ORIGINAL RESEARCH article

Front. Energy Res., 28 July 2023

Sec. Smart Grids

Volume 11 - 2023 | https://doi.org/10.3389/fenrg.2023.1226768

Robust stochastic low-carbon optimal dispatch of park-integrated energy system with multiple uncertainties from source and load

  • 1. Economic Research Institute, State Grid Jiangsu Electric Power Co., Ltd., Nanjing, China

  • 2. School of Electrical Engineering, Southeast University, Nanjing, China

Abstract

To realize the cascaded utilization of energy, improve the effective utilization of energy, and further reduce the carbon emissions of integrated energy systems a robust stochastic low-carbon optimal dispatch model with economy, environmental protection and reliability is developed for a park-integrated energy system wherein the multiple uncertainties brought by source and load are fully considered. First, a two-stage robust optimization algorithm is employed to handle uncertain wind power generation. A multi-case analysis method for the uncertainties of photovoltaics and load is proposed based on an improved centralized reduction algorithm. Then, considering the depreciation of the weighted average of the comprehensive operation cost, carbon emissions, and energy undersupply rate, a robust stochastic optimal dispatch model can be derived and efficiently solved by using a multi-objective fuzzy optimization algorithm with an improved membership function. Finally, by comparing the four cases, the simulation results show that the computational complexity and calculation time of the system can be reduced, the trimming result errors can be decreased, and a balance between economy, environmental protection, reliability, and robustness can be achieved.

1 Introduction

Nowadays, power industry is continuously optimizing its energy structure in response to the national “carbon emission reduction.” Renewable energy is becoming increasingly prevalent because of its low pollutant emissions and sustainable supply (; ; ; ; ). However, renewable energy also has shortcomings, such as its random nature and fluctuations, which pose significant challenges to the safety and stability of park-integrated energy system (PIES). Although related research on energy output and load forecasting has improved (; ; ; ; ; ), the uncertainty remains a significant issue in system dispatch.

Over the past few decades, numerous studies have been conducted on the optimal low-carbon dispatch of PIES. By introducing power-to-gas (P2G) equipment into the system, the effectiveness of P2G technology in the PIES for wind power consumption was verified in (). In (), a refined model of P2G operation was established, and an electricity hydrogen storage system (P2HSS) was constructed; the simulation results showed that the P2HSS could reduce the system carbon emissions and achieve better performance. Carbon trading was taken as a tool utilizing market mechanisms to effectively reduce carbon emissions (). In (), the authors discussed the influence of carbon trading price on system operation. A stepped carbon-trading mechanism was introduced into PIES in (; ), where electricity hydrogen production was completely considered. In (), an optimal dispatch model containing a combined cooling, heating, electricity unit, and carbon capture device was proposed, in which the demand response could help to flexibly shift the load and reduce carbon emissions. In (), a novel stepped carbon-trading model was constructed by introducing rewards and punishments. In (), a low-carbon dispatch model for PIES was developed considering whole-life carbon emissions. However, most of the existing results are deterministic models, and low-carbon optimal dispatch under the influence of multiple source- and load-related uncertainties is rarely considered.

For these uncertainties in load prediction and energy output in PIES optimal operation, case analysis, robust optimization, and fuzzy theory have been adopted (; ; ). In (), an interval optimal model under multiple uncertainty conditions was established and the simulation results showed that the number of optimal intervals gradually increased with an increase in the degree of uncertainty fluctuation. In (), the characteristics of the prediction error of wind power and photovoltaic (PV) were analyzed in advance and a robust optimal model considering the prediction errors was provided. A Gaussian process regression method was used to determine the probability distributions of renewable energy and load forecasts, and a min-max rolling optimal model was established in (). In (), the normal probability density function was used to describe the uncertainty of the load. In (), soyster robust was utilized to handle the uncertainty of photovoltaic and load, and the worst-case scenario was selected as the related output. To reduce the conservatism of robust optimization, a two-stage robust model was proposed, and its effectiveness in improving the system economy and robustness was analyzed in (). The Monte Carlo analysis was used to generate cases of uncertainty in (). These studies used a single method, and the characteristics of the uncertainty factors were rarely combinatorically optimized.

In terms of case analysis, wind power output and load cases were combined to obtain integrated cases and their probabilities (). In (), a risk aversion dispatch strategy was developed with a minimum objective of the conditional value at risk. The number of integrated cases in (; ; ) increased exponentially when the number of uncertain variables increased, which significantly increased the system complexity and computation time. In (), an overall case generation and reduction method was proposed with the purpose of reducing the tediousness of operations; however, the influence of each uncertain variable on the reduction process was not considered, thereby increasing the error of the reduction results and easily leading to a single correlation.

The authors primarily focused on a robust stochastic low-carbon optimal dispatch of PIES with multiple uncertainties. The main contributions and novelty are presented as follows.

  • (1) For uncertain wind power output, a two-stage robust min-max-min optimization algorithm is utilized, and a multi-case analysis method based on an improved centralized case reduction is proposed. To handle the uncertainty of photovoltaic and load. The combination of the two methods reduces the conservatism of the robust optimization method.

