ORIGINAL RESEARCH article

Front. Phys., 04 November 2026

Sec. Statistical and Computational Physics

Volume 14 - 2026 | https://doi.org/10.3389/fphy.2026.1946795

Leakage-resistant graph learning for risk propagation and risk-constrained control in construction supply networks

  • 1. School of Architectural Engineering, Sichuan University of Arts and Science, Dazhou, Sichuan, China

  • 2. College of Intelligent Construction and Manufacturing, Sichuan Technology and Business University, Chengdu, Sichuan, China

Abstract

Introduction:

Construction supply network decisions require both predecision warning from information available before operations unfold and topology-aware diagnosis after the disruption context becomes visible. We introduce an auditable framework that separates these regimes through a strict start-of-week information contract and connects risk scores to safety-gated resource allocation.

Methods:

We combined public SUCCESS construction-logistics records with a frozen queue-flow mechanism producing paired counterfactual outcomes on a heterogeneous network with 302 nodes and 1,277 edges. Models were trained on pilots A and B, selected on pilot C, and evaluated on pilot D. The strict contract excluded all week-t outcomes, service levels, and shock-source indicators. Complementary evaluations comprised context-aware diagnosis, a construction consolidation center (CCC) outage panel, leave-one-project-out evaluation, and an independent SupplyGraph boundary test. Six resource policies were compared through validation-only selection and a held-out Pareto audit.

Results:

Under the strict contract, the graph convolutional network achieved the highest held-out area under the precision–recall curve (AUPRC) of 0.2397 and area under the receiver operating characteristic curve (AUROC) of 0.8161 for 4,252 node-weeks with 60 positives. In the context-aware regime, relational GraphSAGE achieved an AUPRC of 0.5702, exceeding the matched multilayer perceptron (MLP) by 0.0803. Across eight positive pairs involving CCC outages, GraphSAGE achieved an AUPRC of 0.5845 versus 0.4994 for the MLP, with a positive pair-specific advantage in each case. The calibrated-risk guardrail identified an aggregate service improvement of 0.827% but screened the allocation out because the affected sites and failure durations increased. The held-out frontier also identified a deficit-only allocation that improved unserved demand, affected sites, and failure durations without overriding the predeclared deployment rule.

Discussion:

The framework combines leakage-resistant graph evaluation, context-aware relational diagnosis, project-level applicability testing, and risk-gated network control. Its explicit safety gate prevents aggregate efficiency gains from concealing propagation-risk transfer.

1 Introduction

Construction logistics includes a temporary but tightly coupled system of suppliers, sites, consolidation centers, vehicles, and material-specific routes. A capacity loss at a single supplier or facility can increase the backlogs at several sites; the resulting competition for transport and inventory can then redirect scarcity through the network. Such behaviors are naturally described by complex-network physics, in which the topology, time-dependent node states, and local constraints jointly determine spreading and resilience [1–3]. Interdependent systems can experience cascades that are not visible from the isolated components [4], and interventions may change both the propagation paths and aggregate services [5, 6].

The practical importance of such systems is immediate. Construction delays may arise from not only the directly disrupted entity but also shared-resource competition among the otherwise undamaged sites. A useful method must therefore address two different concerns: identify the sites that are at risk before failure occurs, and a feasible allocation scheme that improves service without worsening the propagation elsewhere. Treating the first concern as an ordinary row-wise classification problem can leak information generated after the decision time. Treating the second concern as a simple ranking exercise can allocate scarce capacity toward high-scoring sites while causing a larger failure at another node.

Supply-chain research has long emphasized the importance of uncertainty, coordination, and network exposure [7–10]. Construction-specific evidence further shows that fragmented procurement, temporary project organization, delivery uncertainty, and incomplete digital records are persistent obstacles [11]. Recent construction studies have used complex networks and dynamic models to identify vulnerable nodes and propagation mechanisms [12–14], while the broader value-chain studies have shown how shocks follow trade geometry and directed dependencies [15–17]. However, three gaps remain: propagation labels and intervention outcomes have seldom been observed at node-week resolution; strong discrimination may be created by variables that are contemporaneous with failure, such as ending backlog, served quantity, or service level; predictive improvement does not guarantee an acceptable allocation under shared capacity.

We address these gaps through an auditable and data-grounded semi-synthetic design. First, public SUCCESS records were used to determine the construction entities, demand templates, supplier–material relations, consolidation options, vehicles, and directed travel costs. Then, a frozen queue-flow mechanism was used to supply disruption counterfactuals that were explicitly distinguished from the observed events. Next, pilot components were used to define the project-level splits. Most importantly, we introduced a start-of-week temporal information contract, where a prediction for week may use only static attributes and the opening states known at that decision time, along with the three previous weekly values. The contract prohibited the week- inbound mass, served mass, ending inventory, ending backlog, service level, and all shock-source indicators. Our study was centered on one question: could a construction-network framework preserve useful topology signals while guaranteeing temporal validity and preventing risk transfer during allocation? We attempted to answer this question through four coordinated evaluations: a strict predecision benchmark under equal feature availability and tuning budgets; a context-aware relational diagnostic test; project-level and cross-domain applicability checks; a validation-based policy frontier with explicit propagation-risk guardrails.

The main contributions of our study are as follows: (i) a dual-regime information architecture that separates leakage-resistant early warning cleanly from context-aware diagnosis; (ii) evidence that typed relations provide a reproducible diagnostic ranking advantage when the disturbance context and edge semantics are aligned; (iii) a project-level applicability map that treats the network realizations rather than the individual node-weeks as the generalization unit; (iv) a safety-gated Pareto framework that prevents aggregate service gains from masking propagation-risk transfer. These capabilities transform our graph-based risk analysis into an auditable decision pipeline rather than an unconstrained score.

2 Related works

2.1 Complex-network shock propagation

Classical cascade models explain how interdependence and load redistribution can convert local failures into network-wide transitions [4, 5]. Temporal network theory emphasizes that the order and durations of the interactions are as important as aggregate connectivity [2]. Recent works have moved toward mechanism-specific resilience: graph coloring protection can be used to identify critical intervention sets [19], flow-weighted hypermotifs help expose local vulnerability patterns [20], recovery-aware models can change both the cascade extent and timing [21], and decentralized flow control shows how rerouting decisions interact with capacity [22]. At the value-chain scale, network analyses have quantified economic shock transmission [15], changes in the geometry of international trade [16], and formal representations of global value-chain networks [17]. Together, these studies motivate a model in which the typed edges, delayed states, and constrained control are evaluated jointly.

