_301_12120390.html (Accessed July 26, 2026).

  • 20

    Japan International Cooperation Agency (2018). Japan International Cooperation Agency : Yachiyo Engineering Co. L Implementation Review Study Report on the Project for Improvement of Water Supply Facilities in Dehsabz Southe Area. Available online at: https://openjicareport.jica.go.jp/618/618/618_301_12322756.html (Accessed July 26, 2026).

  • 21

    KeeneyR. L. (1996). Value-Focused Thinking: A Path to Creative Decisionmaking. Harvard University Press.

  • 22

    KhatiwadaK. R.PradhanangaS.NepalS. (2024). Inferring the impacts of climate extreme in the Kabul River Basin. Reg. Environ. Chang.24 (1), 17. 10.1007/s10113-023-02167-3

  • 23

    LimF. H.LeeW. K.IshakA. M.HasanA. A.KhorJ. W. S.SulaimanMNIAet al (2023). Multi-criteria evaluation for long-term water resources augmentation planning with consideration of global change. Environ. Adv.12, 100375. 10.1016/j.envadv.2023.100375

  • 24

    MarttunenM.MustajokiJ.LehtorantaV.SaarikoskiH. (2022). Complementary use of the ecosystem service concept and multi-criteria decision analysis in water management. Environ. Manage69 (4), 719–734. 10.1007/s00267-021-01501-x

  • 25

    Ministry of Energy and Water of Afghanistan (2023). The acting minister of energy and water visited the Gulbahar/Panjshir Dam area. Available online at: https://mew.gov.af/en/acting-minister-energy-and-water-visited-gulbaharpanjshir-dam-area (Accessed July 26, 2026).

  • 26

    MoorthyR.BibiS. (2023). Water security and cross-border water management in the Kabul River Basin. Sustainability15 (1), 792. 10.3390/su15010792

  • 27

    MoreauL.CliffordB.FreireJ.FutrelleJ.GilY.GrothP.et al (2011). The open provenance model core specification (v1. 1). Futur Gener. Comput. Syst.27 (6), 743–756. 10.1016/j.future.2010.07.005

  • 28

    NazariA.ZaryabA.MikhailovichC. (2025). Numerical groundwater modeling for sustainable management of the Kabul urban aquifer. Model Earth Syst. Environ.11, 252. 10.1007/s40808-025-02435-7

  • 29

    RodeO.MatherM.OliverD.NelsonK.ReedV.MooreT.et al (2025). A framework tool that applies weight-of-evidence integration to the analysis of existing datasets to guide freshwater conservation. Front. Freshw. Sci.3, 1520312. 10.3389/wsc.2025.1520312

  • 30

    SaikiaP.BeaneG.GarrigaR. G.AvelloP.EllisL.FisherS.et al (2022). City Water resilience framework: a governance based planning tool to enhance urban water resilience. Sustain Cities Soc.77, 103497. 10.1016/j.scs.2021.103497

  • 31

    ShahT. M.EgwuC. O.HammadM.OtterpohlR. (2024). Decision support systems based on a multiple-criteria decision analysis to promote a whole-of-resource approach for water management, with a case study of rural Bengaluru in India. Water16 (12), 1674. 10.3390/w16121674

  • 32

    ShamsA. K.MuhammadN. S. (2023). Towards sustainable transboundary water cooperation between Afghanistan and Pakistan: a case study of Kabul River. Ain Shams Eng. J.14 (2), 101842. 10.1016/j.asej.2022.101842

  • 33

    TaherM. R.ChornackM. P.MackT. J. (2014). Groundwater Levels in the Kabul Basin, Afghanistan, 2004-2013. Open-File Rep.

  • 34

    TanS.YaoL. (2023). Managing and optimizing urban water supply system for sustainable development: perspectives from water-energy-carbon nexus. Sustain Prod. Consum.37, 39–52. 10.1016/j.spc.2023.02.004

  • 35

    ThakurK.SinghI.SharmaP. (2024). A systematic review of integrated urban water management (IUWM). Environ. Dev. Sustain28, 1–30. 10.1007/s10668-024-05649-4

  • 36

    WangW.WangX.ChenY.LiuC.ZhangY. (2024). Unconventional resources: provenance analysis, sediment transport, reservoir evaluation, geo-energy. (Lausanne, Switzerland: Frontiers Media SA) Earth Sci.12, 153020010.3389/feart.2024.1530200

  • 37

    WongT. H. F.BrownR. R. (2009). The water sensitive city: principles for practice. Water Sci. Technol.60 (3), 673–682. 10.2166/wst.2009.436

  • 38

    World Bank (2018). Mainstreaming Water Resources Management in Urban Projects: Taking an Integrated Urban Water Management Approach - A Guidance Note (English). Available online at: https://documents.worldbank.org/en/publication/documents-reports/documentdetail/633731521818888260 (Accessed July 26, 2026).

  • 39

    World Bank (2020). Afghanistan - water, sanitation, hygiene and institutional support project (English). Available online at: https://documents.worldbank.org/en/publication/documents-reports/documentdetail/511191608001607905.

  • 40

    ZanioloM.GiulianiM.HermanJ. D. (2026). Toward joint information selection and policy learning in water resources management. Water Resour. Res.62, e2025WR042745. 10.1029/2025WR042745

  • 41

    ZaryabA.NasseryH. R.AlijaniF. (2022). The effects of urbanization on the groundwater system of the Kabul shallow aquifers, Afghanistan. Hydrogeol. J.30 (2), 429–443. 10.1007/s10040-021-02445-6

  • 42

    ZhaoJ.SmithT.LavigneM.AenishaenslinC.CoxR.FazilA.et al (2022). A rapid literature review of multi-criteria decision support methods in the context of one health for all-hazards threat prioritization. Front. Public Heal10, 861594. 10.3389/fpubh.2022.861594

Summary

Keywords

archival data, evidence comparability, infrastructure decision-making, multicriteria decision analysis, Pareto analysis, urban water supply, Kabul

Citation

Amini M, Amini MZ, Bawa S, Hassan W and Shnizai Z (2026) Evidence-concordance audit before multicriteria ranking: reassessing Kabul’s historical water-supply options. Front. Built Environ. 12:1958158. doi: 10.3389/fbuil.2026.1958158

Received

04 August 2026

Revised

03 September 2026

Accepted

07 September 2026

Published

09 November 2026

Volume

12 - 2026

Edited by

Shixian Luo, Southwest Jiaotong University, China

Reviewed by

Syed Shahid Shah, Beihang University, China

Yongxing Qian, Ningbo Institute of Technology, Zhejiang University, China

Updates

Copyright

*Correspondence: Mohammad Amini,

Disclaimer

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.