  • (2) By introducing the stepped carbon trading mechanism, a robust stochastic low-carbon optimal dispatch method for PIES is constructed with economy, environmental protection and reliability indicator, which is solved using a multi-objective fuzzy optimization algorithm with an improved membership function. This enables the system to achieve comprehensive operation while reducing the subjectivity of setting multiple objective weights.

The remaining of the manuscript is arranged as: In Section 2, the structure of the PIES is described first, and then uncertain models for the load and PV are provided. In Section 3, the development of a robust stochastic low-carbon optimal dispatch strategy of the PIES and a detailed solution process are presented. In Section 4, a case study and comparison analysis are presented to demonstrate the effectiveness of the proposed model. Finally, the paper concludes with a discussion on future research.

2 System description

2.1 Structure of PIES

A diagram of the proposed PIES is presented in Figure 1. In terms of energy production, upper-level power grid, gas network, and photovoltaic PV and wind turbine (WT) unit are available. The energy conversion components include combined heat and power (CHP) unit, gas boiler (GB), electric chiller (EC), absorption chiller (AC), electrolyzer (EL), methane reactor (MR), hydrogen fuel cell (HFC), and multi-energy storage device. The energy outputs include the cooling, heat, electricity, and gas load. The carbon emissions generated by the PIES are ultimately traded in the carbon trading market.

FIGURE 1

2.2 Mechanism of stepped carbon trading

To reduce greenhouse gas emissions, a carbon emission trading mechanism is developed as an effective approach. The stepped carbon trading mechanism is a flexible market-based approach to reducing carbon emissions. According to its mechanism: carbon emission reduction targets are divided into different tiers, and participants are rewarded by reaching or exceeding the goals of each tier. The mechanism includes carbon quota allocation, carbon trading and reward and punishment mechanism, which encourages enterprises and organizations to adopt innovative emission reduction measures to promote low-carbon economic development and achieve sustainable development goals.

The carbon emission sources considered in this study include purchasing electricity from the grid, CHP, GB, and gas load. The hydrogen conversion process of methane reactors can absorb some CO2, which is primarily consumed through the combustion of gases such as coal and natural gas, resulting in carbon emissions that need to be considered ().

2.3 Model of wind power with uncertainty

It is well known that wind power output is challenging to characterize accurately in real-world cases owing to various factors, such as wind speed and geographical location. However, obtaining a range of output values is relatively straightforward. Therefore, a boxing interval set is used to describe the uncertainty caused by wind power. A robust uncertainty adjustment parameter is employed to adjust the conservatism, a larger parameter results in more conservative solution. Conversely, a smaller parameter leads to more liberal the solution. The range of values includes integers within [0, T], where T represents the total number of periods during the dispatch cycle. The wind power reaches the described fluctuation interval that is expressed as:where and are the actual and predicted wind power generation, respectively. and are upward and downward fluctuating state variables, respectively. is the predicted deviation in wind power generation. is the dispatch period.

2.4 Multi-case model of uncertainties of PV and load

The predicted values of PV generation, cooling, heating, electricity, and gas load deviate. In this study, the actual values are taken as the sum of the predicted values and deviations, which are expressed as:where and are the actual and predicted PV generation for the case, respectively. is the predicted deviation of PV generation. and are the actual and predicted load for the case, respectively. is the predicted deviation of load.

Without a loss of generality, in this study, photovoltaic generation and load are assumed to follow a normal distribution, and the basic parameters are given as:where and are the mean values of PV generation and load for the case, respectively. and are the standard deviation of load output and load for the case, respectively. is the rated capacity of PV unit.

For these uncertainties introduced by photovoltaic power output and load, the corresponding samples are generated through random sampling based on their probability distributions. In this study, the Latin hypercube sampling (LHS) is adopted, which ensures that the samples encompass the entire sample space of the random variable; detailed procedures can be found in () and are excluded in this paper.

3 Robust stochastic low-carbon optimal dispatch model of PIES

Considering the uncertainties from sources and loads, a robust stochastic low-carbon optimal dispatch model is developed for the PIES. The model is divided into two stages: First, the multi-case analysis and multi-objective fuzzy optimization algorithm with an improved membership function are used to obtain the energy storage charging and discharging plan, grid interaction plan, and energy storage equipment output plan. Next, the robust min-max-min optimization algorithm is employed to minimize the energy purchase cost in the worst-case scenario. The proposed robust stochastic low-carbon optimal dispatch model is given bywhere is the number of typical cases. is the probability of occurrence of typical cases. , , , , and are the energy purchase cost, operation and maintenance cost, carbon trading cost, carbon emission, and energy undersupply rate of typical cases, respectively. is a function of multi-objective fuzzy optimization satisfaction. is the first-stage optimization variable, including the energy storage charging and discharging plan, grid interaction plan, and energy storage equipment output plan. is a second-stage optimization variable that includes the unit output and grid interaction. is a set of uncertainties in wind power generation.