2.2 Temporal and heterogeneous graph learning

Graph convolutional networks (GCNs) aggregate normalized neighbor information [23], while GraphSAGE learns inductive neighborhood functions [24], and relation-specific convolutions preserve the heterogeneous edge semantics [25]. Dynamic extensions can be used to update the graph parameters across snapshots, as in EvolveGCN [26], or can use the event-time memory and message functions, as in temporal graph networks [27]. These architectures are appropriate when the topology or node state evolves, but their flexibility does not eliminate the need for a valid prediction time. If a feature is produced after a decision, then a temporal model can learn the leakage more efficiently rather than solving it. SupplyGraph provides a public temporal network of fast-moving consumer goods for graph-based supply planning [28]; its independent reanalysis documents duplicate the identifiers, sparse series, and preprocessing sensitivity [29]. A firm-level study also showed that a supply-chain-specific graph architecture can improve the production-function and transaction forecasts when the edge meanings are aligned with the targets [30]. Our construction task is different because the target is the first counterfactually attributable downstream service failure, the directly shocked sites are excluded, and the graph score is evaluated inside a capacity-constrained decision rule.

2.3 Construction analytics, resilience, and digital twins

Construction analytics now spans multiple decision levels: contractual design and long-term warranties address institutional allocation of risk [31]; game-theoretic works explore coordination and cost under uncertainty [32, 33]; and labor and insurance regulations provide a complementary safety-governance perspective [34]. Some predictive and optimization studies have covered ensemble safety analytics [35], equipment management [36], evidential quality management [37], and building-information-modeling-based clash detection with XGBoost [38]. However, climate-adaptive pavement and asset-management studies have extended this reasoning to lifecycle and environmental uncertainty [39, 40], while machine-learning studies have examined seismic fragility and climate-related productivity [41, 42]. Digital twins link these data streams to resilience-oriented designs [43]. Although these adjacent studies have established the growing roles of data-driven construction management, they address different targets and decision authorities. Construction supply-chain propagation has been examined using epidemic-style or complex-network models [12–14], spatiotemporal shipment analysis [44], integrated production–construction network design [45], and delay-aware stochastic allocation [46]. The unresolved common factor here is a leakage-resistant test of learned graph propagation followed by a risk-constrained allocation test on the same typed network.

2.4 Rare events, calibration, and learning with optimization

Propagation failures are often rare and clustered. Therefore, precision–recall analysis is more informative than receiver operating characteristic (ROC) analysis alone [47, 48], while probability calibration must be assessed separately from ranking [49]. Gradient-boosted trees [50] and gated recurrent models [51, 52] are important comparators because they can capture the non-linear tabular interactions and temporal dependences without graph message passing. Prediction and prescription should also be distinguished; decision-focused learning couples the predictive models to downstream combinatorial objectives [53], whereas robust optimization protects the decisions against uncertain coefficients and scenarios [54]. Our design enforces this distinction such that the predictor is trained for ranking, calibration is fitted only on the validation data, and the policy candidates are evaluated through a separate robust selection rule. The resulting risk gate converts a potentially hidden service–propagation tradeoff to an explicit feasibility decision.

Simulation-to-real research shows that transfer depends on alignment between the computational environment and deployment setting [55]. Similarly, counterfactual reasoning requires explicit distinction between the paired potential outcomes and an observed causal effect [56]. In this study, we use paired queue-flow trajectories to isolate the registered disturbance within the frozen mechanism while the claims remain tied to predictive ranking and policy comparison. Learning-augmented optimization allows aligning the prediction with downstream cost [57]; our policy audit shows how the explicit propagation-risk constraints and independent project evaluations can make such alignments operationally accountable.

3 Materials and methods

3.1 Study design and evidence hierarchy

The workflow in this study encompassed five frozen layers, namely, source-data audit, heterogeneous graph construction, counterfactual scenario generation, propagation learning, and resource reallocation. Each layer produced a manifest, the acceptance tests, and the SHA-256 commitments to the inputs and outputs. A downstream layer can be executed only after its parent gate is passed. Figure 1 shows the overall research framework separated into the primary construction analysis, external structural boundary, targeted mechanism panel, and policy decision. The SUCCESS records were treated as observed source data, and supplier capacities that were not recorded in SUCCESS were considered as frozen proxies and not measured capacities. The disruptions, paired outcomes, propagation labels, and policy effects were considered as simulator-derived counterfactual quantities. The model comparisons were predictive rather than causal, and the policy experiments compared the allocation rules under identical computational authorities. These distinctions were retained in every result and claim. The overall steps in the proposed framework are outlined in Algorithm 1.

FIGURE 1

Algorithm 1

  • Require: audited files ; graph rules ; label rules ; scenario pairs ; capacities

  • Ensure: project-fold metrics ; policy frontier ; acceptance decision

  •  1: verify schemas, units, identifiers, hashes, and parent gates

  •  2: TYPEDGRAPH

  •  3: for all paired scenarios do

  •  4: QUEUEFLOWCOUNTERFACTUAL

  •  5: FIRSTATTRIBUTABLEFAILURE

  •  6: end for

  •  7: STARTOFWEEKCONTRACT

  •  8: remove week- outcomes, service levels, and shock-source fields

  •  9: tune every candidate on pilot C under its frozen four-setting budget

  •  10: refit three seeds on pilots A–B and evaluate pilot D once

  •  11: for all held-out pilot do

  •  12:   record fixed-protocol GCN and logistic metrics on project

  •  13: end for

  •  14: fit Platt calibration on pilot C only and enumerate policy set

  •  15: ROBUSTSELECT

  •  16: PARETOAUDIT

  •  17:

  •  18: return

Leakage-controlled graph learning and risk-gated resource allocation.

3.2 SUCCESS data, sample construction, and target distribution

The SUCCESS Zenodo record contains seven comma-separated value files released for urban construction consolidation center (CCC) research [18]. The audit involved checking the record identity, file hashes, schema, uniqueness, non-negative demand, weekly continuity, directed origin–destination costs, and referential integrity. The source counts and analytical sample sizes are reported in Table 1. The strict construction graph contained 302 unique physical nodes comprising 37 compatible sites, 240 suppliers, and 25 candidate CCCs; typed identifiers were used to prevent collisions. The 1,277 operational edges comprised 1,009 primary supplier–site, 240 supplier–CCC, and 28 CCC–site relations, and no cross-pilot edge was permitted.

