Abstract
Emerging economies with rapidly growing population and energy demand, own some of the most expensive power plants in the world. We hypothesized that corruption has a relationship with the capital cost of power plants in developing countries such as Bangladesh. For this study, we analyzed the capital cost of 61 operational and planned power plants in Bangladesh. Initial comparison study revealed that the mean capital cost of a power plant in Bangladesh is twice than that of the global average. Then, the statistical analysis revealed a significant correlation between corruption and the cost of power plants, indicating that higher corruption leads to greater capital cost. The high up-front cost can be a significant burden on the economy, at present and in the future, as most are financed through international loans with extended repayment terms. There is, therefore, an urgent need for the review of the procurement and due diligence process of establishing power plants, and for the implementation of a more transparent system to mitigate adverse effects of corruption on megaprojects.
Introduction
Bangladesh is the world’s eighth most populous country of 161 million people with annual population and GDP growth rates of 1.2 and 6.6%, respectively (WB, ). While the population grew linearly, electricity consumption per capita increased exponentially since 1970, as shown in Figures 1A,G. The GDP-electricity elasticity of the country exhibits a strong linear relationship (R2 = 0.989); electricity consumption increased by 4.15 kWh/capita for every US$ increase in GDP/capita in 1971–2011 (Figure 2). Moreover, past research indicates a unidirectional causal relationship is running from electricity consumption to investment and economic growth in Bangladesh—implying that over time, increasing electricity consumption results in higher economic growth (Masuduzzaman, ). Therefore, the government aimed toward giving access to electricity all households by 2021 (BPDB, ). The causal relationship between economic growth and electricity consumption illustrated in Figure 2 and available literature suggested that, as more people get access to electricity, the demand of electric power may increase significantly as Bangladesh aims at transition from a lower-middle-income to a middle-income country by 2021 (MoF, ) and developed by 2040 (Jalil and Islam, ; FE, ). The required additional economic growth is expected to result from the expansion and development of the energy-intensive manufacturing and service sectors (Nath, ; ILO and IILS, ; ADB, ).
Figure 1
Figure 2
The power sector in Bangladesh underwent several significant restructurings since its humble beginning at the turn of the twentieth century. Electricity was provided only to the wealthy residents in the capital with small power plants (Omprasad,
National Energy Policy 1994 paved the way for deregulation to encourage broader participation in power generation (Ebinger,
Most RPPs are oil based that relies on imported petroleum as Bangladesh has insufficient oil reserve. By increasing oil dependency (Mujeri et al.,
In the case of fuel types, increased oil-based RPPs have changed the generation fuel mix within 5 years of their expansion. Figure 1H illustrates that 80% of the installed capacity in 2010 was based on natural gas (hereafter gas only), which reduced to 68% in 2015 (MoF,
There have been different studies on the relationship between corruption and cost of big public projects. Study on Italian high-speed railways megaprojects demonstrated that corruption worsens both cost and temporal performance (Locatelli et al.,
Methodology
The study was conducted in three stages. First, annual (BPDB,
Table 1
| Variable | Scale/category | Electricity generation technology | Total (n) | % | ||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Gas turbine | Combined-cycle power plant | Subcritical | Ultra-supercritical | Solar PV | Hydroelectric | Nuclear | ||||
| Commissioning year (–) | 1961–1980 | – | – | – | – | – | 1 | – | 1 | 1.6 |
| 1981–1980 | 2 | 1 | – | – | – | 2 | – | 5 | 8.2 | |
| 2001–2010 | 2 | 2 | 1 | – | – | – | – | 5 | 8.2 | |
| 2011–2020 | 20 | 24 | 1 | – | 2 | – | – | 47 | 77.0 | |
| 2021–2030 | – | – | – | 2 | – | – | 1 | 3 | 4.9 | |
| Ownership | Public | 12 | 26 | 2 | 2 | 2 | 3 | 1 | 48 | 78.7 |