3.1 Objective function

For a typical case of photovoltaic and load case, the objective function is described in detail to develop a robust stochastic low-carbon optimal dispatch model for PIES.

The first objective is to obtain the minimum operational cost within a dispatch period:where denotes the comprehensive operational cost. represents carbon trading cost. and represent the system energy purchase cost and the operation and maintenance cost, respectively; these can be expressed as:where and are the electricity purchase price and gas purchase price at time , respectively. is the electricity selling price. is the power purchased at time . is the purchasing power of gas at time . is the selling power at time . is the actual PV generation at . is the natural gas power input to the CHP system at time . is the natural gas power input to the GB at time . is the electric power input to EL. is the hydrogen energy input to the MR. is the hydrogen energy input to the HFC. is the electrical power input to the EC. is the heat power input to the AC. and are the charging and discharging powers of the energy storage device, respectively.

The second objective is to achieve minimal total carbon dioxide emissions, which are expressed as follows:where is the total carbon emissions, is the carbon emissions caused by purchased power, is the carbon emissions caused by gas load, is the total carbon emissions from the CHP and GB, and is the amount of CO2 absorbed by the MR hydrogen into natural gas. Detailed descriptions are as follows:where and are the electricity and heat power outputs of the CHP system, respectively. is the heat power output of the GB. is the sum of the power output of the CHP system and GB. , , and , , and are the carbon emission factors of the CHP and GB coal-fired units, respectively. is the CO2 absorption parameter of the hydrogen-to-natural gas conversion process in the MR equipment. is the natural-gas power output of the MR.

The third objective is the energy undersupply rate of system, which is shown aswhere is the energy undersupply rate, which refers to a supply shortage when the electrical input and gas input suddenly drop to 50% of the original amount. is the electricity load at time . is the heat load at time . is the gas load at time . is the cooling load at time . , , , are the shortages of supply for the electricity, heat, gas, and cooling load, respectively.

3.2 Constraints

  • (1) Wind turbine (WT) output constraints

where

is the rated power of WT unit during the

period.

  • (2) PV generation constraints

where

is the predicted PV power generation during the

period.

is the rated power of the PV unit during the

period.

  • (3) CHP constraints

where

and

are the energy conversion efficiencies of CHP electricity and heat power, respectively.

and

are the upper and lower limits of the natural gas power input to the CHP system, respectively.

and

are the upper and lower limits of the natural gas power creep input to the CHP system, respectively.

  • (4) GB constraints

where

is the energy conversion efficiency.

and

are the upper and lower limits of the natural gas power input to the GB, respectively.

and

are the upper and lower limits of the natural gas power creep input to the GB, respectively.

  • (5) EL constraints

where

is the hydrogen energy output from EL and

is the energy conversion efficiency.

and

are the upper and lower limits of the electric power input to the EL, respectively.

and

are the upper and lower limits of the electric power creep of the input to the EL, respectively.

  • (6) MR constraints

where

is the energy conversion efficiency of the MR.

and

are the upper and lower limits of the hydrogen energy input to the MR, respectively.

and

are the upper and lower limits of the hydrogen energy-climbing input to the MR, respectively.

  • (7) HFC constraints

where

and

are the electricity and heat power outputs of the HFC, respectively.

and

are the energy conversion efficiencies of the electricity and heat power of the HFC, respectively.

and

are the upper and lower limits of the hydrogen energy input to the HFC, respectively.

and

are the upper and lower limits of the hydrogen energy creep of the input to the HFC, respectively.

  • (8) EC constraints

where

is the cooling power output of the EC.

is the energy conversion efficiency.

and

are the upper and lower limits of the electrical power of the input EC, respectively.

and

are the upper and lower limits of the electrical power creep of the input EC, respectively.

  • (9) AC constraints

where

is the cooling power output of AC.

is the energy conversion efficiency.

and

are the upper and lower limits of the heat power of the input AC.

and

are the upper and lower limits of the heat-power creep of the input AC, respectively.

  • (10) Energy storage device constraints

where

is the type of energy, and

.

are electricity, heat, gas, hydrogen and cold energy, respectively.

is the capacity of the

energy-storage device.

and

are the upper and lower capacity limits of the

energy storage device, respectively.

and

are the charging and discharging efficiencies of the

energy-storage device, respectively.

and

are the charging and discharging 0–1 state variable of the

energy storage device, respectively.

and

are the maximum power of the

energy storage device, respectively.

  • (11) Power balance constraints

where

and

are the upper limits of the electricity selling and purchasing through the upper-level grid during the

period, respectively. The upper limit of electricity purchasing

is set to 3500 kW.

and

are both 0-1 variables. When

= 1, it indicates that PIES purchases electricity from the upper-level grid. When

= 1, it indicates that PIES sells electricity to the upper-level grid.

  • (12) Heat balance constraints

  • (13) Gas balance constraints

where

is the limit for purchasing gas from the upper-level gas grid. The upper limit of gas purchasing

is set to 3000 kW.