TABLE 1

ItemCount or value
CCC options/construction sites in the source25/99
Unique suppliers/supplier–material rows240/407
Demand definitions/demand-period rows1,277/93,663
Directed origin–destination rows/vehicle classes38,640/5
Nodes/typed operational edges302/1,277
Executed scenarios/counterfactual pairs80/32
Graph snapshots/total node-week rows1,682/114,197
Strictly labeled node-weeks, A/B/C/D3,461/1,217/1,245/4,252
Strict positives, A/B/C/D120/52/80/60
Positive prevalence, A/B/C/D3.47%/4.27%/6.43%/1.41%
Number of positive pairs, A/B/C/D3/2/3/1

Source data, network, and labeled sample characteristics.

The source data were highly sparse, with 91.684% of the demand-period rows containing both zero demand and zero delivery. The inactive weeks were designated as service level one and excluded from failure labeling. Fifteen site-size values were missing, including all the pilot D values, so area was not used to scale demand. The material-specific CCC capacity columns had undocumented units and were excluded from kilogram constraints. The positive-kilogram and zero-volume records were treated as missing volume proxies rather than zero occupancy. The executed learning set contained 80 disrupted/baseline members arranged in 32 counterfactual pairs. After applying the site and horizon masks, pilots A, B, C, and D contributed 3,461/120, 1,217/52, 1,245/80, and 4,252/60 labeled node-weeks/positives, respectively. Thus, the positive prevalence ranged from 1.41% to 6.43%. The number of positive pairs for pilots A–D were 3, 2, 3, and 1, respectively. This uneven distribution is central to the uncertainty analysis; the node-weeks were not treated as independent projects.

3.3 Queue-flow dynamics and attributable propagation target

For site during week , the effective demand is the sum of the combined scheduled demand and opening backlog , as shown in Equation 1:

The served mass is bounded by the effective demand, opening inventory, inbound flow, and registered shared capacities. The backlog evolves as shown in Equation 2, and the service level is given by Equation 3:

The baseline and disrupted trajectories use independent copies of the same capacity map. The mass-balance, inventory, and capacity residuals are checked after every execution. A site is considered to have failed when the service level is below 0.80 for two consecutive active-demand or positive-backlog weeks. A disrupted-trajectory failure is attributable only if it is new or occurs earlier than in the paired baseline. For a 4-week horizon, the failure (Equation 4) is given bywhere and are the first failed weeks in the disrupted and baseline trajectories, respectively, and is the set of directly shocked sites. The direct demand-surge targets and route-shock destination sites were excluded, while intervals without the consecutive four weeks and observations at or after the first attributable failure were censored.

3.4 Strict temporal information contract and feature selection

The prediction was issued at the start of week , and the strict input contained the opening states for {}. The available dynamic variables were opening inventory, opening backlog, scheduled demand, and active-demand status. Eleven static variables were used to encode the node type, log degree, project value, site size and missingness, supplier material/vehicle counts and missingness, and CCC capacity. A history-availability indicator was used to distinguish zero padding from an observed zero value. Flattening the four weekly states and the static attributes yielded 31 tabular/graph features; all sequential models received 16 dynamic sequence channels and the static attributes. The following week- quantities were prohibited because they are generated during or after the decision week: effective demand after backlog update, inbound mass, served mass, ending inventory, ending backlog, and service level. The shock seed, shock activity, and shock type were also excluded. Thus, the strict analysis considers whether the ordinary opening-state trajectories and topology forecast an attributable failure before the operational consequences of the current week are observed. Figure 2 shows the precise timeline for the contract and predictions.

FIGURE 2

The features were selected by physical availability and role, not by the test-set significance. Training-only point-biserial correlations were used as the descriptive diagnostics. The largest absolute correlation obtained was 0.195 for the current opening backlog; the remaining non-constant features were at or below 0.082. Because the rows are clustered by project and scenario, these coefficients were not assigned row-wise -values and were not used to screen the features; this avoids selecting inputs after observing the pilot D associations. For comparison, the context-available specification retained 27 variables, including the contemporaneous inbound, served mass, ending state, service level, and six shock-context fields. This answers a complementary question regarding the near-term diagnosis after the active disturbance and week- operating response are visible while providing an information-rich diagnostic regime for the framework.

3.5 Predictive models and fair selection protocol

Eight strict predictors were compared: the non-neural comparators were a backlog heuristic, class-weighted logistic regression, and XGBoost [50]; the neural comparators were a multilayer perceptron (MLP), a gated recurrent unit (GRU) sequence model [52], a two-layer GCN, a two-layer relational GraphSAGE, and a temporal relational GraphSAGE that encoded the four weekly states with a GRU before relation-specific aggregation. This set covers linear, non-linear tabular, recurrent, homogeneous-graph, heterogeneous-graph, and temporal-heterogeneous inductive biases. Every neural family received the same four configurations: a hidden dimension of 32 or 64 with a dropout of 0.1 or 0.3, a learning rate of , and a validation seed of 11. Logistic regression was performed using four values of (0.1, 1, 10, and 100). The XGBoost scheme used four combinations of depth 3 or 5 and 200 or 300 estimators, along with a paired learning rate of 0.05 or 0.03. The area under the precision–recall curve (AUPRC) for pilot C was obtained using one configuration per family; the selected configuration was then fitted with seed values of 11, 23, and 37 for pilots A and B, and the probabilities were averaged. Pilot D was evaluated only once. The thresholds were selected on pilot C using the validation F1-score and were not optimized on pilot D.

For relation type and layer , relational aggregation was performed using Equations 5, 6:where contained the primary supply, supplier–CCC, and CCC–site edges. The neural parameters minimized the class-weighted binary cross-entropy on pilots A and B only, as shown in Equation 7:

The AUPRC was the primary metric because the positives were rare; the area under the ROC curve (AUROC), Brier score, precision, recall, and F1-score were the secondary metrics. Regression metrics such as the root mean-squared error (RMSE), mean absolute error (MAE), coefficient of determination (), and weighted absolute percentage error (WAPE) were used only for the external forecasting task. The mean absolute percentage error was not reported because the daily product demand contains zeros, which would render the percentage errors undefined or arbitrarily large; the WAPE preserves an interpretable denominator at the test-set level.

3.6 Project-level uncertainty and boundary analyses

For the four projects, our analysis reports the leave-one-project-out (LOPO) AUPRC values, ranges, medians, and fold-wise winners rather than a population confidence interval. For each held-out project, another project served as the validation while the remaining two were used for training; the hyperparameter protocol remained fixed. These values form an explicit map of the observed project variation. The bootstrapped counterfactual-pair results from the earlier context-available analysis are provided in the Supplementary Material. The original pilot D context test had eight pairs with a single positive pair. A targeted CCC-outage panel later added eight positive timing–duration pairs without retraining; this was a mechanism stress test on the same topology and not an independent project replication.