| Private | 11 | 2 | – | – | – | – | – | 13 | 21.3 | |
| Fuel | Natural gas | 10 | 24 | – | – | – | – | – | 34 | 60.7 |
| Oil | 9 | – | – | – | – | – | – | 9 | 16.1 | |
| Duel fuel | 5 | 3 | – | – | – | – | – | 8 | 14.3 | |
| Coal | – | – | 2 | 2 | – | – | – | 4 | 7.1 | |
| Nuclear | – | – | – | – | – | – | 1 | 1 | 1.8 | |
| Installed capacity (MW) | <10 | – | – | – | – | 2 | – | – | 2 | 3.3 |
| 10–100 | 8 | 7 | – | – | – | 3 | – | 18 | 29.5 | |
| 101–200 | 9 | 3 | 1 | – | – | – | – | 13 | 21.3 | |
| 201–300 | 6 | 4 | 1 | – | – | – | – | 11 | 18.0 | |
| 301–400 | – | 11 | – | – | – | – | – | 11 | 18.0 | |
| 401–500 | – | 3 | – | – | – | – | – | 3 | 4.9 | |
| >500 | – | – | – | 2 | – | – | 1 | 3 | 4.9 | |
| Capital cost [US$ (2015)/kW] | 500–600 | 1 | 2 | – | – | – | 1 | – | 4 | 6.6 |
| 601–700 | 4 | 1 | – | – | – | – | – | 5 | 8.2 | |
| 701–800 | 2 | 1 | – | – | – | – | – | 3 | 4.9 | |
| 801–900 | 6 | 4 | – | – | – | – | – | 10 | 16.4 | |
| 901–1,000 | 2 | 4 | – | – | – | – | – | 6 | 9.8 | |
| 1,001–1,100 | – | 5 | – | – | – | 1 | – | 6 | 9.8 | |
| 1,101–1,200 | 2 | 2 | – | – | – | – | – | 4 | 6.6 | |
| 1,201–1,300 | 1 | 3 | 1 | – | – | – | – | 5 | 8.2 | |
| 1,301–1,400 | 2 | 1 | – | – | – | – | – | 3 | 4.9 | |
| 1,401–1,500 | 2 | 1 | – | – | – | – | – | 3 | 4.9 | |
| 1,501–1,600 | – | – | – | – | – | – | – | 0 | 0.0 | |
| 1,601–1,700 | 1 | 2 | – | – | – | – | – | 3 | 4.9 | |
| 1,701–1,800 | – | – | – | – | – | – | – | 0 | 0.0 | |
| 1,801–1,900 | 1 | – | – | – | – | – | – | 1 | 1.6 | |
| 1,901–2,000 | – | – | 1 | – | – | – | – | 1 | 1.6 | |
| 2,001–3,000 | – | – | – | 1 | 1 | – | – | 2 | 3.3 | |
| 3,001–4,000 | – | 1 | – | 1 | – | – | – | 2 | 3.3 | |
| 4,001–5,000 | – | – | – | – | 1 | – | – | 1 | 1.6 | |
| 5,001–6,000 | – | – | – | – | – | – | 1 | 1 | 1.6 | |
| >6,000 | – | – | – | – | – | 1 | – | 1 | 1.6 | |
Background information on the cost data.
Among the analyzed 61 power plant units, gas, HFO/HSD/duel fuel, coal, nuclear, and renewable based were 34, 17, 4, 1, and 5, respectively. Moreover, 48 are public, and 13 are privately operated. All the future and under-construction power plants are government owned. Among the eight analyzed duel fuel power plant units, two utilize HFO and gas, of which one is public, and one is privately owned. Six duel fuel power plant units use HSD and gas, of which one is private, and five are publicly owned. There are only nine HFO based power plant units, of which two are planned for future and rest of them are operational. All the HFO based functional power plants are privately owned. In the case of coal-based power plants units, only two are functional, and three are planned for future, and all of them are publicly owned. Similarly, all the renewable power plants are government owned, of which one is the Kaptai hydroelectric plant (five units) and two small solar energy plants. The only planned nuclear power plant (Rooppur 1 and 2) would be publicly owned too. Three phases (Units 1 and 2; Unit 3; Units 4 and 5) of Kaptai hydroelectric power plant was considered separately because three stages had different cost individually. Among the coal power generation technologies, domestic coal-fueled subcritical plants were built in Barapukuria. Moreover, two new ultra-supercritical plants are under construction which would operate with imported coal. Cost per installed capacity in kilowatts (kW) in a specific year of construction of the power plant was calculated and converted to the US dollar (USD) equivalent using the currency exchange rate with Bangladeshi Taka (BDT) on December 31 of the same year, obtained from Bangladesh Bank (BB,
Second, country- and region-wise capital costs of power plants for the same technology used in Bangladesh were collected from the International Energy Agency’s (IEA’s) World Energy Investment Outlook 2014 (IEA,