  • (14) Hydrogen balance constraints

  • (15) Cooling balance constraints

3.3 Solution to optimal model

The number of typical scenes generated by the traditional centralized reduction method is artificially adjustable, which can reduce computational complexity. However, it does not consider the impact of various uncertain variables such as dimensions and value ranges on the typical scene set and probability obtained through centralized reduction. Therefore, an improved centralized reduction method is proposed to handle sampled scene sets. For the developed optimal dispatch model, Latin hypercube sampling is adopted for scene generation, and because its initial scene set is large, an improved centralized reduction approach is developed to process the sampling scene set. In this method, the uncertain variables are sampled using a Latin hypercube. The obtained scene set is then normalized. The system sampling scene set under the improved centralized reduction method is combined. Finally, the heuristic synchronous back-substitution method is used to improve and reduce the typical scene set and its probability, which is expressed as:where is the number of sampled cases. denotes the number of reduction target cases. represents the set of cases sampled by the improved centralized reduction method. , , , , , , , , , and are the maximal and minimal values of power concentration of the sampled cases generated by PV and load, respectively. is the typical case and its probability obtained by the improved centralized reduction method.

An evaluation index called the comprehensive probability distance (CPD) is proposed to evaluate the performance of the proposed reduction strategy:where means Euclidean distance between case and case .

It is noteworthy that the min-max-min structure in a robust stochastic low-carbon optimal dispatch model cannot be solved directly. Therefore, the algorithm of column and constraint generation algorithm (CCG) is employed to decompose the main problem and sub-problem and solve them alternately; the large M method and duality theory can be used to transform the sub-problem into a single objective optimization issue, and a more detailed description can be found in (), which is excluded here owing to the length-limit of the paper.

Furthermore, a new multi-objective fuzzy optimization algorithm with an improved membership function is developed, in which a continuously differentiable inverse sigmoid function in the definition domain is adopted. Based on the maximum and minimum satisfaction approaches, the minimum value of the three objective membership functions is set as satisfaction, and a single objective issue that satisfies all constraints and maximum satisfaction was derived ().

The main steps of the proposed optimization model are as follows.

Step 1The predicted values of the cooling, heat, electricity, gas loads, and PV generation are input and a large number of sample cases is generated using Latin hypercube sampling, which conformed to the corresponding probability distribution.

Step 2A small number of typical representative scenes and their probabilities are obtained using a heuristic synchronous back-substitution method.

Step 3A two-stage robust min-max-min optimization algorithm is developed to deal with the uncertainty of wind power. Typical cases are substituted into the model to build a robust stochastic low-carbon optimal dispatch model based on system equipment parameters and system structure.

Step 4The fuzzy multi-objective optimization algorithm with an improved membership function is used to obtain the solution. A commercial solver, Gurobi, is employed based on Matlab 2020a.The flow of the proposed optimization approach is illustrated in Figure 2.

FIGURE 2

4 Case study

4.1 Basic data

In this study, the optimal dispatch period is 24 h. The multidimensional load, the predicted output of wind and PV power in the PIES, and the purchase and sale prices of electricity at different times are illustrated in Figures 35. The natural gas price is set to 0.35 yuan/(kWh). Table 1 lists the basic parameter settings for each device, and Table 2 lists the parameter settings for each energy storage device. The carbon emission quota for unit power generation is set to 0.798 kg/(kWh). The carbon emission quota for the unit heat supply is set as 0.385 kg/(kWh) (). The interval length of the stepped carbon trading mechanism was set to 2000 kg. Based on the data from (), the price increase rate is set to 25% and the base price of carbon trading is set to 0.252 yuan/kg.

FIGURE 3

FIGURE 4

FIGURE 5

TABLE 1

NameCapacity/kWEfficiency (%)Upper limit of climbing speed/(kW·h-1)Lower limit of climbing speed/(kW·h-1)
CHP1,50030(electricity)/40(heat)300−300
GB4009580−80
EL50087100−100
MR4356087−87
HFC43535(electricity)/60(heat)87−87

Equipment parameters.

TABLE 2

NameCapacity/kWLower limit of capacity/kWLower limit of capacity/kWUpper limit of climbing speed/(kW·h-1)Lower limit of climbing speed/(kW·h-1)
Electricity storage tank4504540590−90
Heat storage tank50050450100−100
Gas storage tank1501513530−30
Hydrogen storage tank2002018040−40
Cooling storage tank3003027060−60

Energy storage parameters.

Using the proposed method, a set of 1,000 sampled cases is generated, as shown in Figure 6. The sampled case set contains 1,000 × 120 data points, representing the size of the PV generation and the load of cooling, heat, electricity, and gas at every hour. A synchronous back-substitution method is adopted to improve and reduce the 1,000 scene sets. Eight typical scenes and their probabilities are shown in Figure 7.

FIGURE 6

FIGURE 7

To further demonstrate the performance of the improved case reduction method, the results are compared with those obtained by separate reduction and traditional centralized reduction with CPD. A comparison of the results is presented in Table 3; Figure 8.