SupplyGraph provided an independent structural boundary [28, 29]. The frozen audit retained 29 of the 40 unique products, 221 contiguous days, and 339 directed plant pairs. The five-day histories of the sales order, production, factory issue, and delivery to distributor values were used to predict the next-day sales order. The dates were split chronologically into 129 training, 43 validation, and 44 test values. The MLP, GCN, GraphSAGE, and topology-shuffled GraphSAGE used the same signals and seeds; this experiment tests whether the topology benefit transfers to a different supply-domain target and thereby maps the scope of the construction result.

3.7 Resource policies, calibration, robust selection, and Pareto audit

All policies were implemented with identical supplier, route, CCC, and fleet-work capacities at a factor of 0.85 without any added capacity. For a request , path , resource , and week , we havewhere is the resource claim of a path and is the requested mass. The HiGHS solver was used to solve the path-flow programs in Equation 8, and the numerical projections ensured that each execution remained within the registered capacity [58]. Six candidates were evaluated for the calibrations as follows: frozen value (reference), value-only flow, deficit-only flow, risk/deficit/value weights (0.4, 0.4, 0.2), weights (0.6, 0.2, 0.2), and a calibrated-risk guardrail with the latter weights. The raw context-available GraphSAGE scores were calibrated on pilot C using Platt scaling [59], as shown in Equation 9:

The guardrail threshold for pilot C was 0.06297. The calibration placed the validation scores on an operationally usable scale for policy screening; the intervention comparison was used as a policy evaluation rather than a causal effect estimate. For each feasible validation candidate (defined as that which does not increase the aggregate affected sites or failure node-weeks relative to the frozen value), robust selection was used to minimize the worst scenario-level absolute change in unserved demand, with the mean change as the tiebreaker. We selected the calibrated-risk guardrail for pilot C and then evaluated all the candidates on pilot D without reselecting the policy.

The primary efficiency outcome was the cumulative unserved demand in kilogram-week, while the risk outcomes were the affected sites and failure node-weeks . The condition for acceptance was

The Pareto efficiency was assessed jointly for and each risk outcome, and an aggregate weighted score could not override the risk-guardrail infeasibility.

3.8 Reproducibility and implementation

In our analyses, we used Python, PyTorch, scikit-learn, NetworkX, SciPy, XGBoost, and HiGHS [50, 58, 60–63]. The manifest files contained fixed data hashes, features, labels, scenario memberships, splits, seeds, model budgets, and policy definitions. The unit tests covered flow conservation, capacity feasibility, counterfactual isolation, direct-site exclusion, temporal availability, and positive/negative controls. All of our derived data, code, and execution records are available from the corresponding author upon reasonable request.

4 Results

4.1 Strict temporal contract identified the strongest predecision model

Under the strict information contract, the GCN achieved the highest AUPRC (0.2397) and AUROC (0.8161) on pilot D, making it the leading predecision ranking model under the shared protocol (Table 2 and Figure 3). This was closely followed by logistic regression (AUPRC of 0.2355), while the GRU achieved an AUPRC of 0.2013. All learned models achieved AUPRC values above the positive prevalence of 0.0141. The benchmark also exposed some complementary operating points: At the validation-selected threshold, logistic regression achieved the highest F1-score (0.3158), with a precision of 0.7500, while GRU and temporal relational GraphSAGE provided high-sensitivity settings with a recall of 0.9333.

TABLE 2

ModelAUPRCAUROCBrierF1-scorePrecisionRecall
GCN0.23970.81610.25200.19400.17570.2167
Logistic regression0.23550.56840.40400.31580.75000.2000
GRU0.20130.62760.26050.03240.01650.9333
Relational GraphSAGE0.18520.69010.23410.18060.15480.2167
Temporal relational GraphSAGE0.14130.65130.26400.03240.01650.9333
MLP0.13220.52980.26610.23190.88890.1333
Backlog heuristic0.11510.56650.01410.23190.88890.1333
XGBoost0.03340.47440.34160.03410.01820.2833

Strict start-of-week performance on the held-out pilot D (; 60 positives).

The best values are shown in boldface, and lower values are considered better for the Brier score.

FIGURE 3

Together, the strict and context-available analyses define two complementary operating regimes (Table 3). In the context-aware diagnosis, relational GraphSAGE achieved an AUPRC of 0.5702 and exceeded the matched MLP by 0.0803. Removing the shock localization yielded an AUPRC of 0.4828, while collapsing the relation types yielded an AUPRC of 0.4170, directly attributing the diagnostic advantage to context and typed edge semantics. Under the predecision contract, the GCN provided the best leakage-resistant screening. Therefore, our framework assigns relational GraphSAGE to information-rich diagnosis and GCN to strict early warning instead of treating the two estimands interchangeably.

TABLE 3

SpecificationAUPRCAUROCInterpretation
Relational GraphSAGE0.57020.8331Full diagnostic context
GCN0.55530.8404Homogeneous graph
Logistic regression0.52720.8045Local linear
MLP0.48990.8040Local non-linear
Relation types collapsed0.4170–Edge semantics removed
Shock-source fields removed0.4828–Shock localization removed

Context-aware diagnostic performance on pilot D. These inputs include contemporaneous operating and shock context while defining a complementary estimand to strict early warning.

The best values are shown in boldface.

4.2 Project-level evaluation mapped the complementary inductive biases

The LOPO AUPRC ranged from 0.0677 to 0.2397 for the GCN and from 0.0439 to 0.2513 for logistic regression (Table 4). The median AUPRC was 0.1786 for the GCN and 0.2364 for logistic regression. The GCN was better for folds B and D, while logistic regression was better for folds A and C. Reporting each project explicitly turns this variation into an applicability map: the relational structure and local opening-state trends provide complementary inductive biases whose values depend on the project composition.

TABLE 4

Held-outValidationTrainingPositivesLogisticGCN
ABC + D1200.23720.2182
BCA + D520.04390.0677
CDA + B800.25130.1391
DCA + B600.23550.2397
Median–––0.23640.1786
Range–––0.0439–0.25130.0677–0.2397

Fixed-protocol leave-one-project-out AUPRC.

The validation pilot and two training pilots are shown explicitly, and the best values are shown in boldface.