Third, the average cost of power plants in Bangladesh was compared with that of the identified countries, regions and the world using 2015 as a base year. The evolution of cost was also analyzed for both public and private sectors in Bangladesh. Pearson’s test was conducted at normalized capital cost and CPI score to examine the effect of corruption on power plant capital cost in Bangladesh. CPI data are available only from 1995, which reduced the sample size down to 42 for the correlation study. Among the collected cost data, power plants commissioned from 2004 to 2016 were considered. There were no cost data available for any power plants established between 1995 and 2003. There were also some cost data for power plants built before 1995. As the CPI started in 1995, the cost data before that were not considered for the correlation study. As the sample size is less than 50, Shapiro–Wilk and Kolmogorov–Smirnov tests of normality were conducted (Ghasemi and Zahediasl,
Table 2
| Corruption Perceptions Index (CPI)a | Kolmogorov–Smirnovb | Shapiro–Wilk | |||||
|---|---|---|---|---|---|---|---|
| Statistic | df | Sig. | Statistic | df | Sig. | ||
| $/kW | 25 | 0.172 | 14 | 0.200c | 0.882 | 14 | 0.062 |
| 26 | 0.139 | 7 | 0.200c | 0.974 | 7 | 0.925 | |
| 27 | 0.185 | 7 | 0.200c | 0.916 | 7 | 0.442 | |
Test of normality.
The data are normal because of the sig. value of the Shapiro–Wilk Test was higher than 0.05.
aCPI has been omitted when CPIs are 15, 20, and 24 because $/kW is constant.
bLilliefors significance correction.
cThis is a lower bound of the true significance.
Discussion
Power generation technology is the critical factor for the variation in the capital cost. For this study, initially, capital cost of various public and private power plants in Bangladesh with varied technologies such as gas turbines (GTs) and combined-cycle power plant (CCPP); subcritical and ultra-supercritical plants; hydroelectric; nuclear and solar PV plants were compared with the world average, to find out the cost difference. When the cost of GT and steam turbines (ST) are compared, public power plants (hereafter plants) in Bangladesh are found to be approximately 2.2 times more expensive than that of the world mean (Figure 3A). The cost of public GTs is even higher, around 1.5 times than the private plants in Bangladesh. In the case of CCPP, public plants’ mean is 1.2 and 1.7 times more expensive than that of the world mean and the private plants’ mean, respectively (Table 3).
Figure 3

Capital cost comparison among fossil fueled power plants from the world with Bangladesh. In the case of gas turbine/steam turbine and combined-cycle power plant (CCPP). Bangladeshi public power plant’s mean capital cost is higher than that of the mean of private and world counterparts. Surprisingly, private power plant’s mean capital cost was lower than the world mean for CCPP. Subcritical coal plant means capital cost is slightly higher than that of global mean. However, ultra-supercritical mean capital cost of Bangladesh would be significantly greater than the world mean. (A) Gas/steam turbine. (B) CCPP. (C) Coal: subcritical. (D) Coal: ultra-supercritical.
Table 3
| Fuel | Technology | Capital cost [US$ (2015)/kW] | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| World | Bangladesh (public) | Bangladesh (private) | Difference in mean | |||||||||||||
| Min | Max | Mean | SD | Min | Max | Mean | SD | Min | Max | Mean | SD | Public and private | World and public | World and private | ||
| Natural gas and oil | Gas turbine | 361 | 741 | 551 | 190 | 680 | 1,823 | 1,177 | 336 | 545 | 1,495 | 819 | 235 | 258 | −626 | −268 |
| Combined-cycle power planta | 568 | 1,381 | 974 | 407 | 545 | 3,005 | 1,164 | 505 | 560 | 848 | 704 | 144 | 460 | −189 | 270 | |
| Coal | Subcritical | 619 | 2,168 | 1,394 | 774 | 1,245 | 1,924 | 1,584 | 479 | −191 | ||||||
| Ultra-supercritical | 826 | 2,374 | 1,600 | 774 | 2,867 | 3,820 | 3,343 | 477 | −1,743 | |||||||
| Renewable | Solar PVa | 1,910 | 6,198 | 4,054 | 2,144 | 2,391 | 4,907 | 3,649 | 1,258 | 405 | ||||||
| Hydroelectrica | 1,755 | 3,977 | 2,866 | 1,111 | 543 | 6,409 | 2,676 | 2,648 | 190 | |||||||
| Nuclear | Nuclearb | 2,065 | 6,883 | 4,474 | 2,409 | 5,625 | 5,625 | |||||||||
The capital cost of power generation plants in the World and Bangladesh. Power plants in Bangladesh are further disaggregated into public and private. Historical and projected costs are rounded to the nearest US$ (2015).
aCCGT, solar photovoltaics—large-scale and hydropower—large-scale in International Energy Agency’s World Energy Investment Outlook 2014 (IEA,
bThere is only one planned nuclear power plant in Bangladesh. Caution should, therefore, be applied when interpreting the difference in mean.