TABLE 3

ProgramsCPDLength of interval
Separate reductionTraditional centralized reductionImproved centralized reduction
PV1,013.29269.46675.56336.0515
Electricity load1993.171,425.131,281.10904.64
Heat load1725.391,186.971,227.66544.56
Gas load561.84154.02384.22241.67
Cooling load1,189.53992.39378.06815.68

Evaluation results of different reduction methods.

The bold values represent the optimization scheduling results of the model proposed in this paper.

FIGURE 8

From Table 3; Figure 8, the CPD of each uncertain variable is found to be more significant than that of centralized reduction and improved centralized reduction using the separate reduction method, because the heuristic synchronous backtracking algorithm calculates the probability distance between each scene in the generated scene set and the rest of the scenes. The scene pair with the smallest probability distance is selected and reduced by adding the probability of one scene to the other. This process was repeated until the number of scenes is reduced to one or fewer. As the number of scenes decreases, the CPD of the remaining scene pairs becomes the maximum CPD value for the same number of scene pairs in the original scene set.

For the traditional centralized reduction and improved centralized reduction methods, the CPD of the gas load is smaller when using the improved centralized reduction, while the CPDs of the electrical load and cooling load are larger when using the traditional centralized reduction because the value ranges of the photovoltaic, heat load, and gas load are relatively small, and the value ranges of the electric load and cooling load are relatively large. The traditional centralized reduction method has a greater impact on the probability distance of the scene set in the reduction process owing to the relatively large value ranges of the electric and cooling loads. The reduction process is more correlated with the electric and cooling loads; therefore, the reduction is more inclined to be conducted according to the trend of separate reduction of the electric and cooling loads. Therefore, the difference between the CPD under the traditional centralized reduction mode of the electric load and cooling load, and the CPD under the separate reduction mode is smaller. After adopting the improved centralized reduction mode, the uncertain variables in the scene set are normalized to obtain the normalized scene set, which significantly reduced the influence of the length of the value range of the uncertain variables on the reduction process. Simultaneously, the dimensionality of the uncertain variables can be eliminated. The influences of different variables on the reduction process are more balanced. Therefore, with the increase in the CPD of photovoltaic, heat load, and gas load, the correlation of the reduction process can be improved such that the error of the reduction result is reduced and a single correlation of the reduction result is avoided.

4.2 Analysis of simulation results

In this section, the advantages of a multi-objective low-carbon optimal PIES in terms of economic and environmental protection and reliability are discussed. Without loss of generality, the load demand and wind and PV power outputs are considered as the predicted values. The following four models were constructed with different objectives.

Model 1PIES economic model to minimize optimal comprehensive operation cost.

Model 2PIES low carbon model to minimize carbon emissions.

Model 3PIES reliability model to minimize the energy undersupply rate.

Model 4PIES multi-objective low-carbon optimal dispatch model considering economic and environmental protection and reliability indicator.The optimization results are summarized in Table 4. Table 4 demonstrates that the carbon emissions of the PIES are 13.21% higher than the minimum emissions, and the energy undersupply rate is 12.47% higher. The system cost is 12.71% higher than the optimal economic cost. The energy undersupply rate is 24.48% higher. The energy undersupply rate is the lowest, and the system cost is 31.22% higher. The carbon emission is 49.38% higher. Compared with the single economic objective, the carbon emissions and energy undersupply rate increased by 3.30% and decreased by 3.60%, respectively. Compared with the single carbon emission objective, the system cost and energy undersupply rate decrease by 2.07% and 12.89%, respectively. Compared with the single minimum energy undersupply rate objective, the system cost reduces by 15.88%, and carbon emissions reduce by 21.71%, which is more suitable for meeting the engineering requirements.Figure 9 shows the optimal results for Model 1. Wind power resources are abundant whereas the electric load is relatively low at 1:00–7:00 and 23:00–24:00. To absorb abundant wind power and promote economic operations, surplus wind power is sold through a higher-level power grid. Some part of it is input into the EL equipment for hydrogen production. Hydrogen is the first input into HFC because of its high energy-conversion efficiency. The remaining hydrogen is converted into natural gas via the MR or stored in a hydrogen storage tank. When energy prices are high, wind power generation is low at 8:00–22:00. The system mainly satisfies its electricity and heat-load demand through the CHP output, thereby reducing the system operation cost.Figure 10 shows the optimal results for Model 2. The system relies on CHP to meet its load requirements of the electricity and heat throughout the day, compared to when the system operates in the economically optimal mode. When the economic objective is pursued, a portion of the abundant wind power is consumed by inputting the EL equipment for hydrogen production. Hydrogen can be used by HFC to output a large amount of electricity and heat, thereby improving the operating economy of the system. When carbon emissions are minimized, the system sells all surplus wind power through the higher-level power grid; thus, carbon emissions can be reduced. This is because the factor of carbon emission for purchased electricity is higher, resulting in all surplus wind power being sold in Model 2.Figure 11 shows the optimal results for Model 3. Compared to the system in the economically optimal mode and the carbon emissions minimum mode, the surplus wind power is entirely consumed using the EL device for hydrogen production. A large amount of electricity and heat power are generated using HFC. However, owing to equipment capacity limitations, more than one HFC thermal power generation is required to satisfy the load demand. Therefore, the system relies primarily on a upper-level grid to satisfy its electricity load demand. A small number of CHP units are used to satisfy the heat demand. When the goal is to minimize the energy undersupply rate, the average energy conversion efficiency of the power-consuming units is higher than that of the gas-consuming units. Therefore, when the system needs to meet the same load demand, it must purchase less electricity than gas. To meet the electricity load demand, it tends to purchase electricity from the upper-level grid and meet the heat-load demand of the system using HFC. This reduces the output of the CHP units and causes a decrease in the purchase of gas by the system from the upper-level gas grid and a lower dependence on external energy purchases. Consequently, the operational reliability of the system improves.Figure 12 shows the optimal results for Model 4. Compared with Models 1, 2, and 3, Model 4 comprehensively considers the multi-energy complementarity and collaborative optimization of wind power hydrogen production, CHP, and other equipment; it completely utilizes the existing wind and photovoltaic resources, interacts with external energy prices, such as time-of-use electricity and gas prices, and balances the three indicators of economic and environmental protection and reliability to obtain the optimal dispatch plan.