4.3 Mechanism and external-network tests localized the topological advantage

The target CCC-outage panel contained eight positive pairs, 2,864 labeled node-weeks, and 420 positives. For the original frozen context-available checkpoints, relational GraphSAGE achieved an AUPRC of 0.5845 versus 0.4994 for the MLP; here, each pair-specific difference was positive (range: 0.0544–0.1268). The frozen models and uniformly positive pair differences provide mechanism-level reproducibility for context-aware relational diagnosis across the registered CCC timing–duration profiles. The independent SupplyGraph test assigned the best forecasting metrics to the MLP (Table 5), with an RMSE of 1,637.4 compared to 1,988.6 for the GCN and 3,142.8 for GraphSAGE. Thus, its plant-edge view provides a useful external boundary: the graph benefit emerges when the edge semantics, information timing, and prediction target are all aligned rather than from the supply network label alone.

TABLE 5

ModelRMSEMAEWAPE
MLP1,637.4675.70.26480.7651
GCN1,988.6842.40.9539
GraphSAGE, shuffled topology2,602.3840.60.9519
GraphSAGE3,142.8921.81.0438

Independent SupplyGraph results on 44 chronological test dates and 29 products.

The best values are shown in boldface.

4.4 Risk-gated policy audit separated the efficiency from propagation safety

Pilot C selected the calibrated-risk guardrail among the validation-feasible policies. On the 32 pilot D scenarios, this reduced the total unserved demand from 4,514,115 to 4,476,777 kg-week, which is a 37,338 kg-week (0.827%) aggregate improvement. The joint audit also detected an increase from seven to eight affected sites and from 74 to 77 failure node-weeks, so the acceptance rule of Equation 10 screened the allocation out. This is the intended safety function of the gate: an aggregate efficiency gain cannot authorize propagation-risk transfer. The full frontier reveals why policy ranking cannot be summarized by a single weighted score (Table 6; Figure 4). The (0.4, 0.4, 0.2) risk policy produced the largest aggregate service gain (1.329%), while the joint risk coordinates rendered the additional affected sites and duration visible immediately. The deficit-only flow reduced the unserved demand by 0.561%, affected sites from seven to six, and duration from 74 to 72, making it Pareto efficient on pilot D. Because this held-out Pareto point was outside the validation-feasible set on pilot C, it is retained as a preregistered candidate for future evaluation rather than for overriding the original selection rule.

TABLE 6

PolicyUnserved demand (kg-week)Change (%)Affected sitesFailure node-weeksStatus
Frozen value4,514,1150.000774Reference
Value only4,569,936+1.237978Dominated
Deficit 4,488,807672Exploratory
Risk 0.4*4,454,107977Outside risk gate
Risk 0.6*4,476,777877Outside risk gate
Calibrated 4,476,777877Selected; screened out

Policy frontier on the 32 held-out pilot D scenarios. The percentage change is relative to the frozen value, and a negative percentage change in unserved demand indicates improvement.

a

Selected on pilot C before inspecting the pilot D outcomes.

The asterisks denote the Pareto-efficient held-out points, and the best values are shown in boldface.

FIGURE 4

The scenario-level audit added a complementary robustness view. The calibrated policy improved the unserved demand in 17 of 32 scenarios, with a worst scenario change of kg-week; the deficit-only case improved 14 scenarios, with a worst change of kg-week. Together with the affected-site and duration counts, these diagnostics show why the joint guardrails provide decision information that an average service score alone cannot supply.

5 Discussion

5.1 Dual-regime architecture links strict warning and relational diagnosis

The central contribution of this work is a dual-regime architecture for two operationally distinct concerns. In context-aware diagnosis, the typed relations and explicit shock localization enabled relational GraphSAGE to achieve an AUPRC of 0.5702 and a 0.0803 advantage over the matched MLP. Under the start-of-week contract, the GCN provided the strongest predecision ranking with an AUPRC of 0.2397 and AUROC of 0.8161. Rather than forcing a single model to serve incompatible information conditions, the proposed framework assigns relational diagnosis and leakage-resistant screening to the settings in which their inductive biases are most useful. This distinction matters beyond implementation. The ending backlog and service level are physically meaningful inputs for within-week monitoring, whereas the opening states define the predecision information set. Similarly, the shock-source fields support situational awareness after a disruption is identified. By making these screenings explicit, the framework preserves the strong relational diagnostic signal without relabeling it as start-of-week evidence.

The findings identify the conditions under which the graph structure is valuable. Typed edges contribute maximally when they represent the mechanism linking disturbance origin, operating response, and downstream failure [30]; the uniformly positive CCC-panel differences reinforce this mechanism-specific advantage. The SupplyGraph boundary test complements such evidence by showing that a different target and edge view call for a different inductive bias. This applicability map is consistent with temporal graph neural network (GNN) theory: dynamic encoders represent delayed interactions [26, 27], while event definition and topology quality determine which representation is informative.

5.2 Project-level validation maps the complementary inductive biases

The pair-level and project-level analyses quantify different yet complementary uncertainty axes. The target CCC panel measures mechanism consistency across eight positive timing–duration pairs, where the relational GraphSAGE exceeded the MLP in all pairs. The LOPO evaluation maps project variation: the GCN performed better on two held-out projects while logistic regression performed better on the remaining two projects. Presenting the analyses for both levels converts the variation into an explicit guide for model selection and deployment scope. This separation prevents a common inferential error: thousands of node-weeks do not create thousands of independent network realizations. Treating the project and scenario mechanisms as the external units yields a more decision-relevant evidence hierarchy than a row-wise confidence interval. The same hierarchy provides a clear expansion path through additional independently collected construction projects and preregistered disruption clusters.

5.3 Risk gates enable explicit decision quality

The policy frontier delivers a second substantive contribution: the calibration and direct risk guardrail convert a hidden network tradeoff into an explicit decision rule. The validation-based policy improves the aggregate service by 0.827%, while the joint gate detects the accompanying changes in affected sites and failure durations along with screening the allocation out. This demonstrates the value of safety-gated control in an interdependent system, where an intervention can redirect burden through competing paths and downstream thresholds [5, 22]. The deficit-only Pareto point provides a concrete design direction: on pilot D, it jointly improved the unserved demand, affected sites, and failure durations. The prospective protocol correctly preserves it as a candidate for evaluation on new projects rather than using a held-out discovery to replace the validation-based policy. A next-stage formulation would involve placing and limits directly in the feasible region, optimizing over project/scenario distributions, and reporting the entire service–risk Pareto set. Decision-focused learning can align training with such operational objectives [53], while robust optimization can control the worst-case coefficients and scenario shifts [54].