The private CCPP with an average cost of $540/kW, where publicly owned ones ranged from $853 to 3,005/kW (Figure 3B). Moreover, future planned public CCPP cost range from $554 to 1,612/kW. Therefore, public CCPP in Bangladesh can be built with as low-cost as China ($568/kW between 2012 and 2020) to 19% greater than that of the highest cost of USA ($1,358/kW between 2015 and 2020). The difference between lowest and highest capital cost of CCPP (going to be commissioned in 2017) is $1,058/kW, the equivalent of constructing almost two CCPP plants in China. Cost difference can happen depending on the installed capacity. From long-term generation expansion planning study of Sri Lanka, two separate CCPP cost difference was $202/kW depending on the installed capacity. The capital cost of CCPP-Auto Diesel of 144 and 288 MW was $853 and $1,055/kW, respectively in Sri Lanka (Samarasekara and Silva,
Figures 3C,D compare the cost of coal power plants. The subcritical coal plant, capital cost range from $1,245 to $1,923/kW, which is higher than the expense of the USA in the upper bound, and Africa in lower bound. However, the cost of the proposed ultra-supercritical power plant is going to be highest compared with the rest of the world (Figure 3D).
In the case of renewable energy, Bangladesh has been utilizing hydroelectricity from Kaptai power plant since 1962, making it the oldest active power plant in Bangladesh with a capital cost of $6,408/kW for Units 1 and 2, and parts of Unit 3. Capital cost reduced with the construction of Unit 3 in 1982, from $6,408 to $543/kW (Figure 4B). Unit 3 was partially built during the construction of Units 1 and 2 in 1962, which reduced the capital cost of completion of Unit 3 in 1982. However, the capital cost for Units 4 and 5 was $1,075/kW, which was constructed in 1988. Units 4 and 5 were constructed in an already established infrastructure with facilities such as dam, reservoir during the construction of Units 1–3. Therefore, Units 4 and 5 had higher capital cost than that of Unit 3. While comparing the capital cost of Bangladeshi hydroelectric plants with the world, the cost reported for other countries were suggested for the construction of new plants.
Figure 4

Capital cost comparison among nuclear and renewable power plants from different country regions with Bangladesh. In the case of solar PV plants, mean capital cost of Bangladesh is lower than the world mean. However, the installed capacity is only 12 MW. Mean capital cost for hydroelectric plants is also lower than that of global mean capital cost. The reason behind this lower cost is the later units were in the same plant side, which reduced the ancillary cost. For nuclear, only one plant is going to be built in Bangladesh by 2030, and its cost would be significantly higher than that of the world mean capital cost. (A) Solar PV plants. (B) Hydroelectric. (C) Nuclear.
Currently, Bangladesh has small-scale SHS in households, but no significant commercial, operational project. Two large solar PV plants are going to be constructed in 2016–2017 with an installed capacity of 5 and 7 MW costing $4,906 and $2,391/kW, respectively (Figure 4A). Despite the continuing descending trend in cost, one is costing higher than that of the highest in the world for that year. Also, it is not clear why the difference in cost would be $2,515/kW for just 2 MW, almost two times more than the cost of establishing similar technology power plant in China in 2020.
In the case of nuclear power plants, the planned power plant in Bangladesh would be established with the assistance from Russia in 2024–2025. However, the capital cost would be 1.45 times than that of Russia and almost equivalent to Japan (Figure 4C).
Although power plants cost more in Bangladesh, the public plants are significantly more expensive than the private ones, indicating that there may as well be other factors related to public sector governance in play (Table 3). Further studies may reveal other factors such as political instability, inefficient project management leading to construction delays and eventual increase in cost. However, the deep-rooted and widespread corruption culture could have a higher impact on the capital cost of the power plants, which needs further investigation with more data.