TABLE 4

Single objectiveSingle-objective optimization resultsMulti-objective fuzzy optimization results
Comprehensive operation cost/CNYCarbon emissions/kgEnergy undersupply rate/%
Comprehensive operation cost/CNY20475.123077.126866.322599.5
Carbon emissions/kg16784.014825.522146.517338.2
Energy undersupply rate%38.0542.1133.8336.68

Multi-objective results of different dispatch models.

The bold values represent the optimization scheduling results of the model proposed in this paper.

FIGURE 9

FIGURE 10

FIGURE 11

FIGURE 12

4.3 Comparison of optimal models

In this subsection, four cases are presented. Additionally, the comparison of the advantages of the robust stochastic optimization model and its verification are explained.

Case 1Source and load uncertainty are not considered;

Case 2A multi-case analysis method is utilized for the uncertainties from the source and load.

Case 3A two-stage robust optimization algorithm is utilized for source and load uncertainties.

Case 4A two-stage robust optimization algorithm is employed for the uncertain wind power output, and a multi-case analysis method is used for the uncertainty of the photovoltaic output and load.The comparison results of the different cases are listed in Table 5. In Case 1, uncertainty is considered; therefore, the results of the comprehensive operation cost and carbon emissions are the best, while the energy undersupply rate is not reliable. The worst case for each uncertain variable is considered in Case 3 to maximize the multi-objective result. The proposed robust stochastic optimization method represents the actual operation situation. Multi-objective results are obtained between those of Cases 1 and 3. Thus, the method improves the shortcomings of the over-conservative two-stage robustness and has more reference values.

TABLE 5

CasesMulti-objective fuzzy optimization results
Comprehensive operation cost/CNYCarbon emissions/kgEnergy undersupply rate/%
122599.517338.236.68
223311.618369.237.84
323904.018753.338.28
422839.717842.337.22

Multi-objective results of different cases.

The bold values represent the optimization scheduling results of the model proposed in this paper.

5 Conclusion

In this study, a robust stochastic low-carbon optimal dispatch strategy for PIES was constructed with economy and environmental protection and reliability factor, in which the uncertain source load factors were entirely considered and a stepped carbon-trading mechanism was introduced with multiple objectives. The optimal dispatch scheme was solved under the worst wind power cases by using a two-stage robust min-max-min optimization algorithm, with a focus on the uncertain wind power. A multi-scene analysis based on improved centralized reduction was proposed, which reasonably considered the impact of uncertain variables on the reduction process for photovoltaic and load uncertainty, compared to separate reduction and traditional concentrated reduction. Finally, a multi-objective fuzzy optimization algorithm with an improved membership function was adopted to solve the multi-objective optimal dispatch model, which can reduce the subjectivity of multi-objective weights to some extent. The simulation results demonstrated the usefulness and effectiveness of the proposed method, which could provide a reference for future applications of the PIES.

However, it should be pointed out that the proposed method in this paper still has certain subjectivity and conservatism. Therefore, in the future, some interesting research topics, such as further reducing conservatism by using distributed robust methods, further weaking the subjectivity of selecting the multi-objective weight and establish a more refined model, etc., which are some ongoing research directions.

Statements

Data availability statement

The original contributions presented in the study are included in the article/Supplementary material, further inquiries can be directed to the corresponding author.

Author contributions

XZ: Building models and simulation analysis. SZ and HZ: Literature collection and drafting. XD: Reviewing and editing. All authors contributed to the article and approved the submitted version.

Funding

This work is supported by the Science and Technology Project of State Grid Jiangsu Electric Power Co., LTD. (No. J2021191).

Acknowledgments

The authors would express their appreciation for the project for the contribution of the research fund. The authors would also like to acknowledge the reviewers for their constructive comments and careful revision of this paper.