5.4 Theoretical and practical implications

Theoretically, our study identifies an information–topology interaction. The typed topology delivered a reproducible advantage when the disturbance origin and current operating response were visible, while the strict opening-state regime selected the GCN as the leading predecision model. Therefore, complex-network prediction should specify not only and a horizon but also the filtration , i.e., the information genuinely available at decision time. This addition renders the scientific target and source of graph value explicit. Practically, the results support a staged decision architecture. A project control team can use the GCN for leakage-resistant predecision screening, activate the relational GraphSAGE for topology-aware diagnosis once a disruption context is available, and pass any reallocation through the site-count, duration, capacity, and scenario guardrails. This staged workflow is more operationally informative than a single unconstrained score because each output has a defined information set and decision authority. For digital twin research, the implication is that fidelity requires an auditable temporal interface as much as a detailed network. A twin that updates with the served quantities and ending backlog can support within-week monitoring, but these variables cannot be labeled retrospectively as predecision signals. Here, explicit timestamps, unit provenance, and decision authority should accompany every predictive interface.

5.5 Scope and next-stage validation

The evidence is intentionally scoped to a data-grounded counterfactual construction analysis. The SUCCESS records define the entities, demand templates, and network relations, while the frozen queue-flow mechanism defines the disruption, capacity, and intervention outcomes. The resulting claims concern predictive ranking and policy comparison within that registered mechanism, while the 37 sites across the four pilots support explicit project-fold evaluations. The targeted panel establishes mechanism consistency within the pilot D topology, while the LOPO design evaluates project shifts and SupplyGraph provides a cross-domain structural boundary. These layers serve distinct validation roles and are reported separately. Prospective generalization efforts can build on this hierarchy by adding independently collected construction projects with multiple preregistered disruption clusters.

Strict scores are used as the ranking signals, while Platt scaling is confined to the policy experiment. The supplier capacities and material-specific CCC quantities remain registered proxies, and the policy frontier covers six formulations under a single frozen capacity and path configuration. These design choices define a focused next-stage agenda for calibrated conformal risk bounds, direct chance constraints, recovery decisions, and multiperiod recourse. Future works should prospectively register additional construction projects before refitting, collect time-stamped opening and ending states, and reserve multiple positive disruption clusters per project. Then, temporal GNNs can be compared with GRU, long short-term memory, temporal convolutional network, tree, and linear baselines under the same filtration and budget. On the decision side, project-distributionally robust network flow, calibrated conformal risk bounds, and decision-focused training can be evaluated against a predeclared Pareto acceptance region and observed intervention logs.

6 Conclusion

This work introduces an auditable dual-regime framework for construction supply network propagation and risk-constrained control. The strict temporal contract proposed herein identified GCN as the leading predecision model with a held-out AUPRC of 0.2397 and AUROC of 0.8161. In context-aware diagnosis, relational GraphSAGE achieved an AUPRC of 0.5702, exceeding the matched MLP by 0.0803, and maintained a positive advantage across all eight targeted CCC-outage pairs. The project-fold and external-network tests then converted the variations into an explicit applicability map for topology-aware learning.

For network control, the safety gate detected that an aggregate service improvement of 0.827% could transfer risk to additional sites and failure weeks while screening the allocation out. The held-out Pareto frontier separately identified a deficit-only direction that improved all three outcomes while preserving the predeclared selection rule. The central result is therefore constructive: graph structures create value when the topology, target, and available information are aligned; then, the explicit temporal contracts, project-level validation, and propagation-risk gates convert this value into an accountable decision architecture. The proposed framework provides a practical foundation for prospective multiproject validation and decision-aware construction digital twins.

Statements

Data availability statement

The raw data supporting the conclusions of this article will be made available by the authors without undue reservation.

Ethics statement

The study used public construction-logistics records and computational counterfactual analysis. It involved no human participants, personal data, animals, or biological materials; institutional ethics approval and informed consent were therefore not applicable.

Author contributions

QF: Data curation, Conceptualization, Writing – original draft, Formal analysis, Methodology. YW: Project administration, Validation, Writing – review and editing, Investigation, Supervision, Software. YX: Writing – original draft, Software, Conceptualization, Data curation, Investigation.

Funding

The author(s) declared that financial support was not received for this work and/or its publication.

Acknowledgments

The authors wish to acknowledge the SUCCESS H2020 project, Samuel Renault, and the SupplyGraph contributors for publicly releasing the datasets used in this study.

Conflict of interest

The author(s) declared that this work was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Generative AI statement

The author(s) declared that generative AI was not used in the creation of this manuscript.

Any alternative text (alt text) provided alongside figures in this article has been generated by Frontiers with the support of artificial intelligence and reasonable efforts have been made to ensure accuracy, including review by the authors wherever possible. If you identify any issues, please contact us.

Publisher’s note

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article, or claim that may be made by its manufacturer, is not guaranteed or endorsed by the publisher.

Supplementary material

The Supplementary Material for this article can be found online at: https://www.frontiersin.org/articles/10.3389/fphy.2026.1946795/full#supplementary-material

References

  • 1.

    BoccalettiSLatoraVMorenoYChavezMHwangDU.Complex networks: structure and dynamics. Phys Rep (2006) 424:175–308. 10.1016/j.physrep.2005.10.009

  • 2.

    HolmePSaramäkiJ.Temporal networks. Phys Rep (2012) 519:97–125. 10.1016/j.physrep.2012.03.001

  • 3.

    Pastor-SatorrasRCastellanoCVan MieghemPVespignaniA.Epidemic processes in complex networks. Rev Mod Phys (2015) 87:925–79. 10.1103/RevModPhys.87.925

  • 4.

    BuldyrevSVParshaniRPaulGStanleyHEHavlinS.Catastrophic cascade of failures in interdependent networks. Nature (2010) 464:1025–8. 10.1038/nature08932

  • 5.

    MotterAE.Cascade control and defense in complex networks. Phys Rev Lett (2004) 93:098701. 10.1103/PhysRevLett.93.098701

  • 6.

    GaoJBarzelBBarabásiAL.Universal resilience patterns in complex networks. Nature (2016) 530:307–12. 10.1038/nature16948

  • 7.

    VrijhoefRKoskelaL.The four roles of supply chain management in construction. Eur J Purchasing Supply Manage (2000) 6:169–78. 10.1016/S0969-7012(00)00013-7

  • 8.

    HoWZhengTYildizHTalluriS.Supply chain risk management: a literature review. Int J Prod Res (2015) 53:5031–69. 10.1080/00207543.2015.1030467

  • 9.

    BasoleRCBellamyMA.Visual analysis of supply network risks: insights from the electronics industry. Decis Support Syst (2014) 67:109–20. 10.1016/j.dss.2014.08.008

  • 10.