Cost Evolution
The cost evolution in Bangladeshi public and private plants do not follow the same trend. The cost of most of the power generation technology in the world reduces with time (Neij,
Figure 5

Cost evolution of different power generation technologies. In the case of coal, one subcritical power plants and two future ultra-supercritical ones not sufficient to see the cost evolution. For hydroelectric, solar PV, and nuclear, the power plant numbers are insufficient for analysis of learning rate or cost evolution. Under these circumstances, highly utilized technologies such as gas turbine engine and combined-cycle power plant (CCPP) for public and private power plants were analyzed for cost evolution.
Independent-samples t-test was conducted to compare the capital cost in public and private owned power plants. The cost of GT/ST and CCPP technologies were considered for the tests. In the case of GT/ST, there was a significant difference in the capital cost of public (M = 1,226.09, SD = 360.62) and private (M = 751.68, SD = 108.80) owned power plants; t(11.97) = 4.16, p = 0.001. These results suggest that GT/ST power plant ownership depending on being public and private influences its capital cost. The test results suggest that public power plants have higher capital cost. In the case of CCPP, there was not a significant difference in the capital cost of public (M = 1,075.33, SD = 263.21) and private (M = 704, SD = 203.60) owned power plants; t(19) = 1.92, p = 0.070. These results suggest that CCPP power plant ownership depending on being public and private does not influence its capital cost. However, the private CCPP power plants number was only two. With more data points in the future, this analysis may be improved.
Corruption
Several reports and articles suggested that there has been significant evidence of corruption in electricity generation projects and operations, as well as in distribution system in Bangladesh (Ruth,
Figure 6

(A) Average capital cost (2004–2016) and (B) Corruption Perceptions Index (CPI) score (2004–2016). Chart (B) is demonstrating that CPI is not gradually reducing. Moreover, the average capital cost of power plants is related to the change of CPI score. Here, higher CPI score means lower corruption.
To assess the relationship between the CPI score and the capital cost of power plants in Bangladesh, Pearson’s test for normally distributed interval data was conducted. There was a negative correlation between the two variables, r = −0.477, n = 42, p = 0.001 (Table 4). Figure 7 summarizes the results and demonstrated that corruption in Bangladesh is negatively related to a capital cost of power plants with R2 = 0.32 for annual CPI scores. Overall, there was a strong, negative correlation between corruption and capital cost of power plants. Decreases in corruption (increase in annual CPI score) were correlated with decreased capital cost of power plants. Corruption is a continual socioeconomic phenomenon traversing through years from megaproject construction and operation. CPI score represents an annual performance of a country. Whereas the power plant megaproject constructions usually go on for 2–7 years (GoB,
Table 4
| Annual CPI (–) | Biannual average CPI (–) | Triannual average CPI (–) | Quadrennial average CPI (–) | ||
|---|---|---|---|---|---|
| Pearson correlation | −0.565a | −0.445a | −0.430a | −0.396a | |
| Capital cost ($/kW) | Sig. (2-tailed) | 0.001 | 0.003 | 0.004 | 0.010 |
| N | 42 | 42 | 42 | 42 |
Pearson correlation test between Corruption Perceptions Index (CPI) score and capital cost per installed capacity of power plants in Bangladesh.
aCorrelation is significant at the 0.01 level (2-tailed).
Figure 7

Corruption vs. capital cost analysis for Bangladeshi power plants: (A) normalized capital cost vs. average annual Corruption Perceptions Index (CPI) scores, (B) normalized capital cost vs. average biannual CPI scores, (C) normalized capital cost vs. average triannual CPI scores, and (D) normalized capital cost vs. average quadrennial CPI scores.