Conflict of interest

XZ, SZ, and HZ was employed by State Grid Jiangsu Electric Power Co., Ltd.

The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Correction note

This article has been corrected with minor changes. These changes do not impact the scientific content of the article.

Publisher’s note

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article, or claim that may be made by its manufacturer, is not guaranteed or endorsed by the publisher.

References

  • 1

    AlabiT. M.AgbajorF. D.YangZ.LuL.OgungbileA. J. (2022). Strategic potential of multi-energy system towards carbon neutrality: A forward-looking overview. Energy Built Environ.4, 689708. 10.1016/j.enbenv.2022.06.007

  • 2

    CuiD.GeW.ZhaoW.JiangF.ZhangY. (2022). Economic low-carbon clean dispatching of power system containing P2G considering the comprehensive influence of multi-price factor. J. Electr. Eng. Technol.17, 155166. 10.1007/s42835-021-00877-4

  • 3

    Di SommaM.GraditiG.Heydarian-ForushaniE.Shafie-khahM.SianoP. (2017). Stochastic optimal scheduling of distributed energy resources with renewables considering economic and environmental aspects. Renew. Energy116, 272287. 10.1016/j.renene.2017.09.074

  • 4

    DongX.ZhangC.SunB. (2022). Optimization strategy based on robust model predictive control for RES-CCHP system under multiple uncertainties. Appl. Energy325, 119707. 10.1016/j.apenergy.2022.119707

  • 5

    GaoJ.YangY.GaoF.WuH. (2022). Two-stage robust economic dispatch of regional integrated energy system considering source-load uncertainty based on carbon neutral vision. Energies15, 1596. 10.3390/en15041596

  • 6

    HuangN.WangS.WangR.CaiG.LiuY.DaiQ. (2023). Gated spatial-temporal graph neural network based short-term load forecasting for wide-area multiple buses. Int. J. Electr. Power & Energy Syst.145, 108651. 10.1016/j.ijepes.2022.108651

  • 7

    LiH.YeY.LinL. (2021b). Low-carbon economic bi-level optimal dispatching of an integrated power and natural gas energy system considering carbon trading. Appl. Sciences-Basel.11, 6968. 10.3390/app11156968

  • 8

    LiY.TangF.GaoX.ZhangT.QiJ.XieJ.et al (2021a). Numerical weather prediction correction strategy for short-term wind power forecasting based on bidirectional gated recurrent unit and XGBoost. Front. Energy Res.9, 836144. 10.3389/fenrg.2021.836144

  • 9

    LiY.WangK.GaoB.ZhangB.LiuX.ChenC. (2021c). Interval optimization based operational strategy of integrated energy system under renewable energy resources and loads uncertainties. Int. J. Energy Res.45, 31423156. 10.1002/er.6009

  • 10

    LiuX. (2022). Research on optimal placement of low-carbon equipment capacity in integrated energy system considering carbon emission and carbon trading. Int. J. Energy Res.46, 2053520555. 10.1002/er.7826

  • 11

    MaZ.YangM.JiaW.DingT. (2022). Decentralized robust optimal dispatch of user-level integrated electricity-gas-heat systems considering two-level integrated demand response. Front. Energy Res.10. 10.3389/fenrg.2022.1030496

  • 12

    MahdaviM.AlhelouH. H.SianoP.LoiaV. (2022). Robust mixed-integer programing model for reconfiguration of distribution feeders under uncertain and variable loads considering capacitor banks, voltage regulators, and protective relays. IEEE Trans. Ind. Inf.18, 77907803. 10.1109/TII.2022.3141412

  • 13

    QiN.ChengL.LiH.ZhaoY.TianH. (2023). Portfolio optimization of generic energy storage-based virtual power plant under decision-dependent uncertainties. J. Energy Storage63, 107000. 10.1016/j.est.2023.107000

  • 14

    QiX.HanY. (2023). Research on the evolutionary strategy of carbon market under “dual carbon” goal: From the perspective of dynamic quota allocation. Energy274, 127265. 10.1016/j.energy.2023.127265

  • 15

    QinG.YanQ.KammenD. M.ShiC.XuC. (2022). Robust optimal dispatching of integrated electricity and gas system considering refined power-to-gas model under the dual carbon target. J. Clean. Prod.371, 133451. 10.1016/j.jclepro.2022.133451

  • 16

    SunP.HaoX.WangJ.ShenD.TianL. (2021b). Low-carbon economic operation for integrated energy system considering carbon trading mechanism. Energy Sci. Eng.9, 20642078. 10.1002/ese3.967

  • 17

    SunY.WuX.WangJ.HouD.WangS. (2021a). Power compensation of network losses in a microgrid with BESS by distributed consensus algorithm. IEEE Trans. Syst. Man, Cybern. Syst.51, 20912100. 10.1109/TSMC.2020.2968605

  • 18

    SunY.ZhouY.WangS.MahfoudR. J.AlhelouH. H.SideratosG.et al (2023). Nonparametric probabilistic prediction of regional PV outputs based on granule-based clustering and direct optimization programming. J. Mod. Power Syst. Clean Energy11 (5), 14501461. 10.35833/MPCE.2022.000577