    GarveyMDCarnovaleSYeniyurtS.An analytical framework for supply network risk propagation: a Bayesian network approach. Eur J Oper Res (2015) 243:618–27. 10.1016/j.ejor.2014.10.034

  • 11.

    BaghalzadehSMMoehlerRCFangYAboutorabHHijaziAA.Construction supply chain risk management. Autom Constr (2024) 162:105396. 10.1016/j.autcon.2024.105396

  • 12.

    WangLChengYZhangY.Exploring the risk propagation mechanisms of supply chain for prefabricated building projects. J Build Eng (2023) 74:106771. 10.1016/j.jobe.2023.106771

  • 13.

    WangHZhouZ.Identification of key risk nodes and invulnerability analysis of construction supply chain networks. Buildings (2024) 14:1997. 10.3390/buildings14071997

  • 14.

    LiuWLuoXFengZLiangBFanG.Research on risk propagation mechanism and control strategy of prefabricated building supply chain: based on complex network model and dynamic simulation analysis. Eng Constr Archit Manage (2026) 33:5901–33. 10.1108/ECAM-10-2024-1480

  • 15.

    AngelidisGVarsakelisNC.Economic shock transmission through global value chains: an assessment using network analysis. Int Adv Econ Res (2023) 29:111–28. 10.1007/s11294-023-09871-0

  • 16.

    IoannidisEDadakasDAngelidisG.Shock propagation and the geometry of international trade: the US–China trade bipolarity in the light of network science. Mathematics (2025) 13:838. 10.3390/math13050838

  • 17.

    AngelidisG.A mathematical framework for modeling global value chain networks. Foundations (2026) 6:8. 10.3390/foundations6010008

  • 18.

    RenaultS.Data Sets for Simulation of Urban Construction Consolidation Centres (2018). [Dataset]. 10.5281/zenodo.1249519

  • 19.

    SinghKChandrasekarVKZouWKurthsJSenthilkumarDV.Graph coloring framework to mitigate cascading failure in complex networks. Commun Phys (2025) 8:170. 10.1038/s42005-025-02089-y

  • 20.

    ZhuTYangXMaZSunHWuJGaoZet alA small set of critical hyper-motifs governs heterogeneous flow-weighted network resilience. Nat Commun (2025) 16:7809. 10.1038/s41467-025-63001-4

  • 21.

    ZhangXRenHFengYZhaoZChenXMiZ.A cascading failure propagation model for a network with a node emergency recovery function. Appl Energy (2024) 371:123655. 10.1016/j.apenergy.2024.123655

  • 22.

    Al-TakrouriSAl-MaghalsehM.Decentralized control of flow in complex networks. Proced Comput Sci (2024) 241:298–307. 10.1016/j.procs.2024.08.040

  • 23.

    KipfTNWellingM.Semi-supervised classification with graph convolutional networks. In: International Conference on Learning Representations (2017).

  • 24.

    HamiltonWLYingRLeskovecJ. Inductive representation learning on large graphs. Adv Neural Inf Process Syst (2017) 30:1024–34.

  • 25.

    SchlichtkrullMKipfTNBloemPvan den BergRTitovIWellingM. Modeling relational data with graph convolutional networks. In: The Semantic Web. Springer (2018). p. 593–607. 10.1007/978-3-319-93417-4_38

  • 26.

    ParejaADomeniconiGChenJMaTSuzumuraTKanezashiHet alEvolveGCN: evolving graph convolutional networks for dynamic graphs. Proc AAAI Conf Artif Intell (2020) 34:5363–70. 10.1609/aaai.v34i04.5984

  • 27.

    RossiEChamberlainBFrascaFEynardDMontiFBronsteinM. Temporal graph networks for deep learning on dynamic graphs. arXiv Preprint (2020). 10.48550/arXiv.2006.10637

  • 28.

    WasiATIslamMSAkibAR. SupplyGraph: A Benchmark Dataset for Supply Chain Planning Using Graph Neural Networks (2024). 10.48550/arXiv.2401.15299arXiv Preprint

  • 29.

    HanK. Applying Graph Neural Network to SupplyGraph for Supply Chain Network (2024). 10.48550/arXiv.2408.14501arXiv Preprint

  • 30.

    ChangSLinZYanBBembdeSXiuQWongCHet alLearning production functions for supply chains with graph neural networks. Proc AAAI Conf Artif Intell. (2025) 39:27878–86. 10.1609/aaai.v39i27.35004

  • 31.

    AlshboulOShehadehA. Enhancing infrastructure project outcomes through optimized contractual structures and long-term warranties. Eng Constr Archit Manage (2024) 33:2220–42. 10.1108/ECAM-07-2024-0954

  • 32.

    ShehadehAAlshboulO. Game theory integration in construction management: a comprehensive approach to cost, risk, and coordination under uncertainty. J Constr Eng Manage (2025) 151:04025039. 10.1061/JCEMD4.COENG-15109

  • 33.

    AlshboulOShehadehA. Conflict resolution and negotiation in construction projects using game theory: achieving win-win outcomes. Int J Constr Manage (2025) 26:1341–64. 10.1080/15623599.2025.2550484

  • 34.

    AlshboulOShehadehA. Integrating labor and insurance regulations for enhanced safety and security of construction workers. J Leg Aff Dispute Resolution Eng Constr (2025) 17:04525021. 10.1061/JLADAH.LADR-1259

  • 35.

    ShehadehAAlshboulO. Enhancing occupational safety in construction: predictive analytics using advanced ensemble machine learning algorithms. Eng Appl Artif Intell (2025) 159:111761. 10.1016/j.engappai.2025.111761

  • 36.

    AlshboulOAl-ShboulKShehadehATatariO. Advancing equipment management for construction: introducing a new model for cost, time and quality optimization. Constr Innov (2025) 26:1191–217. 10.1108/CI-04-2024-0129

  • 37.

    AlshboulOShehadehASalehE. Advancing construction quality management: an integrated evidential reasoning and belief functions framework. J Constr Eng Manage (2025) 151:04025093. 10.1061/JCEMD4.COENG-15969

  • 38.

    AlshboulOShehadehA. Adaptive integration of BIM and Navisworks for real-time clash detection using the XGBoost algorithm. J Constr Eng Manage (2026) 152:04025232. 10.1061/JCEMD4.COENG-16001

  • 39.

    ShehadehAAlshboulOTamimiM. Quantitative analysis of climate-adaptive pavement technologies: mitigating environmental impact and enhancing economic viability in urban infrastructure. J Constr Eng Manage (2025) 151:04025064. 10.1061/JCEMD4.COENG-15682

  • 40.