The upper and lower limits of cost reduction per CPI score increase were $116.94 and $45.47/kW, respectively. In some cases, the capital cost of public plants was two times higher than that of the private ones for the similar technology and time frame. Therefore, Bangladesh can reduce their cost of establishing power plants by reducing corruption. The power plant projects are expensive, and the government takes 66–94% (GoB,
One of the reasons behind this significant corruption was the lack of governance in the energy sector. Implementing “Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act, 2010” enabled the government and responsible departments with authority to take rapid energy development initiatives while bypassing the 2006 public procurement law, with easy and quick procurement procedure for investing in the energy sector outside the bar of jurisdiction of the court (GoB,
Conclusion
As a rapidly developing economy, Bangladesh has been establishing and will continue to build more power plants to support the growing demand for electricity. Literature suggested that there is a lack of research on the cost analysis of the rapidly growing energy sector in Bangladesh; partially because of the data inadequacy and lack of transparency in the government. Initially, a cost database was compiled from different resources for this study. For analyzing the cost of installing power plants in Bangladesh, the cost (public and private) data were compared with the world. The results demonstrated an intriguing aspect of a rapidly developing economy. Most of the public plants showed higher capital cost compared with the world average. Also, the cost of similar power generation technologies in private and public sector has a significant difference in Bangladesh. On top of the higher capital cost, the cost evolution demonstrated that cost of establishing public power plants is augmenting with time, whereas its opposite in private sector as well as in the world. In the case of expanding cost, this study showed a significant correlation between corruption and higher cost of power plants. Higher corruption may increase the cost of a power plant in a developing context such as Bangladesh.
This study renders the opportunity to focus on the amendable condition of corruption within the governmental system to reduce the cost of establishing public power plants in Bangladesh. The government should implement more transparent and supervised system for establishing power plants to reduce the adverse influences of corruption on the megaprojects. Otherwise, there is a possibility the expensive power plants would become into “white elephant” projects (Lewis and Williams,
Statements
Author contributions
KD collected the data. KD and MM analyzed and interpreted the data and wrote the paper.
Conflict of interest
The authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.
References
1
ADB. (2016). Bangladesh: Consolidating Export-Led Growth. s.l.: Asian Development Bank.
2
AhmedZ. (2011). Electricity crisis of Bangladesh: result of organizational inefficiency?Energy Environ. Res.1, 12.10.5539/eer.v1n1p12
3
APSCL. (2015a). Ashuganj Power Station Company LTD. Available at: http://www.apscl.com/home/plant_status
4
APSCL. (2015b). Power Generation Development Plan-2012. Ashuganj: Ashuganj Power Station Company LTD.
5
BB. (2016). Exchange Rate of Taka. Available at: https://www.bb.org.bd/econdata/exchangerate.php
6
BPDB. (2008). Annual Report 2007–2008. Dhaka: Bangladesh Power Development Board.
7
BPDB. (2009). Annual Report 2008–2009. Dhaka: Bangladesh Power Development Board.
8
BPDB. (2010). Annual Report 2009–2010. Dhaka: Bangladesh Power Development Board.
9
BPDB. (2011). Annual Report 2010–2011. Dhaka: Bangladesh Power Development Board.
10
BPDB. (2012). Annual Report 2011–2012. Dhaka: Bangladesh Power Development Board.
11
BPDB. (2013). Annual Report 2012–2013. Dhaka: Bangladesh Power Development Board.
12
BPDB. (2014). Annual Report 2013–2014. Dhaka: Bangladesh Power Development Board.
13
BPDB. (2015). Annual Report 2014–2015. Dhaka: Bangladesh Power Development Board.
14
BPDB. (2017). Available at: http://www.bpdb.gov.bd/bpdb/
15
BREB. (2016). History of Rural Electrification in Bangladesh. Available at: http://www.reb.gov.bd/index.php/2-reb
16
CapassoS.SantoroL. (2017). Active and passive corruption: theory and evidence. Eur. J. Polit. Econ.10.1016/j.ejpoleco.2017.05.004
17
ChoudhuryS. R.AliM.ShamsuddinA. K. M.KarimZ.MazumderM. A. M.IslamA. B. M. A.et al (2010). Evaluation of the Implementation of the Paris Declaration, Phase – II, Country Evaluation Bangladesh. Dhaka, Bangladesh: Natural Resources Planners Ltd.
18
Coinnews. (2016). Consumer Price Index Data from 1913 to 2016. Available at: http://www.usinflationcalculator.com/inflation/consumer-price-index-and-annual-percent-changes-from-1913-to-2008/
19
CPGCBL. (2015). Coal Power Generation Company Bangladesh Limited. Available at: http://www.cpgcbl.gov.bd/?page_id=73
20
D’CostaB. (2012). Bangladesh in 2011. Asian Surv.52, 147–156.10.1525/as.2012.52.1.147
21
De ChiaraA.LivioL. (2017). The threat of corruption and the optimal supervisory task. J. Econ. Behav. Organ.133, 172–186.10.1016/j.jebo.2016.11.006
22
EbingerC. K. (2011). Energy and Security in South Asia: Cooperation Or Conflict?s.l.: Brookings Institution Press.