  • 19

    TangY.TangZ.GaoY.WeiL.ZhouJ.HanF.et al (2022). An adaptive forecasting method for the aggregated load with pattern matching. Front. Energy Res.10. 10.3389/fenrg.2022.1088100

  • 20

    WangF.LvC.XuJ. (2023a). Carbon awareness oriented data center location and configuration: An integrated optimization method. Energy278, 127744. 10.1016/j.energy.2023.127744

  • 21

    WangG.ZhouF.LiP.WangZ. (2019). “Optimal operation analysis of integrated community energy system considering source-load uncertainty,” in Proceedings of 2019 IEEE 3RD International Electrical and Energy Conference, Beijing, China, September 2019, 12171222. 10.1109/CIEEC47146.2019

  • 22

    WangL.DongH.LinJ.ZengM. (2022). Multi-objective optimal scheduling model with IGDT method of integrated energy system considering ladder-type carbon trading mechanism. Int. J. Electr. Power & Energy Syst.143, 108386. 10.1016/j.ijepes.2022.108386

  • 23

    WangS.SunY.ZhangS.ZhouY.HouD.WangJ. (2023b). Very short-term probabilistic prediction of PV based on multi-period error distribution. Electr. Power Syst. Res.214, 108817. 10.1016/j.epsr.2022.108817

  • 24

    XieY.XuY. (2022). Transmission expansion planning considering wind power and load uncertainties. Energies15, 7140. 10.3390/en15197140

  • 25

    XiongJ.SunY.WangJ.LiZ.XuZ.ZhaiS. (2022). Multi-stage equipment optimal configuration of park-level integrated energy system considering flexible loads. Int. J. Electr. Power Energy Syst.140, 112. 10.1016/j.ijepes.2022.108050

  • 26

    YanL.ZhaoY.XueT.MaN.LiZ.YanZ. (2022). Two-layer optimal operation of AC-DC hybrid microgrid considering carbon emissions trading in multiple scenarios. Sustainability14, 10524. 10.3390/su141710524

  • 27

    YangP.JiangH.LiuC.KangL.WangC. (2023). Coordinated optimization scheduling operation of integrated energy system considering demand response and carbon trading mechanism. Int. J. Electr. Power & Energy Syst.147, 108902. 10.1016/j.ijepes.2022.108902

  • 28

    ZengB.LiuY.XuF.LiuY.SunX.YeX. (2020). Optimal demand response resource exploitation for efficient accommodation of renewable energy sources in multi-energy systems considering correlated uncertainties. J. Clean. Prod.288, 125666. 10.1016/j.jclepro.2020.125666

  • 29

    ZhangJ.TianG.ChenX.LiuP.LiZ. (2023). A chance-constrained programming approach to optimal planning of low-carbon transition of a regional energy system. Energy278, 127813. 10.1016/j.energy.2023.127813

  • 30

    ZhangK.XuN.LingY.ZhouB.SongY. (2022a). Economic dispatch analysis of comprehensive energy system considering carbon trading. Front. Energy Res.546, 022058. 10.1088/1755-1315/546/2/022058

  • 31

    ZhangY.FuZ.XieY.HuQ.LiZ.GuoH. (2022c). A comprehensive forecasting-optimization analysis framework for environmental-oriented power system management-A case study of Harbin city, China. Sustainability12, 4272. 10.3390/su12104272

  • 32

    ZhangY.NiM.SunY. (2022b). Fully distributed economic dispatch for cyber physical power system with time delays and channel noises. J. Mod. Power Syst. Clean Energy10, 14721481. 10.35833/MPCE.2020.000847

  • 33

    ZhouW.SunY.ZongX.ZhouH.ZouS. (2023). Low-carbon economic dispatch of integrated energy system considering carbon trading mechanism and LAES-ORC-CHP System. Front. Energy Res.11, 112. 10.3389/fenrg.2023.1134221

Summary

Keywords

low carbon optimal dispatch, robust optimization, multiple uncertainties of source and load, improved centralized reduction, multi-objective fuzzy optimization

Citation

Zong X, Zou S, Zhou H and Dou X (2023) Robust stochastic low-carbon optimal dispatch of park-integrated energy system with multiple uncertainties from source and load. Front. Energy Res. 11:1226768. doi: 10.3389/fenrg.2023.1226768

Received

22 May 2023

Accepted

17 July 2023

Published

28 July 2023

Corrected

23 January 2026

Volume

11 - 2023

Edited by

Nantian Huang, Northeast Electric Power University, China

Reviewed by

Yi Wang, Zhengzhou University, China

Zhenkun Li, Shanghai University of Electric Power, China

Hassan Haes Alhelou, Tishreen University, Syria

Updates

Copyright

*Correspondence: Xuanjun Zong,

Disclaimer

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.

Outline

Figures

Cite article

Copy to clipboard


Export citation file


Share article

Article metrics