    AlshboulOShehadehATamimiM. Sustainability-focused pavement management under climate variability. J Constr Eng Manage (2025) 151:04025076. 10.1061/JCEMD4.COENG-15829

  • 41.

    AlshboulOShehadehAAlmasabhaG. Enhanced seismic resilience of cross-laminated timber buildings: a machine learning approach to developing robust fragility curves. Eng Appl Artif Intell (2026) 167:113848. 10.1016/j.engappai.2026.113848

  • 42.

    ShehadehAAlshboulOTamimiMF. Hybrid machine learning solutions for mitigating climate-induced productivity losses in sustainable construction management. J Clean Prod (2026) 538:147285. 10.1016/j.jclepro.2025.147285

  • 43.

    ShehadehAAlshboulOAburamadanRArarMAbuhazeemSKhazalehKet alIntegrating climate resilience and digital twin technologies in housing: a comparative analysis and sustainable design proposal for Jordan and South Africa. Results Eng (2025) 28:108409. 10.1016/j.rineng.2025.108409

  • 44.

    WinterMScholzJ. Spatio-temporal spread of disruptions in interconnected supply networks. AGILE GIScience Ser (2024) 5:53–6. 10.5194/agile-giss-5-53-2024

  • 45.

    HelliSSMokhtariHDehnaviS. A mathematical modelling for integrated construction and production supply chain network design. Sci Rep (2025) 15:35883. 10.1038/s41598-025-21137-9

  • 46.

    DuQChenQYangJZhouJBaiLLuoX. Incorporating delay propagation into decision-making for optimizing prefabricated building supply chain networks under uncertainty. Front Eng Manage (2026) 13:363–85. 10.1007/s42524-026-5206-3

  • 47.

    DavisJGoadrichM. The relationship between precision-recall and roc curves. In: Proceedings of the 23rd International Conference on Machine Learning (2006). p. 233–40. 10.1145/1143844.1143874

  • 48.

    SaitoTRehmsmeierM. The precision-recall plot is more informative than the ROC plot when evaluating binary classifiers on imbalanced datasets. PLoS One (2015) 10:e0118432. 10.1371/journal.pone.0118432

  • 49.

    GuoCPleissGSunYWeinbergerKQ. On calibration of modern neural networks. In: Proceedings of the 34th International Conference on Machine Learning (2017) 70:1321–30.

  • 50.

    ChenTGuestrinC. XGBoost: a scalable tree boosting system. In: Proceedings of the 22nd ACM SIGKDD International Conference on Knowledge Discovery and Data Mining. New York, NY: Association for Computing Machinery. (2016) 785–94. 10.1145/2939672.2939785

  • 51.

    HochreiterSSchmidhuberJ. Long short-term memory. Neural Comput (1997) 9:1735–80. 10.1162/neco.1997.9.8.1735

  • 52.

    ChoKvan MerrienboerBGulcehreCBahdanauDBougaresFSchwenkHet alLearning phrase representations using RNN encoder–decoder for statistical machine translation. In: Proceedings of the 2014 Conference on Empirical Methods in Natural Language Processing. Doha, Qatar: Association for Computational Linguistics (2014). p. 1724–34. 10.3115/v1/D14-1179

  • 53.

    WilderBDilkinaBTambeM. Melding the data-decisions pipeline: decision-focused learning for combinatorial optimization. Proc AAAI Conf Artif Intell (2019) 33:1658–65. 10.1609/aaai.v33i01.33011658

  • 54.

    BertsimasDSimM. The price of robustness. Oper Res (2004) 52:35–53. 10.1287/opre.1030.0065

  • 55.

    TobinJFongRRayASchneiderJZarembaWAbbeelP. Domain randomization for transferring deep neural networks from simulation to the real world. In: 2017 IEEE/RSJ International Conference on Intelligent Robots and Systems. IEEE (2017). p. 23–30. 10.1109/IROS.2017.8202133

  • 56.

    PearlJ. Causality: Models, Reasoning and Inference. 2 edn.Cambridge: Cambridge University Press (2009). 10.1017/CBO9780511803161

  • 57.

    ElmachtoubANGrigasP. Smart “predict, then optimize”. Manage Sci (2022) 68:9–26. 10.1287/mnsc.2020.3922

  • 58.

    HuangfuQHallJAJ. Parallelizing the dual revised simplex method. Math Prog Comput (2018) 10:119–42. 10.1007/s12532-017-0130-5

  • 59.

    PlattJC. Probabilistic outputs for support vector machines and comparisons to regularized likelihood methods. In: SmolaAJBartlettPLSchölkopfBSchuurmansD, editors. Advances in Large-Margin Classifiers. MIT Press (2000). p. 61–74.

  • 60.

    PaszkeAGrossSMassaFLererABradburyJChananGet alPyTorch: an imperative style, high-performance deep learning library. Adv Neural Inf Process Syst (2019) 32:8026–37. Available online at: https://papers.nips.cc/paper_files/paper/2019/file/bdbca288fee7f92f2bfa9f7012727740-Metadata.json.

  • 61.

    PedregosaFVaroquauxGGramfortAMichelVThirionBGriselOet alScikit-learn: machine learning in python. J Mach Learn Res (2011) 12:2825–30.

  • 62.

    HagbergAASchultDASwartPJ. Exploring network structure, dynamics, and function using networkx. In: Proceedings of the 7th Python in Science Conference (2008). p. 11–5. 10.25080/TCWV9851

  • 63.

    VirtanenPGommersROliphantTEHaberlandMReddyTCournapeauDet alScipy 1.0: fundamental algorithms for scientific computing in python. Nat Methods (2020) 17:261–72. 10.1038/s41592-019-0686-2

Summary

Keywords

complex networks, construction supply chain, counterfactual propagation, graph neural network, network control, rare-event prediction, robust optimization, temporal information

Citation

Fu Q, Wei Y and Xiang Y (2026) Leakage-resistant graph learning for risk propagation and risk-constrained control in construction supply networks. Front. Phys. 14:1946795. doi: 10.3389/fphy.2026.1946795

Received

23 July 2026

Revised

08 August 2026

Accepted

07 September 2026

Published

04 November 2026

Volume

14 - 2026

Edited by

Satheesh Kumar, Digital University Kerala, India

Reviewed by

Odey Alshboul, Hashemite University, Jordan

Georgios Angelidis, Aristotle University of Thessaloniki, Greece

Updates

Copyright

*Correspondence: Yao Wei,

Disclaimer

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.