23
EGCBL. (2015). Electricity Generation Company of Bangladesh Limited. Available at: http://www.egcb.com.bd/welcome/plant_details/1
24
FE. (2015). Bangladesh to be developed country by 2040. Available at: http://today.thefinancialexpress.com.bd/public/?date=21-06-2015 [cited June 21, 2015].
25
GaltungF. (2006). Measuring the immeasurable: boundaries and functions of (macro) corruption indices. Meas. Corrupt.101, 101–130.
26
GhasemiA.ZahediaslS. (2012). Normality tests for statistical analysis: a guide for non-statisticians. Int. J. Endocrinol. Metab.10, 486.10.5812/ijem.3505
27
GoB. (2015). Annual Report 2015. Dhaka: Power Division, Ministry of Power, Energy and Mineral Resources (MPEMR).
28
GoB. (2016). Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act, 2010. Dhaka: Ministry of Power, Energy & Mineral Resources, Government of the People’s Republic of Bangladesh.
29
HossainI.TamimM. (2005/2006). Energy and Sustainable Development in Bangladesh. s.l.: HELIO International.
30
IBP. (2012). Bangladesh Country Study Guide: Strategic Information and Developments. USA: International Business Publications.
31
IDCOL. (2015). Annual Environmental and Social Compliance Audit: 108 MW Power Project at Kolagaon. Chittagong, Bangladesh: Infrastructure Development Company Limited (IDCOL).
32
IDCOL. (2017). Renewable Energy. Available at: http://idcol.org/home/penergy
33
IEA. (2014). Assumed Investment Costs, Operation and Maintenance Costs and Efficiencies in the IEA World Energy Investment Outlook 2014. s.l.: International Energy Agency.
34
ILO, IILS. (2013). Bangladesh: Seeking Better Employment Conditions for Better Socioeconomic Outcomes. Geneva, Switzerland: ILO.
35
JalilM. A.IslamM. S. (2010). Towards a long-term development vision for Bangladesh: some socioeconomic and legal aspects. Asian Cult. Hist.2, 58.10.5539/ach.v2n2p58
36
JICA, TEPCO. (2011). The Study for Master Plan on Coal Power Development in the People’s Republic of Bangladesh, Power System Master Plan 2010. s.l.: Energy and Meneral Resources, Ministry of Power, People’s Republic of Bangladesh.
37
KennyC. (2007). Infrastructure Governance and Corruption: Where Next?s.l.: World Bank Publications.
38
KhanM. Z. H.RasheduzzmanM. (2013). Performance of the Power Sector of Bangladesh: Governance Failures and Remedial Measures. s.l.: Transparency International Bangladesh.
39
KhanS. (2007). Honesty = Success, Dishonesty = Failure An Overview of Power Sector Unbundling in Bangladesh (1996–2006), Vol. 2. Dhaka: The Daily Star.
40
KhatunF.AhamadM. (2013). FDI in the Energy and Power Sector and Economic Growth in Bangladesh. s.l.: CPD-CMI Working Paper Series.
41
KPCL. (2014). Annual Report. s.l.: Khulna Power Company Ltd.
42
LambsdorffJ. G. (2006). Measuring corruption – the validity and precision of subjective indicators (CPI). Meas. Corrupt.81, 81–99.
43
LewisJ.WilliamsA. (1985). The Sines Project: Portugal’s growth centre or white elephant?Town Plan. Rev.56, 339.10.3828/tpr.56.3.t57q91u885076373
44
LocatelliG.MarianiG.SainatiT.GrecoM. (2017). Corruption in public projects and megaprojects: there is an elephant in the room!Int. J. Project Manage.35, 252–268.10.1016/j.ijproman.2016.09.010
45
MahmoodS. A. I. (2010). Public procurement and corruption in Bangladesh confronting the challenges and opportunities. J. Publ. Admin. Policy Res.2, 103–111.
46
MasuduzzamanM. (2012). Electricity consumption and economic growth in Bangladesh: co-integration and causality analysis. Glob. J. Manage. Business Res.12, 47–56.
47
MoF. (2009). Invigorating Investment Initiative through Public Private Partnership: A Position Paper. Dhaka, Bangladesh: Ministry of Finance, Government of Bangladesh.
48
MoF. (2010). Towards Revamping Power and Energy Sector: A Road Map. Dhaka: Bangladesh: Ministry of Finance, Government of Bangladesh.
49
MoF. (2011). Power and Energy Sector Road Map: An Update. Dhaka: Bangladesh: Government of Bangladesh.
50
MourshedM. (2013). Pitfalls of oil-based expansion of electricity generation in a developing context. Energy Strat. Rev.1, 205–210.10.1016/j.esr.2012.08.001
51
MujeriM. K.ChowdhuryT. T.ShahanaS. (2014). Energy Sector in Bangladesh: An Agenda for Reforms. Ontario, Canada: International Institute for Sustainable Development.
52
NathN. C. (2012). Manufacturing Sector of Bangladesh-Growth, Structure and Strategies for Future Development. s.l.Bangladesh Economic Association (BEA). Available at: http://bea-bd.org/site/images/pdf/47.pdf
53
NeijL. (2008). Cost development of future technologies for power generation – a study based on experience curves and complementary bottom-up assessments. Energy Policy36, 2200–2211.10.1016/j.enpol.2008.02.029
54
NREL. (2012). Cost and Performance Data for Power Generation Technologies. s.l.: National Renewable Energy Laboratory.
55
OmprasadG. (2016). Structure, growth and associated problems in Bangladesh power sector: a glance into the PreReform period. Ind. J. Appl. Res.6, 753–754.
56
OthmanZ.ShafieR.HamidF. Z. A. (2014). Corruption-Why do they do it?Proc. Soc. Behav. Sci.164, 248–257.10.1016/j.sbspro.2014.11.074
57
PhadkeA. (2009). How many Enrons? Mark-ups in the stated capital cost of independent power producers’(IPPs’) power projects in developing countries. Energy34, 1917–1924.10.1016/j.energy.2009.07.043
58
RossJ.StawB. M. (1993). Organizational escalation and exit: lessons from the Shoreham nuclear power plant. Acad. Manage. J.36, 701–732.10.2307/256756
59
RuthM. (2002). Corruption and the Energy Sector. Washington, DC: Management Systems International.
60
SamarasekaraM. B.SilvaM. T. D. (2015). Long Term Generation Expansion Planning Studies 2015–2034. Colombo: Ceylon Electricity Board, Sri Lanka.
61
TI. (2012). Corruption Perceptions Index (CPI). Available at: https://www.transparency.org/
62
TI. (2017a). Corruption Perceptions Index: Overview. Available at: https://www.transparency.org/research/cpi/overview
63
TI. (2017b). Corruption Perceptions Index: Overview. Available at: https://www.transparency.org/research/cpi
64
TIB. (2016). Anti-Corruption Agency Strengthening Initiative: Assessment of the Bangladesh Anti-Corruption Agency 2016. s.l.: Transparency International Bangaldesh.
65
WB. (2016). World Data Bank. Available at: http://data.worldbank.org/
66
WB. (2017). Siddhirganj Power Project. Available at: http://projects.worldbank.org/P095965/siddhirganj-peaking-power-project?lang=en&tab=documents&subTab=projectDocuments
67
ZouP. X. (2006). Strategies for minimizing corruption in the construction industry in China. J. Construct. Dev. Countries11, 15–29.
Summary
Keywords
corruption, power plant, energy sector, capital cost, developing context
Citation
Debnath KB and Mourshed M (2018) Corruption Significantly Increases the Capital Cost of Power Plants in Developing Contexts. Front. Energy Res. 6:8. doi: 10.3389/fenrg.2018.00008
Received
11 September 2017
Accepted
14 February 2018
Published
08 March 2018
Volume
6 - 2018
Edited by
Sonia Yeh, Chalmers University of Technology, Sweden
Reviewed by
Peter Burgherr, Paul Scherrer Institut (PSI), Switzerland; Constantinos Taliotis, Royal Institute of Technology, Sweden
Updates

Check for updates
Copyright
© 2018 Debnath and Mourshed.
This is an open-access article distributed under the terms of the Creative Commons Attribution License (CC BY). The use, distribution or reproduction in other forums is permitted, provided the original author(s) and the copyright owner are credited and that the original publication in this journal is cited, in accordance with accepted academic practice. No use, distribution or reproduction is permitted which does not comply with these terms.
*Correspondence: Kumar Biswajit Debnath, debnathk@cardiff.ac.uk
Specialty section: This article was submitted to Energy Systems and Policy, a section of the journal Frontiers in Energy Research
Disclaimer
All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.